HomeMy WebLinkAbout06 2027-2031 Capital Improvement PlanTOWN OF ESTES PARK
SUMMARY OF CAPITAL IMPROVEMENT PLAN PROJECTS
BY DEPARTMENT / DIVISION
For Years Ending December 31,
Project Costs
Recap by Dept / Division 2027 2028 2029 2030 2031 Total
Community Services
Cultural Services - - - - - -
Special Events 130,000 3,990,000 - 405,578 - 4,525,578
Public Works -
Engineering - Stormwater 800,000 2,170,100 22,180,000 2,990,000 33,300,000 61,440,100
Engineering - Transportation 1,490,000 2,150,000 1,800,000 720,000 24,568,000 30,728,000
-
Parking / Transit 173,735 5,118,000 144,100 2,278,000 15,282,000 22,995,835
Parks 175,000 - - - - 175,000
Internal Services -
Facilities 34,891,865 2,802,940 1,539,250 67,812 710,325 40,012,192
-
Utilities -
Power and Communication - 2,711,387 696,771 - 707,002 4,115,160
Water - 8,245,000 85,446,600 1,071,200 5,766,250 100,529,050
Total 37,660,600 27,187,427 111,806,721 7,532,590 80,333,577 264,520,915
Attachment 6
TOWN OF ESTES PARK
SUMMARY OF CAPITAL IMPROVEMENT PLAN PROJECTS
BY DEPARTMENT / DIVISION
For Years Ending December 31,
Funding Source
Total Project
Costs Debt $
Fundraising &
Other $Federal Grant $State Grant $InKind Match
Net Town
Project Funds
Needed
Community Services
Cultural Services - - - - - - -
Special Events 4,525,578 - - 3,990,000 - - 535,578
Public Works
Engineering - Stormwater 61,440,100 - - 45,900,000 - - 15,540,100
Engineering - Transportation 30,728,000 - - 15,733,000 3,480,000 - 11,515,000
Parking / Transit 22,995,835 18,333,000 - - - - 4,662,835
Parks 175,000 - - - - - 175,000
Facilities 40,012,192 - - 34,000,000 - - 6,012,192
Utilities
Power and Communication 4,115,160 - - 1,216,648 - 102,313 2,796,199
Water 100,529,050 68,000,000 - - - - 32,529,050
Total 264,520,915 86,333,000 - 100,839,648 3,480,000 102,313 73,765,954
Recap by Dept / Division
Town of Estes Park
Summary of CIP Projects
For Year Ended 12-31-2027
Subtotals 37,660,600 27,187,427 111,806,721 7,532,590 80,333,577 264,520,915
Sheet #Dept Division Fund Project Title 2027 2028 2029 2030 2031 Total
1 CommunityServices SpecialEvents 304 Events Center Safety Lighting Improvments 130,000 - - - - 130,000
2 CommunityServices SpecialEvents 304 Events Complex Signage - - - 105,635 - 105,635
3 CommunityServices SpecialEvents 304 Highway 36/Community Drive Fencing - - - 299,943 - 299,943
4 CommunityServices SpecialEvents 304 Stall Barn Relocation and Replacement - 3,990,000 - - - 3,990,000
5 InternalServices Facilities 304 Brown Sand Tent Repair 82,500 - - - - 82,500
6 InternalServices Facilities 304 Facility Security Modernization and Enhancement - 110,000 - - - 110,000
7 InternalServices Facilities 304 Fleet Shop Addition/Extension - - 450,000 - - 450,000
8 InternalServices Facilities 304 New Public Safety (PD) Facility - Construction 34,000,000 - - - - 34,000,000
9 InternalServices Facilities 304 Riverside Public Restroom Replacement - 1,327,200 - - - 1,327,200
10 InternalServices Facilities 304 Roof Replacement (Section 5, TAO area)- - 250,000 - - 250,000
11 InternalServices Facilities 304 Roof Replacement (Above Board Room)- - 312,500 - - 312,500
12 InternalServices Facilities 304 Roof Replacement (Section 2 - Police)534,800 - - - - 534,800
13 InternalServices Facilities 304 Roof Replacement (Section 4 - Comm Dev)- 951,000 - - - 951,000
14 InternalServices Facilities 304 Streets Maintenance Shop Extension - - 310,750 - - 310,750
15 InternalServices Facilities 304 Town Hall Board Room Carpeting - - - 67,812 - 67,812
16 InternalServices Facilities 304 Town Hall Elevator Replacment and ADA Compliance - - - - 710,325 710,325
17 InternalServices Facilities 304 Town Hall Window Replacement Program (2027-2031)- 125,000 - - - 125,000
18 InternalServices Facilities 304 Visitor Center Exterior Log Support Rehabilitation - - 216,000 - - 216,000
19 InternalServices Facilities 304 Visitor Center Exterior/Interior Log Restoration and Preservation 274,565 - - - - 274,565
20 InternalServices Facilities 304 Visitor Center Restrooms Renovation - 289,740 - - - 289,740
21 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2027 - Neighborhood Drainage 800,000 - - - - 800,000
22 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Big Thompson - 1,900,000 - - - 1,900,000
23 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2029 - Big Thompson Construct - - 14,300,000 - - 14,300,000
24 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 Phase 5 - - 7,600,000 - - 7,600,000
25 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Neighborhood Drainage - 270,100 - - - 270,100
26 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 - Neighborhood Drainage - - 280,000 - - 280,000
27 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2030 - Big Thomp Bridge Design - - - 2,700,000 - 2,700,000
28 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2030 - Neighborhood Drainage - - - 290,000 - 290,000
29 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2031 - Big Thomp Bridge Replacemt - - - - 33,300,000 33,300,000
30 PublicWorks Engineering / Transportation 304 Crags Bridge Rehabilitation - - - - 645,000 645,000
31 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 2 Downtown Loop - 275,000 - - - 275,000
32 PublicWorks Engineering / Transportation 304 Downtown Wayfinding - Ph 3 - Trail System - - 300,000 - - 300,000
33 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 4 Building Mounted - - - 120,000 - 120,000
34 PublicWorks Engineering / Transportation 304 Downtown Wayfinding Phase 5- Auto Directional - - - - 570,000 570,000
35 PublicWorks Engineering / Transportation 304 Moraine Avenue Multi-Modal Improvements - - - - 19,003,000 19,003,000
36 PublicWorks Engineering / Transportation 304 N St Vrain Avenue (US36) Multi-Modal Improvements - - - - 4,350,000 4,350,000
37 PublicWorks Engineering / Transportation 246 North Saint Vrain Avenue (US36) Trail Replacement - 275,000 - - - 275,000
38 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2027 1,000,000 - - - - 1,000,000
39 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2028 - 850,000 - - - 850,000
40 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2029 - - 800,000 - - 800,000
41 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2027 120,000 - - - - 120,000
42 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2028 - 150,000 - - - 150,000
43 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2029 - - 100,000 - - 100,000
44 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 3 - 600,000 - - - 600,000
45 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 4 - - 600,000 - - 600,000
46 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 5 - - - 600,000 - 600,000
47 PublicWorks Parks 220 Children's Park Remodel, 2027 175,000 - - - - 175,000
48 PublicWorks Engineering / Transportation 246 Wonderview Ave Trail Extension 370,000 - - - - 370,000
49 PublicWorks ParkingTransit 256 Big Horn Parking Structure (Construction)- 4,950,000 - - - 4,950,000
50 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan (DPMP) - Ph. 3 - 168,000 - - - 168,000
51 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV (Construction)- - - - 15,282,000 15,282,000
52 PublicWorks ParkingTransit 256 Visitor Center Parking Garage Structure Maintenance 173,735 - - - - 173,735
53 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV Design - - - 2,278,000 - 2,278,000
54 PublicWorks ParkingTransit 256 Electric Vehicle (EV) Charging Station - - 144,100 - - 144,100
55 Utilities Power & Communications 502 P & C Building New Restrooms - 100,000 - - - 100,000
56 Utilities Power & Communications 502 Allenspark Mainline - 162,417 - - - 162,417
57 Utilities Power & Communications 502 Bellevue, Brown Trout, Big Thompson - 924,950 - - - 924,950
58 Utilities Power & Communications 502 Big Owl - 63,771 - - - 63,771
59 Utilities Power & Communications 502 Big Thompson Grid Hardening - - 500,000 - - 500,000
60 Utilities Power & Communications 502 Fish Hatchery Road - - - - 87,915 87,915
61 Utilities Power & Communications 502 Eagle Cliff - 436,663 - - - 436,663
62 Utilities Power & Communications 502 Fish Creek rd, line rebuild to tree cable - - 87,771 - - 87,771
63 Utilities Power & Communications 502 Glacier - 436,663 - - - 436,663
64 Utilities Power & Communications 502 High Drive - - - - 56,280 56,280
65 Utilities Power & Communications 502 Hwy36 - - - - 200,417 200,417
66 Utilities Power & Communications 502 Hwy 66 - 94,000 - - - 94,000
67 Utilities Power & Communications 502 Larkspur Road - - - - 112,390 112,390
68 Utilities Power & Communications 502 Mall Road Grid Hardening - - - - 250,000 250,000
69 Utilities Power & Communications 502 RMNP Fall River Rd - 116,000 - - - 116,000
70 Utilities Power & Communications 502 Rockwood lane area, Line Rebuild - 104,000 - - - 104,000
71 Utilities Power & Communications 502 Wind Cliff Three Phase - - 109,000 - - 109,000
72 Utilities Power & Communications 502 West - 147,923 - - - 147,923
73 Utilities Power & Communications 502 YMCA - 125,000 - - - 125,000
74 Utilities Water 503 16" Pipeline Crossing of Big Thompson River near C - - - - 1,370,000 1,370,000
75 Utilities Water 503 Big Horn Drive Water Main Replacement - - - 1,071,200 - 1,071,200
76 Utilities Water 503 Big Thompson Raw Water Intake - - 4,110,000 - - 4,110,000
77 Utilities Water 503 Big Thomposon Tank - 6,350,000 - - - 6,350,000
78 Utilities Water 503 Eagle Cliff - - - - 760,000 760,000
79 Utilities Water 503 Electrical Upgrades and Grounding - 310,000 - - - 310,000
80 Utilities Water 503 Fall River Estates Pump House - Structure/Capacit*- 1,585,000 - - - 1,585,000
81 Utilities Water 503 New Water Treatment Plant - - 80,800,000 - - 80,800,000
82 Utilities Water 503 Parking Garage Line Connection - - - - 352,500 352,500
83 Utilities Water 503 Strong Pumphouse Improvements - - - - 1,495,000 1,495,000
84 Utilities Water 503 Virginia Drive and East Riverside - - 536,600 - - 536,600
85 Utilities Water 503 West Elkhorn waterline replacement - - - - 1,788,750 1,788,750
-
Totals 37,660,600 27,187,427 111,806,721 7,532,590 80,333,577 264,520,915
Town of Estes Park
Summary of CIP Projects
For Year Ended 12-31-2027
Subtotals
Sheet #Dept Division Fund Project Title
1 CommunityServices SpecialEvents 304 Events Center Safety Lighting Improvments
2 CommunityServices SpecialEvents 304 Events Complex Signage
3 CommunityServices SpecialEvents 304 Highway 36/Community Drive Fencing
4 CommunityServices SpecialEvents 304 Stall Barn Relocation and Replacement
5 InternalServices Facilities 304 Brown Sand Tent Repair
6 InternalServices Facilities 304 Facility Security Modernization and Enhancement
7 InternalServices Facilities 304 Fleet Shop Addition/Extension
8 InternalServices Facilities 304 New Public Safety (PD) Facility - Construction
9 InternalServices Facilities 304 Riverside Public Restroom Replacement
10 InternalServices Facilities 304 Roof Replacement (Section 5, TAO area)
11 InternalServices Facilities 304 Roof Replacement (Above Board Room)
12 InternalServices Facilities 304 Roof Replacement (Section 2 - Police)
13 InternalServices Facilities 304 Roof Replacement (Section 4 - Comm Dev)
14 InternalServices Facilities 304 Streets Maintenance Shop Extension
15 InternalServices Facilities 304 Town Hall Board Room Carpeting
16 InternalServices Facilities 304 Town Hall Elevator Replacment and ADA Compliance
17 InternalServices Facilities 304 Town Hall Window Replacement Program (2027-2031)
18 InternalServices Facilities 304 Visitor Center Exterior Log Support Rehabilitation
19 InternalServices Facilities 304 Visitor Center Exterior/Interior Log Restoration and Preservation
20 InternalServices Facilities 304 Visitor Center Restrooms Renovation
21 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2027 - Neighborhood Drainage
22 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Big Thompson
23 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2029 - Big Thompson Construct
24 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 Phase 5
25 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Neighborhood Drainage
26 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 - Neighborhood Drainage
27 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2030 - Big Thomp Bridge Design
28 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2030 - Neighborhood Drainage
29 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2031 - Big Thomp Bridge Replacemt
30 PublicWorks Engineering / Transportation 304 Crags Bridge Rehabilitation
31 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 2 Downtown Loop
32 PublicWorks Engineering / Transportation 304 Downtown Wayfinding - Ph 3 - Trail System
33 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 4 Building Mounted
34 PublicWorks Engineering / Transportation 304 Downtown Wayfinding Phase 5- Auto Directional
35 PublicWorks Engineering / Transportation 304 Moraine Avenue Multi-Modal Improvements
36 PublicWorks Engineering / Transportation 304 N St Vrain Avenue (US36) Multi-Modal Improvements
37 PublicWorks Engineering / Transportation 246 North Saint Vrain Avenue (US36) Trail Replacement
38 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2027
39 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2028
40 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2029
41 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2027
42 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2028
43 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2029
44 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 3
45 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 4
46 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 5
47 PublicWorks Parks 220 Children's Park Remodel, 2027
48 PublicWorks Engineering / Transportation 246 Wonderview Ave Trail Extension
49 PublicWorks ParkingTransit 256 Big Horn Parking Structure (Construction)
50 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan (DPMP) - Ph. 3
51 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV (Construction)
52 PublicWorks ParkingTransit 256 Visitor Center Parking Garage Structure Maintenance
53 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV Design
54 PublicWorks ParkingTransit 256 Electric Vehicle (EV) Charging Station
55 Utilities Power & Communications 502 P & C Building New Restrooms
56 Utilities Power & Communications 502 Allenspark Mainline
57 Utilities Power & Communications 502 Bellevue, Brown Trout, Big Thompson
58 Utilities Power & Communications 502 Big Owl
59 Utilities Power & Communications 502 Big Thompson Grid Hardening
60 Utilities Power & Communications 502 Fish Hatchery Road
61 Utilities Power & Communications 502 Eagle Cliff
62 Utilities Power & Communications 502 Fish Creek rd, line rebuild to tree cable
63 Utilities Power & Communications 502 Glacier
64 Utilities Power & Communications 502 High Drive
65 Utilities Power & Communications 502 Hwy36
66 Utilities Power & Communications 502 Hwy 66
67 Utilities Power & Communications 502 Larkspur Road
86,333,000 - 100,839,648 3,480,000 102,313 73,765,954
Debt $ Fundraising &
Other $
Federal Grant $ State Grant $ In-Kind Match
with Staff Time
Net Town Funds
Needed
130,000
105,635
299,943
3,990,000 -
82,500
110,000
450,000
34,000,000 -
1,327,200
250,000
312,500
534,800
951,000
310,750
67,812
710,325
125,000
216,000
274,565
289,740
800,000
300,000 1,600,000
11,000,000 3,300,000
6,300,000 1,300,000
270,100
280,000
2,700,000
290,000
28,300,000 5,000,000
645,000
275,000
300,000
120,000
570,000
15,733,000 3,270,000
3,480,000 870,000
275,000
1,000,000
850,000
800,000
120,000
150,000
100,000
600,000
600,000
600,000
175,000
370,000
4,655,000 295,000
168,000
13,678,000 1,604,000
173,735
2,278,000
144,100
100,000
141,646 20,771 -
924,950
43,000 20,771 -
500,000
87,915 -
436,663
67,000 20,771 -
436,663
56,280 -
160,417 40,000 -
94,000 -
112,390 -
FUNDING SOURCE
68 Utilities Power & Communications 502 Mall Road Grid Hardening
69 Utilities Power & Communications 502 RMNP Fall River Rd
70 Utilities Power & Communications 502 Rockwood lane area, Line Rebuild
71 Utilities Power & Communications 502 Wind Cliff Three Phase
72 Utilities Power & Communications 502 West
73 Utilities Power & Communications 502 YMCA
74 Utilities Water 503 16" Pipeline Crossing of Big Thompson River near C
75 Utilities Water 503 Big Horn Drive Water Main Replacement
76 Utilities Water 503 Big Thompson Raw Water Intake
77 Utilities Water 503 Big Thomposon Tank
78 Utilities Water 503 Eagle Cliff
79 Utilities Water 503 Electrical Upgrades and Grounding
80 Utilities Water 503 Fall River Estates Pump House - Structure/Capacit*
81 Utilities Water 503 New Water Treatment Plant
82 Utilities Water 503 Parking Garage Line Connection
83 Utilities Water 503 Strong Pumphouse Improvements
84 Utilities Water 503 Virginia Drive and East Riverside
85 Utilities Water 503 West Elkhorn waterline replacement
Totals
250,000
116,000 -
104,000 -
109,000 -
147,923
125,000 -
1,370,000
1,071,200
4,110,000
6,350,000
760,000
310,000
1,585,000
68,000,000 12,800,000
352,500
1,495,000
536,600
1,788,750
86,333,000 - 100,839,648 3,480,000 102,313 73,765,954
Town of Estes Park
Summary of CIP Projects
For Year Ended 12-31-2027
Subtotals
Sheet #Dept Division Fund Project Title
1 CommunityServices SpecialEvents 304 Events Center Safety Lighting Improvments
2 CommunityServices SpecialEvents 304 Events Complex Signage
3 CommunityServices SpecialEvents 304 Highway 36/Community Drive Fencing
4 CommunityServices SpecialEvents 304 Stall Barn Relocation and Replacement
5 InternalServices Facilities 304 Brown Sand Tent Repair
6 InternalServices Facilities 304 Facility Security Modernization and Enhancement
7 InternalServices Facilities 304 Fleet Shop Addition/Extension
8 InternalServices Facilities 304 New Public Safety (PD) Facility - Construction
9 InternalServices Facilities 304 Riverside Public Restroom Replacement
10 InternalServices Facilities 304 Roof Replacement (Section 5, TAO area)
11 InternalServices Facilities 304 Roof Replacement (Above Board Room)
12 InternalServices Facilities 304 Roof Replacement (Section 2 - Police)
13 InternalServices Facilities 304 Roof Replacement (Section 4 - Comm Dev)
14 InternalServices Facilities 304 Streets Maintenance Shop Extension
15 InternalServices Facilities 304 Town Hall Board Room Carpeting
16 InternalServices Facilities 304 Town Hall Elevator Replacment and ADA Compliance
17 InternalServices Facilities 304 Town Hall Window Replacement Program (2027-2031)
18 InternalServices Facilities 304 Visitor Center Exterior Log Support Rehabilitation
19 InternalServices Facilities 304 Visitor Center Exterior/Interior Log Restoration and Preservation
20 InternalServices Facilities 304 Visitor Center Restrooms Renovation
21 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2027 - Neighborhood Drainage
22 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Big Thompson
23 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2029 - Big Thompson Construct
24 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 Phase 5
25 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2028 - Neighborhood Drainage
26 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2029 - Neighborhood Drainage
27 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2030 - Big Thomp Bridge Design
28 PublicWorks Engineering / Stormwater 265 Stormwater Management Program - 2030 - Neighborhood Drainage
29 PublicWorks Engineering / Stormwater 265 Stormwater Mgmt Program - 2031 - Big Thomp Bridge Replacemt
30 PublicWorks Engineering / Transportation 304 Crags Bridge Rehabilitation
31 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 2 Downtown Loop
32 PublicWorks Engineering / Transportation 304 Downtown Wayfinding - Ph 3 - Trail System
33 PublicWorks Engineering / Transportation 304 Downtown Wayfinding- Phase 4 Building Mounted
34 PublicWorks Engineering / Transportation 304 Downtown Wayfinding Phase 5- Auto Directional
35 PublicWorks Engineering / Transportation 304 Moraine Avenue Multi-Modal Improvements
36 PublicWorks Engineering / Transportation 304 N St Vrain Avenue (US36) Multi-Modal Improvements
37 PublicWorks Engineering / Transportation 246 North Saint Vrain Avenue (US36) Trail Replacement
38 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2027
39 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2028
40 PublicWorks Engineering / Transportation 260 STIP Overlay & Patch Program 2029
41 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2027
42 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2028
43 PublicWorks Engineering / Transportation 260 STIP Parking Lot Rehabilitation 2029
44 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 3
45 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 4
46 PublicWorks Engineering / Transportation 220 Trail Reconstruction US 34 and SH7 Phase 5
47 PublicWorks Parks 220 Children's Park Remodel, 2027
48 PublicWorks Engineering / Transportation 246 Wonderview Ave Trail Extension
49 PublicWorks ParkingTransit 256 Big Horn Parking Structure (Construction)
50 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan (DPMP) - Ph. 3
51 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV (Construction)
52 PublicWorks ParkingTransit 256 Visitor Center Parking Garage Structure Maintenance
53 PublicWorks ParkingTransit 256 Downtown Parking Mgmt Plan Ph. IV Design
54 PublicWorks ParkingTransit 256 Electric Vehicle (EV) Charging Station
55 Utilities Power & Communications 502 P & C Building New Restrooms
56 Utilities Power & Communications 502 Allenspark Mainline
57 Utilities Power & Communications 502 Bellevue, Brown Trout, Big Thompson
58 Utilities Power & Communications 502 Big Owl
59 Utilities Power & Communications 502 Big Thompson Grid Hardening
60 Utilities Power & Communications 502 Fish Hatchery Road
61 Utilities Power & Communications 502 Eagle Cliff
62 Utilities Power & Communications 502 Fish Creek rd, line rebuild to tree cable
63 Utilities Power & Communications 502 Glacier
64 Utilities Power & Communications 502 High Drive
65 Utilities Power & Communications 502 Hwy36
66 Utilities Power & Communications 502 Hwy 66
67 Utilities Power & Communications 502 Larkspur Road
0
- 15,147,770 1,075,000 1,545,000 3,020,000 4,662,835 12,540,100 2,796,199 32,529,050 450,000
101 204 220 246 260 256 265 502 503 612
General Fund Comm Reinvest Open Space Trails ST
Extension
Streets Parking Fund Stormwater
Fund
Pwr & Comm Water Fleet
130,000
105,635
299,943
82,500
110,000
450,000
1,327,200
250,000
312,500
534,800
951,000
310,750
67,812
710,325
125,000
216,000
274,565
289,740
800,000
1,600,000
3,300,000
1,300,000
270,100
280,000
2,700,000
290,000
3,000,000 2,000,000
645,000
275,000
300,000
120,000
570,000
3,270,000
870,000
275,000
1,000,000
850,000
800,000
120,000
150,000
100,000
300,000 300,000
300,000 300,000
300,000 300,000
175,000
370,000
295,000
168,000
1,604,000
173,735
2,278,000
144,100
100,000
924,950
500,000
436,663
436,663
FUND
68 Utilities Power & Communications 502 Mall Road Grid Hardening
69 Utilities Power & Communications 502 RMNP Fall River Rd
70 Utilities Power & Communications 502 Rockwood lane area, Line Rebuild
71 Utilities Power & Communications 502 Wind Cliff Three Phase
72 Utilities Power & Communications 502 West
73 Utilities Power & Communications 502 YMCA
74 Utilities Water 503 16" Pipeline Crossing of Big Thompson River near C
75 Utilities Water 503 Big Horn Drive Water Main Replacement
76 Utilities Water 503 Big Thompson Raw Water Intake
77 Utilities Water 503 Big Thomposon Tank
78 Utilities Water 503 Eagle Cliff
79 Utilities Water 503 Electrical Upgrades and Grounding
80 Utilities Water 503 Fall River Estates Pump House - Structure/Capacit*
81 Utilities Water 503 New Water Treatment Plant
82 Utilities Water 503 Parking Garage Line Connection
83 Utilities Water 503 Strong Pumphouse Improvements
84 Utilities Water 503 Virginia Drive and East Riverside
85 Utilities Water 503 West Elkhorn waterline replacement
Totals
250,000
147,923
1,370,000
1,071,200
4,110,000
6,350,000
760,000
310,000
1,585,000
12,800,000
352,500
1,495,000
536,600
1,788,750
- 15,147,770 1,075,000 1,545,000 3,020,000 4,662,835 12,540,100 2,796,199 32,529,050 450,000
Events Center Safety Lighting Improvements
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
Events Center
60
Community Services
Special Events
2027
Infrastructure
Public Safety, Health & Environment
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$130,000 $0 $0 $0 $0$0 $0 $130,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$130,000 $0 $0 $0 $0 $130,000
Funding Details:
Project Description and Justification
The Events Center Pavilion parking area currently lacks lighting, and illumination is limited throughout the Events Complex bar and
chute areas. This creates safety concerns for guests and employees during evening operations. Install lighting in identified priority
locations to improve visibility and safety.
Sheet 1 of 85
Events Complex Signage
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Rob Hinkle
Events Complex
60
Community Services
Special Events
2030
Infrastructure
Public Safety, Health & Environment
New
Duration (Years):
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$105,635 $0 $0 $0 $0$0 $0 $105,635
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$105,635 $0 $0 $0 $0 $105,635
Funding Details:
Project Description and Justification
Currently no internal directional signage to create a sense of arrival for Events Complex. Design, construct and install permanent
signage through the Events Complex.
Sheet 2 of 85
Highway 36/Community Drive Fencing
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Rob Hinkle
Events Complex
Community Services
Special Events
2030
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$299,943 $0 $0 $0 $0$0 $0 $299,943
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$299,943 $0 $0 $0 $0 $299,943
Funding Details:
Project Description and Justification
Replace the Events Complex chain link fencing along Hwy 36 and Community Drive with a double four board fence. This fence
will start the beautification of the Hwy 36 and Community Drive corridors following the installation of the Roundabout at the inters
Sheet 3 of 85
Stall Barn Relocation and Replacement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
Events Complex
Community Services
Special Events
2028
Robust Economy
Exceptional Guest Services
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$3,630,000 $0 $0 $0 $360,000$0 $0 $3,990,000
Funding Sources
Federal Grant or
Loan
Bonds NA NA NA Total
$3,990,000 $0 $0 $0 $0 $3,990,000
Funding Details: Funding request adds 10% yearly from 2026 costs estimates. ($3M in 2026)
Project Description and Justification
This project includes design and construction of a new consolidated barn facility to replace six existing stall barns (65 total stalls)
at the Event Center. The current barns occupy the non-deed restricted parcel identified as the preferred location for as the
preferred location for a new Public Safety Facility, while supporting the continued community and economic benefits provided by
the Event Center. The project will likely be completed over two years.
Sheet 4 of 85
Brown Sand Tent Repair
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Robert Shumaker
640 Elm Road
10
InternalServices
Facilities
2027
Infrastructure
Government Services & Internal Support
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$74,250 $0 $0 $0 $8,250$0 $0 $82,500
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$82,500 $0 $0 $0 $0 $82,500
Funding Details:
Project Description and Justification
Repair the fabric coating on the original sand tent. Upgrade foundation as needed to accommodate new codes, if necessary.
Sheet 5 of 85
Facility Security Modernization and Enhancement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
Downtown Corridor
10
InternalServices
Facilities
2028
Government Services & Internal Support
Public Safety, Health & Environment
New
Duration (Years):
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$100,000 $0 $0 $0 $10,000$0 $0 $110,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$110,000 $0 $0 $0 $0 $110,000
Funding Details:
Project Description and Justification
Enhance physical security across multiple facilities with exterior video systems and modernization of access control. This
prevents vandalism, security issues and minimized staff costs for closures. This phase would include security cameras and
access controls at the public restrooms in the downtown (Performance Park, Tregent, Weist).
Sheet 6 of 85
Fleet Shop Addition/Extension
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
575 Elm Road
20
InternalServices
Facilities
2029
Government Services & Internal Support
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$450,000 $0 $0 $0 $0$0 $0 $450,000
Funding Sources
Other Funding NA NA NA NA Total
$450,000 $0 $0 $0 $0 $450,000
Funding Details: 30404000-531130. Need budget plan to add $150,000 each year for 3 years.
Project Description and Justification
This project will include design services and construction to add an extension to the Fleet Division Maintenance Shop. This
addition will include an additional 2 oversize bays to accommodate the increased demand in servicing of fleet vehicles and also
storage of equipment and supplies.
Sheet 7 of 85
New Public Safety Facility Construction
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
Unknown
50
InternalServices
Facilities
2027
Government Services & Internal Support
Outstanding Community Services
Public Safety, Health & Environment
New
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$34,000,000 $0 $0 $0 $0$0 $0 $34,000,000
Funding Sources
Federal Grant or
Loan
NA NA NA NA Total
$34,000,000 $0 $0 $0 $0 $34,000,000
Funding Details: Use of existing sales tax revenue currently allocated to EVFPD
Project Description and Justification
This project will construct a new Public Safety Facility to replace the Police Department’s current space in Town Hall, a former
school built in the 1930s and converted for police use in 1974. The existing facility is undersized and has received no significant
capital investment since conversion. Estimated costs include $12,000,000 for construction services in 2027 and $18,000,000 in
2028.
Sheet 8 of 85
Riverside Public Restroom Replacement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
Riverside Public Restrooms
20
InternalServices
Facilities
2028
Infrastructure
Outstanding Community Services
Exceptional Guest Services
New
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$1,327,200 $0 $0 $0 $0$0 $0 $1,327,200
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$1,327,200 $0 $0 $0 $0 $1,327,200
Funding Details:
Project Description and Justification
The Riverside Public Restroom facility is one of the most heavily used in the Downtown. Built in 1974, consisting of 518sf, the
current facility has a number of challenges related to ADA and location within the flood plain. This project would involve full design
services (MEP, civil, architectural, etc) and construction of a new Riverside Restroom for public use on the opposite sid of the Big
Thompson river from its current location.
Sheet 9 of 85
Roof Replacement (Section 5, TAO area)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
170 MacGregor Ave
20
InternalServices
Facilities
2029
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$250,000 $0 $0 $0 $0$0 $0 $250,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$250,000 $0 $0 $0 $0 $250,000
Funding Details:
Project Description and Justification
Roof replacement at Town Hall above Town Administration area. Costs include asbestos testing and remediation.
Sheet 10 of 85
Roof Replacement Above Board Room
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
170 MacGregor Ave
20
InternalServices
Facilities
2029
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$312,500 $0 $0 $0 $0$0 $0 $312,500
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$312,500 $0 $0 $0 $0 $312,500
Funding Details:
Project Description and Justification
Roof replacement at Town Hall above the Board Room area. Cost includes asbestos testing and remediation.
Sheet 11 of 85
Town Hall Roof Replacement (Section 2 - Police)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
Town Hall
20
$0
InternalServices
Facilities
2027
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$534,800 $0 $0 $0 $50,000$0 $0 $584,800
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$584,800 $0 $0 $0 $0 $584,800
Funding Details:
Project Description and Justification
Complete the full replacement of Section 2 of the Town Hall roofing system, including removal, remediation and disposal of the
existing roof and installation of a new roof system. This section covers the area directly above the Police Department.
Sheet 12 of 85
Town Hall Roof Replacements (Section 4 - Comm Dev)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
Town Hall 170 MacGregor Ave
20
InternalServices
Facilities
2028
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$951,000 $0 $0 $0 $0$0 $0 $951,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$951,000 $0 $0 $0 $0 $951,000
Funding Details:
Project Description and Justification
Replace the existing roof system on Section 4 of Town Hall, including complete removal, remediation as needed, and
installation of a new roof . Section 4 is located above the Community Development Department.
Sheet 13 of 85
Streets Maintenance Shop Extension
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
577 Elm Road
40
InternalServices
Facilities
2029
Government Services & Internal Support
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$282,500 $0 $0 $0 $28,250$0 $0 $310,750
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$310,750 $0 $0 $0 $0 $310,750
Funding Details:
Project Description and Justification
This project would aim to extend the existing bay garage doors and walls to accommodate the vehicles that have outgrown the
current space. This would include design services to extend the wall approximately 10 ft, construction of the new walls and new
garage doors
Sheet 14 of 85
Town Hall Board Room Carpeting
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
170 MacGregor Ave
10
InternalServices
Facilities
2030
Outstanding Community Services
Exceptional Guest Services
Government Services & Internal Support
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$50,000 $0 $0 $0 $17,812$0 $0 $67,812
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$67,812 $0 $0 $0 $0 $67,812
Funding Details:
Project Description and Justification
The carpet in the Town Board room needs replacement as a part of lifecycle improvements following completion of repainting of
the Board room and recarpeting in other sections of Town Hall.
Sheet 15 of 85
Town Hall Elevator Replacement and ADA Compliance
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Robert Shumaker
Town Hall
20
$1,320
InternalServices
Facilities
2031
Exceptional Guest Services
Government Services & Internal Support
Public Safety, Health & Environment
Extend Useful Life
Duration (Years):
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$577,500 $57,750 $17,325 $0 $57,750$0 $0 $710,325
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$710,325 $0 $0 $0 $0 $710,325
Funding Details:
Project Description and Justification
Subject to Town Board policy decisions regarding the future use of the Town Hall facility. this project would replace the existing
elevator with an ADA compliant system.
Sheet 16 of 85
Town Hall Window Replacement Program (2027–2031)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
170 MacGregor Ave
20
InternalServices
Facilities
2028
Government Services & Internal Support
Replacement
Duration (Years):5
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$125,000 $0 $0 $0 $0$0 $0 $125,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$125,000 $0 $0 $0 $0 $125,000
Funding Details:
Project Description and Justification
This project proposes the phased replacement of 33 Town Hall windows over a five-year period, replacing approximately several
windows annually to address aging, energy-inefficient units that are believed to date back to the building’s 1974 conversion fro a
school to Town Hall. Implementation of the project should be coordinated with Town policy decisions regarding the long-term use
and occupancy of the current Town Hall facility.
Sheet 17 of 85
Visitor Center Exterior Log Support Rehabilitation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
500 Big Thompson
50
InternalServices
Facilities
2029
Exceptional Guest Services
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$196,000 $0 $0 $0 $20,000$0 $0 $216,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$216,000 $0 $0 $0 $0 $216,000
Funding Details:
Project Description and Justification
Remove and replace the deteriorated lower sections of all 13 exterior logs at the Visitor Center that have sustained long-term
water and snow damage. Install new stone pilasters to support the logs and match the existing stone support structures at the
building entrances.
Sheet 18 of 85
Visitor Center Log Restoration and Preservation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
500 Big Thompson
10
InternalServices
Facilities
2027
Outstanding Community Services
Exceptional Guest Services
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$274,565 $0 $0 $0 $0$0 $0 $274,565
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$274,565 $0 $0 $0 $0 $274,565
Funding Details:
Project Description and Justification
This project will restore and preserve the interior and exterior log structures at the Visitor Center. Work includes repairing cracks
in structural and decorative logs, refinishing and sealing interior wood surfaces and addressing water-damaged exterior logs.
Exterior improvements include crack and damage repair, surface preparation, sanding, staining, and application of a protective
clear coat to all exterior logs.
Sheet 19 of 85
Visitor Center Restrooms Renovation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul Fetherston
500 Big Thompson
20
InternalServices
Facilities
2028
Outstanding Community Services
Exceptional Guest Services
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$263,400 $0 $0 $0 $26,340$0 $0 $289,740
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$289,740 $0 $0 $0 $0 $289,740
Funding Details:
Project Description and Justification
This project will fully renovate the men's, women's and family restrooms within the Visitor Center. Improvements include
replacement of all plumbing fixtures, lighting, flooring, wall tile, stall partitions, heaters, and paint. Serving approximately
400,000 visitors annually, the Visitor Center plays a key role in shaping visitors' perceptions of Estes Park, making the quality,
accessibility, and appearance of these facilities an important component of the overall visitor experience.
Sheet 20 of 85
Stormwater MGMT PRGM- Local Drainage Projects 2027
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
20
Public Works
Engineering / Transportation
2027
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$700,000 $0 $0 $0 $100,000$0 $0 $800,000
Funding Sources
SalesTax1ASTOR
M
NA NA NA NA Total
$800,000 $0 $0 $0 $0 $800,000
Funding Details:
Project Description and Justification
Each year neighborhood drainage projects will be identified for design and construction to resolve local drainage problems.
Woodstock and Brook Dr.
Sheet 21 of 85
Stormwater MGMT PRGM- 2028- Big Thompson
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
40
$109,000
Public Works
Engineering / Stormwater
2028
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$0 $1,500,000 $0 $0 $100,000$300,000 $0 $1,900,000
Funding Sources
Federal Grant or
Loan
SalesTax1ASTOR
M
NA NA NA Total
$300,000 $1,600,000 $0 $0 $0 $1,900,000
Funding Details:All costs per SWMP. Funding is dependent on sales tax collection
Project Description and Justification
This is the design of the Big Thompson River Improvements from US36 upstream to the Riverside Dr Bridge. Accrued fund
balance will be used
Sheet 22 of 85
Stormwater MGMT PRGM- 2029- Big Thompson Const
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
40
$109,000
Public Works
Engineering / Stormwater
2029
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$12,000,000 $0 $1,000,000 $0 $1,000,000$300,000 $0 $14,300,000
Funding Sources
Federal Grant or
Loan
SalesTax1ASTOR
M
NA NA NA Total
$11,000,000 $3,300,000 $0 $0 $0 $14,300,000
Funding Details: 1% Sales tax collected since 2024 will fund a 20% local match for a future 11 million federal grant.
Project Description and Justification
This project constructs the Big Thompson River Improvements from US 36 upstream to Riverside Dr bridge. Project to be more
specifically defined by the future stormwater engineer.
Sheet 23 of 85
Stormwater MGMT PRGM- 2029- Phase 5
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Town Limits
40
$109,000
Public Works
Engineering / Stormwater
2029
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$6,300,000 $500,000 $400,000 $0 $100,000$300,000 $0 $7,600,000
Funding Sources
Federal Grant or
Loan
SalesTax1ASTOR
M
NA NA NA Total
$6,300,000 $1,300,000 $0 $0 $0 $7,600,000
Funding Details: All costs per SWMP. Funding is dependent on future grant opportunities.
Project Description and Justification
The Stormwater Management Plan will implement the O& M and capital recommendations of the adopted Stormwater Master
Plan. Priority is given to annual O &M; neighborhood drainage projects; and larger projects downstream to upstream. This is a
placeholder project to be more specifically defined by the future stormwater engineer.
Sheet 24 of 85
Stormwater MGMT PRGM- Local Drainage 2028
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
40
Public Works
Engineering / Stormwater
2028
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$230,050 $20,000 $20,000 $0 $50$0 $0 $270,100
Funding Sources
SalesTax1ASTOR
M
NA NA NA NA Total
$270,100 $0 $0 $0 $0 $270,100
Funding Details:
Project Description and Justification
Each year a neighborhood drainage project will be identified for design and construction to resolve local drainage issues.
Sheet 25 of 85
Stormwater MGMT PRGM- Local Drainage 2029
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
40
Public Works
Engineering / Stormwater
2029
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$190,000 $20,000 $20,000 $0 $50,000$0 $0 $280,000
Funding Sources
SalesTax1ASTOR
M
NA NA NA NA Total
$280,000 $0 $0 $0 $0 $280,000
Funding Details:
Project Description and Justification
Each year a neighborhood drainage project will be identified for design and construction to resolve local drainage issues.
Sheet 26 of 85
Stormwater 2030- Big Thompson- Bridge Design
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
40
$109,000
Public Works
Engineering / Stormwater
2030
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$0 $2,200,000 $0 $0 $200,000$300,000 $0 $2,700,000
Funding Sources
SalesTax1ASTOR
M
NA NA NA NA Total
$2,700,000 $0 $0 $0 $0 $2,700,000
Funding Details: Accrued fund balance will be used. It also includes 1 million to design the channel improvements between
the 2 bridges.
Project Description and Justification
This is the design effort to replace bridges over the Big Thompson River at Riverside Drive and Rockwell St Vrain.
Sheet 27 of 85
Stormwater MGMT PRGM- Local Drainage 2030
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
throughout Estes Park
40
Public Works
Engineering / Stormwater
2030
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$200,000 $20,000 $20,000 $0 $50,000$0 $0 $290,000
Funding Sources
SalesTax1ASTOR
M
NA NA NA NA Total
$290,000 $0 $0 $0 $0 $290,000
Funding Details:
Project Description and Justification
Each year a neighborhood drainage project will be identified for design and construction to resolve local drainage issues.
Sheet 28 of 85
Stormwater MGMT PRGM- Big Thomp Riv Bridge Replace
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
40
$545,000
Public Works
Engineering / Stormwater
2031
Infrastructure
Replacement
Duration (Years):5
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$26,500,000 $3,000,000 $2,000,000 $0 $300,000$1,500,000 $0 $33,300,000
Funding Sources
Federal Grant or
Loan
SalesTax1ASTOR
M
Community
Reinvestment
NA NA Total
$28,300,000 $2,000,000 $3,000,000 $0 $0 $33,300,000
Funding Details: All costs per SWMP. Annual O & M = $545k. Funding is dependent on future grant opportunities.
Project Description and Justification
This project replaces the two bridges over the Big Thompson River at Riverside Dr and Rockwell. It also includes $10m to
construct channel improvements.
Sheet 29 of 85
Crags Bridge Rehabilitation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Crags Drive over the Big Thompson River
10
$1,000
Public Works
Engineering / Transportation
2031
Transportation
Extend Useful Life
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$410,000 $82,000 $65,000 $4,000 $84,000$0 $0 $645,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$645,000 $0 $0 $0 $0 $645,000
Funding Details:
Project Description and Justification
1 of 3 bridges identified as needing significant rehabilitation via CDOT Off-System Bridge Inspection. Potential replacement in
years via Stormwater Management Program if implemented. The other two bridges: Ivy Bridge has been replaced by DELoop;
Rockwell bridge proposed to be replaced with FEMA grant.
Sheet 30 of 85
Downtown Wayfinding- Phase 2 Downtown Loop
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
20
Public Works
Engineering / Transportation
2028
Transportation
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$225,000 $0 $25,000 $0 $25,000$0 $0 $275,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$275,000 $0 $0 $0 $0 $275,000
Funding Details:
Project Description and Justification
Fourteen (14) signs for pedestrian and vehicle wayfinding in the downtown area within the current Estes Park Loop project limits.
Sheet 31 of 85
Downtown Wayfinding - Ph 3 - Trail System
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
20
$3,000
Public Works
Engineering / Transportation
2029
Transportation
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$260,000 $0 $20,000 $0 $20,000$0 $0 $300,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$300,000 $0 $0 $0 $0 $300,000
Funding Details:
Project Description and Justification
Downtown wayfinding signage program- design and implementation plan was adopted by TB in January 2023. Phase 1 of this plan
was completed in 2023. This phase will be constructed in 2028 to provide pedestrian level wayfinding along the trail system. Build
out phased program.
Sheet 32 of 85
Downtown Wayfinding- Phase 4 Building Mounted
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
20
$1,000
Public Works
Engineering / Transportation
2030
Transportation
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$96,000 $0 $12,000 $0 $12,000$0 $0 $120,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$120,000 $0 $0 $0 $0 $120,000
Funding Details:
Project Description and Justification
Additional building mounted pedestrian scale wayfinding signs located in areas where larger signage is not feasible.
Sheet 33 of 85
Downtown Wayfinding Phase 5- Auto Directional
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Downtown Estes Park
20
$1,000
Public Works
Engineering / Transportation
2031
Transportation
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$500,000 $0 $30,000 $0 $40,000$0 $0 $570,000
Funding Sources
Community
Reinvestment
NA NA NA NA Total
$570,000 $0 $0 $0 $0 $570,000
Funding Details:
Project Description and Justification
Vehicular wayfinding signs to direct users to parking areas and destinations. These signs will replace the parking pilot signs
that were installed in 2021.
Sheet 34 of 85
Moraine Avenue Multi-Modal Improvements
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Moraine Ave (US36) from west of Crags to Marys Lake Road
20
$5,000
Public Works
Engineering / Transportation
2031
Transportation
Replacement
Duration (Years):3
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$11,314,000 $1,640,000 $2,590,000 $0 $2,499,000$960,000 $0 $19,003,000
Funding Sources
Federal Grant or
Loan
Community
Reinvestment
NA NA NA Total
$15,733,000 $3,270,000 $0 $0 $0 $19,003,000
Funding Details:Costs per 2019 FLAP grant application. Funding dependent on future grant award. FLAP grant not awarded
in 2016 & 2019. Update scope, schedule, and budget for 2026 grant cycle.
Project Description and Justification
Add bike lanes, turn lanes, and roundabout (Elm Road). Combine with separate CIP project proposal for roundabout at Mary’s
Lake Road intersection? The 2026 Town Strategic Plan includes Objective T.3.B to begin advance planning with RMNP and
other stakeholders to develop stronger FLAP grant applications.
Sheet 35 of 85
N St Vrain Avenue (US36) Multi-Modal Improvements
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
N St Vrain Avenue (US36), Community Drive Roundabout to SH7
20
$2,000
Public Works
Engineering / Transportation
2031
Transportation
New
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$3,000,000 $350,000 $300,000 $50,000 $400,000$250,000 $0 $4,350,000
Funding Sources
State Grant or
Loan
Community
Reinvestment
NA NA NA Total
$3,480,000 $870,000 $0 $0 $0 $4,350,000
Funding Details:Funding is dependent on future grant award.
Project Description and Justification
Construct multi-use trail along the south side of N St Vrain Avenue (US36) from Community Drive roundabout to 4th Street.
Construct 2nd westbound travel lane from Community Drive roundabout to 4th Street. Coordinate w/relocation of campground at
Fairgounds.
Sheet 36 of 85
North Saint Vrain Avenue (US36) Trail Replacement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
North Saint Vrain Avenue- 1st Street- 4th Street
20
Public Works
Engineering / Transportation
2028
Transportation
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$250,000 $0 $0 $0 $25,000$0 $0 $275,000
Funding Sources
SalesTax1ATRL NA NA NA NA Total
$275,000 $0 $0 $0 $0 $275,000
Funding Details:
Project Description and Justification
Replacement of existing inadequate failing sidewalk with new eight foot wide trail.
Sheet 37 of 85
STIP Overlay & Patch Program 2027
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
10
$0
Public Works
Engineering / Transportation
2027
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$800,000 $50,000 $0 $0 $150,000$0 $0 $1,000,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$1,000,000 $0 $0 $0 $0 $1,000,000
Funding Details:
Project Description and Justification
Each year a number of streets will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD.
Sheet 38 of 85
STIP Overlay & Patch Program 2028
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
10
$0
Public Works
Engineering / Transportation
2028
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$595,000 $85,000 $85,000 $0 $85,000$0 $0 $850,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$850,000 $0 $0 $0 $0 $850,000
Funding Details:
Project Description and Justification
Each year a number of streets will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD.
Sheet 39 of 85
STIP Overlay & Patch Program 2029
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Throughout Estes Park
10
$0
Public Works
Engineering / Transportation
2029
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$560,000 $80,000 $80,000 $0 $80,000$0 $0 $800,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$800,000 $0 $0 $0 $0 $800,000
Funding Details:
Project Description and Justification
Each year a number of streets will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD.
Sheet 40 of 85
STIP Parking Lot Rehabilitation 2027
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Any Town-owned parking lot
10
$0
Public Works
Engineering / Transportation
2027
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$120,000 $0 $0 $0 $0$0 $0 $120,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$120,000 $0 $0 $0 $0 $120,000
Funding Details:
Project Description and Justification
Each year one or more parking lots will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD in coordination with P&T Division.
Sheet 41 of 85
STIP Parking Lot Rehabilitation 2028
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Any public parking lot
10
$0
Public Works
Engineering / Transportation
2028
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$150,000 $0 $0 $0 $0$0 $0 $150,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$150,000 $0 $0 $0 $0 $150,000
Funding Details:
Project Description and Justification
Each year one or more parking lots will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD in coordination with P&T Division.
Sheet 42 of 85
STIP Parking Lot Rehabilitation 2029
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Any Town-owned parking lot
10
$0
Public Works
Engineering / Transportation
2029
Transportation
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$100,000 $0 $0 $0 $0$0 $0 $100,000
Funding Sources
SalesTax1AST NA NA NA NA Total
$100,000 $0 $0 $0 $0 $100,000
Funding Details:
Project Description and Justification
Each year one or more parking lots will be addressed based on Pavement Condition Index (PCI) evaluation. Project location and
specific scope TBD in coordination with P&T Division.
Sheet 43 of 85
Trail Reconstruction US 34 and SH7 Phase 3
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
along us 34 and SH7
20
Public Works
Engineering / Transportation
2028
Transportation
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$416,667 $0 $77,778 $5,556 $77,777$22,222 $0 $600,000
Funding Sources
Open Space SalesTax1ATRL NA NA NA Total
$300,000 $300,000 $0 $0 $0 $600,000
Funding Details:This funding is split over 9 different phases. The total anticipated amount over the life of the project is
5,400,000. (this does not include the $250,000 spent on design).
Project Description and Justification
This is phase 3 of 9 phases that will be developed based on design and refined cost estimates. The intent is to proceed in a
logical manner that leaves no intermittent gaps as the project progresses.
Sheet 44 of 85
Trail Reconstruction US 34 and SH7 Phase 4
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Along US 34 and SH7
20
Public Works
Engineering / Transportation
2029
Transportation
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$416,667 $0 $77,778 $5,556 $77,777$22,222 $0 $600,000
Funding Sources
Open Space SalesTax1ATRL NA NA NA Total
$300,000 $300,000 $0 $0 $0 $600,000
Funding Details:This funding is split over 9 different phases. The total anticipated amount over the life of the project is
5,400,000 (this does not include the $250,000 spent on design).
Project Description and Justification
This is phase 4 of 9 phases that will be developed based on design and refined cost estimates. The intent is to proceed in a
logical manner that leaves no intermittent gaps as the project progresses.
Sheet 45 of 85
Trail Reconstruction US 34 and SH7 Phase 5
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Along US 34 and SH7
20
Public Works
Engineering / Transportation
2030
Transportation
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$416,667 $0 $77,778 $5,556 $77,777$22,222 $0 $600,000
Funding Sources
Open Space SalesTax1ATRL NA NA NA Total
$300,000 $300,000 $0 $0 $0 $600,000
Funding Details:This funding is split over 9 different phases. The total anticipated amount over the life of the project is
5,400,000 (this does not include the $250,000 spent on design).
Project Description and Justification
This is phase 5 of 9 phases that will be developed based on design and refined cost estimates. The intent is to proceed in a
logical manner that leaves no intermittent gaps as the project progresses.
Sheet 46 of 85
Children's Park Remodel, 2027
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Brian Berg
Children's Park
20
$200
Public Works
Parks
2027
Infrastructure
Outstanding Community Services
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$175,000 $0 $0 $0 $0$0 $0 $175,000
Funding Sources
Open Space NA NA NA NA Total
$175,000 $0 $0 $0 $0 $175,000
Funding Details:
Project Description and Justification
Renovate Children’s Park by installing a new ADA-accessible play structure and rubber pour-in-place surfacing. Replace the
existing paver area with stamped concrete that complements and matches the Loop concrete design, improving accessibility,
safety, and overall aesthetics.
Sheet 47 of 85
Wonderview Ave Trail Extension
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Trevor Wittwer
Along the north side of Wonderview Avenue, from north of the US34/US36 intersection to the
MacGregor Avenue roundabout sidewalk
20
$1,000
Public Works
Engineering / Transportation
2027
Transportation
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$330,000 $0 $0 $0 $40,000$0 $0 $370,000
Funding Sources
SalesTax1ATRL NA NA NA NA Total
$370,000 $0 $0 $0 $0 $370,000
Funding Details:
Project Description and Justification
Construct trail along the north side of Wonderview (US34) to close the gap between existing sidewalks at Steamer Village and
the MacGregor roundabout. The Town owns 2 of the 3 parcels that front this stretch of highway.
Sheet 48 of 85
Big Horn Parking Structure (Construction)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Dana Klein
Big Horn and Cleave street
50
Public Works
ParkingTransit
2028
Transportation
Robust Economy
Exceptional Guest Services
Master Plan
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$4,500,000 $0 $0 $0 $450,000$0 $0 $4,950,000
Funding Sources
Parking Bonds NA NA NA Total
$295,000 $4,655,000 $0 $0 $0 $4,950,000
Funding Details:cost per space is $39000
Project Description and Justification
Build a parking structure on current Big Horn parking lot footprint. Estimate 115 spaces, three levels, no ramps. Contingent on
implementation of phase 3 of DPMP. This project may be modified significantly as a result of the proposed combined retail,
residential and parking project by others.
Sheet 49 of 85
Downtown Parking Mgmt Plan (DPMP) - Ph. 3
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Dana Klein
Downtown Estes Park
10
$562,500
Public Works
ParkingTransit
2028
Transportation
Robust Economy
Exceptional Guest Services
Master Plan
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$168,000 $0 $0 $0 $0$0 $0 $168,000
Funding Sources
Parking NA NA NA NA Total
$168,000 $0 $0 $0 $0 $168,000
Funding Details: Additional paid parking revenues. We estimate an additional $525,000 in season revenue.
Project Description and Justification
If supported by parking data collected in the 2025 and 2026 paid parking seasons, full implementation of DPMP would occur in
2028. This would include expansion of the paid parking program into additional public parking areas in downtown.
Demand-based pricing would also be considered. This amount would support additional parking payment kiosks and lot signage
for the expanded program.
Sheet 50 of 85
Downtown Parking Mgmt Plan Ph. IV (Construction)
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Dana Klein
Downtown Estes Park
50
$32,000
Public Works
ParkingTransit
2031
Transportation
Robust Economy
Exceptional Guest Services
Master Plan
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$11,772,000 $0 $1,170,000 $0 $2,340,000$0 $0 $15,282,000
Funding Sources
Parking Bonds NA NA NA Total
$1,604,000 $13,678,000 $0 $0 $0 $15,282,000
Funding Details:
Project Description and Justification
Build second parking structure in the downtown core with 300 spaces. Est $39,200 per space with minimal land acq costs.
Contingent upon implementation of DPMP Phase 3 expansion of paid parking.
Sheet 51 of 85
VC Parking Garage Structural Maintenance
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Paul FetherstonPublic Works
ParkingTransit
2027
Exceptional Guest Services
Robust Economy
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$143,735 $0 $30,000 $0 $0$0 $0 $173,735
Funding Sources
Parking NA NA NA NA Total
$173,735 $0 $0 $0 $0 $173,735
Funding Details:
Project Description and Justification
The parking structure, constructed in 2017, underwent a third-party condition assessment and 10 year asset management review.
The study identified $400,000 in structural improvements over the next several years to maintain facility integrity. This represents
year 1 of recommended structural maintenance (sealants, cracks, floor repair and patch).
Sheet 52 of 85
Downtown Parking Mgmt Plan Ph. IV Design
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Dana Klein
Downtown Estes Park
10
$0
Public Works
ParkingTransit
2030
Transportation
Robust Economy
Exceptional Guest Services
Master Plan
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$0 $1,980,000 $0 $0 $198,000$100,000 $0 $2,278,000
Funding Sources
Parking NA NA NA NA Total
$2,278,000 $0 $0 $0 $0 $2,278,000
Funding Details:
Project Description and Justification
Site selection & design for second parking structure (300 spaces) located within the downtown core. Revenue assumes
implementation of DPMP Phase 3, expanded paid parking.
Sheet 53 of 85
Electric Vehicle (EV) Charging Station
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Dana Klein
Visitor Center Parking Lot
10
Public Works
ParkingTransit
2029
Transportation
Exceptional Guest Services
Outstanding Community Services
New
Duration (Years):
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$132,000 $0 $0 $0 $12,100$0 $0 $144,100
Funding Sources
Parking NA NA NA NA Total
$144,100 $0 $0 $0 $0 $144,100
Funding Details:
Project Description and Justification
This project proposes the addition of four fast electric vehicle (EV) charging stations to the Performance Park parking lot.
Originally planned for completion in 2025, the project timeline is moving to 2028 based on a check in with the Town Board (TB)
The 2028 timeline will allow for the collection and analysis of demand data and further check in with the TB. This project
anticipates grant funding with a local match budgeted.
Sheet 54 of 85
P&C Building New Restrooms
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Derek Pastor
615 Elm Road
50
Utilities
Power & Communications
2028
Government Services & Internal Support
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$100,000 $0 $0 $0 $0$0 $0 $100,000
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$100,000 $0 $0 $0 $0 $100,000
Funding Details:
Project Description and Justification
Architectural design and construction to create a new ADA accessible unisex restroom to accommodate the need to the
number of staff in that space.
Sheet 55 of 85
Allenspark mainline rebuild to Tree cable
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
CR84
50
Utilities
Power & Communications
2028
Infrastructure
Public Safety, Health & Environment
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$162,417 $0 $0 $0 $0$0 $0 $162,417
Funding Sources
Federal Grant or
Loan
InKind NA NA NA Total
$141,646 $20,771 $0 $0 $0 $162,417
Funding Details:
Project Description and Justification
Replace with tree cable
Sheet 56 of 85
Bellevue, Brown Trout, Big Thompson
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Hwy 34
50
Utilities
Power & Communications
2028
Infrastructure
Robust Economy
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$924,950 $0 $0 $0 $0$0 $0 $924,950
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$924,950 $0 $0 $0 $0 $924,950
Funding Details:Earmarked money from BEAD
Project Description and Justification
Build out Hwy 34 for with Fiber
Sheet 57 of 85
Big Owl road, line rebuild to tree cable
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Big Owl Road
50
Utilities
Power & Communications
2028
Infrastructure
Public Safety, Health & Environment
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$63,771 $0 $0 $0 $0$0 $0 $63,771
Funding Sources
Federal Grant or
Loan
InKind NA NA NA Total
$43,000 $20,771 $0 $0 $0 $63,771
Funding Details:
Project Description and Justification
Replace with Tree Cable
Sheet 58 of 85
Big Thompson Grid Hardening
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
50
Utilities
Power & Communications
2029
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$500,000 $0 $0 $0 $0$0 $0 $500,000
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$500,000 $0 $0 $0 $0 $500,000
Funding Details:
Project Description and Justification
Underground the 3 phase main line, could replace with tree cable
Sheet 59 of 85
1A Sales Tax Wildfire Mitigation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Fish Hatchery Road
50
Utilities
Power & Communications
2031
Infrastructure
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$87,915 $0 $0 $0 $0$0 $0 $87,915
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$87,915 $0 $0 $0 $0 $87,915
Funding Details:
Project Description and Justification
Replace three phase bare copper with insulated tree cable, replace poles, replace bare jumpers with insulated jumpers.
Sheet 60 of 85
Eagle Cliff
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Eagle Cliff
50
Utilities
Power & Communications
2028
Infrastructure
Robust Economy
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$436,663 $0 $0 $0 $0$0 $0 $436,663
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$436,663 $0 $0 $0 $0 $436,663
Funding Details:
Project Description and Justification
Build out fiber infrastructure to Eagle Cliff CBA
Sheet 61 of 85
Fish Creek rd, line rebuild to tree cable
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Fish Creek
50
Utilities
Power & Communications
2029
Infrastructure
Public Safety, Health & Environment
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$87,771 $0 $0 $0 $0$0 $0 $87,771
Funding Sources
Federal Grant or
Loan
InKind NA NA NA Total
$67,000 $20,771 $0 $0 $0 $87,771
Funding Details:
Project Description and Justification
Replace three with Tree Cable
Sheet 62 of 85
Glacier
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Glacier Cabinet Boundary Area
Utilities
Power & Communications
2028
Infrastructure
Robust Economy
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$436,663 $0 $0 $0 $0$0 $0 $436,663
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$436,663 $0 $0 $0 $0 $436,663
Funding Details:
Project Description and Justification
Build fiber to Glacier Cabinet Area
Sheet 63 of 85
1A Sales Tax Wildfire Mitigation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
High Drive
50
Utilities
Power & Communications
2031
Infrastructure
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$56,280 $0 $0 $0 $0$0 $0 $56,280
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$56,280 $0 $0 $0 $0 $56,280
Funding Details:
Project Description and Justification
Replace the bare three phase copper lines with insulated tree cable, replace poles, replace bare jumpers with insulated
jumpers.
Sheet 64 of 85
Hwy36
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Hwy 36
50
Utilities
Power & Communications
2031
Infrastructure
Public Safety, Health & Environment
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$200,417 $0 $0 $0 $0$0 $0 $200,417
Funding Sources
Federal Grant or
Loan
InKind NA NA NA Total
$160,417 $40,000 $0 $0 $0 $200,417
Funding Details:
Project Description and Justification
Replace with tree cable
Sheet 65 of 85
1A Sales Tax Wildfire Mitigation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Highway 66
50
Utilities
Power & Communications
2028
Infrastructure
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$94,000 $0 $0 $0 $0$0 $0 $94,000
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$94,000 $0 $0 $0 $0 $94,000
Funding Details:
Project Description and Justification
Replace the bare copper line with insulated tree cable, replace poles, replace bare jumpers with insulated jumpers.
Sheet 66 of 85
1A Sales Tax Wildfire Mitigation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Larkspur Road area
50
Utilities
Power & Communications
2031
Infrastructure
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$112,390 $0 $0 $0 $0$0 $0 $112,390
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$112,390 $0 $0 $0 $0 $112,390
Funding Details:
Project Description and Justification
Replace the bare copper line with insulated tree cable, replace poles, replace bare jumpers with insulated jumpers.
Sheet 67 of 85
Mall Road Grid Hardening
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Haybarn Hill
50
Utilities
Power & Communications
2031
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$250,000 $0 $0 $0 $0$0 $0 $250,000
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$250,000 $0 $0 $0 $0 $250,000
Funding Details:
Project Description and Justification
Underground 3 phase main line
Sheet 68 of 85
RMNP Fall River Road 1A
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
RMNP Fall River toad
50
Utilities
Power & Communications
2028
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$116,000 $0 $0 $0 $0$0 $0 $116,000
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$116,000 $0 $0 $0 $0 $116,000
Funding Details:
Project Description and Justification
Upgrade Powerline to tree cable
Sheet 69 of 85
Rockwood lane area, Line Rebuild
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Hwy7
50
Utilities
Power & Communications
2028
Infrastructure
Public Safety, Health & Environment
Government Services & Internal Support
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$104,000 $0 $0 $0 $0$0 $0 $104,000
Funding Sources
Federal Grant or
Loan
NA NA NA NA Total
$104,000 $0 $0 $0 $0 $104,000
Funding Details:
Project Description and Justification
Replace line with Tree Cable
Sheet 70 of 85
1A Sales Tax Wildfire Mitigation
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Wind Cliff Three Phase
50
Utilities
Power & Communications
2029
Infrastructure
Extend Useful Life
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$109,000 $0 $0 $0 $0$0 $0 $109,000
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$109,000 $0 $0 $0 $0 $109,000
Funding Details:
Project Description and Justification
Replace all the bare copper three phase lines in the Wind Cliff area with insulated tree cable, pole replacements, replace bare
jumpers with insulated jumpers.
Sheet 71 of 85
West
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
Elm Rd.
50
Utilities
Power & Communications
2028
Infrastructure
Robust Economy
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$147,923 $0 $0 $0 $0$0 $0 $147,923
Funding Sources
Power &
Communication
Enterprise Fund
NA NA NA NA Total
$147,923 $0 $0 $0 $0 $147,923
Funding Details:Earmarked money
Project Description and Justification
Fiber Optic Buildout for West Cabinet
Sheet 72 of 85
YMCA
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Joe Lockhart
YMCA
80
Utilities
Power & Communications
2028
Infrastructure
Public Safety, Health & Environment
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$125,000 $0 $0 $0 $0$0 $0 $125,000
Funding Sources
SalesTax1APWRFI
RE
NA NA NA NA Total
$125,000 $0 $0 $0 $0 $125,000
Funding Details:
Project Description and Justification
Install Tree Cable West of Town
Sheet 73 of 85
16" Pipeline Crossing of Big Thompson River near C
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jason Lang
Riverside near Crags
120
Utilities
Water
2031
Infrastructure
New
Duration (Years):3
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$1,000,000 $250,000 $0 $20,000 $100,000$0 $0 $1,370,000
Funding Sources
Water Fund NA NA NA NA Total
$1,370,000 $0 $0 $0 $0 $1,370,000
Funding Details:
Project Description and Justification
Cross Big Thompson River near Crags and connect existing 16" pipe to line on Riverside to complete looping.
Sheet 74 of 85
Big Horn Drive Water Main Replacement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
Big Horn Drive, pipe between MacGregor and Far View, Sunny Acres, Spruce Dr
80
Utilities
Water
2030
Infrastructure
Replacement
Duration (Years):3
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$800,000 $120,000 $0 $25,200 $126,000$0 $0 $1,071,200
Funding Sources
Water Fund NA NA NA NA Total
$1,071,200 $0 $0 $0 $0 $1,071,200
Funding Details:
Project Description and Justification
Replacement of approximately 3200 LF of galvanized pipe that is past its useful life.
Sheet 75 of 85
Big Thompson Raw Water Intake
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
Big Thompson River at location TBD
50
Utilities
Water
2029
Infrastructure
Public Safety, Health & Environment
New
Duration (Years):4
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$3,000,000 $750,000 $0 $150,000 $200,000$10,000 $0 $4,110,000
Funding Sources
Water Fund NA NA NA NA Total
$4,110,000 $0 $0 $0 $0 $4,110,000
Funding Details:
Project Description and Justification
New intake for raw water from Big Thompson which will connect to new raw water pipeline to Mary's Lake WTP.
Sheet 76 of 85
Big Thompson Tank
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jason Lang
Big Thompson Tank Site
50
Utilities
Water
2028
Infrastructure
Replacement
Duration (Years):2
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$5,000,000 $750,000 $0 $100,000 $500,000$0 $0 $6,350,000
Funding Sources
Water Fund NA NA NA NA Total
$6,350,000 $0 $0 $0 $0 $6,350,000
Funding Details:
Project Description and Justification
Increase capacity at Big Thompson tank through construction of new tank. This will eliminate the need to spend capital on the
Castel and Fall River Tanks and improve water quality in the Fall River Zone.
Sheet 77 of 85
Eagle Cliff
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jason Lang
80
Utilities
Water
2031
Infrastructure
Public Safety, Health & Environment
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$625,000 $93,750 $0 $0 $31,250$0 $10,000 $760,000
Funding Sources
Water Fund NA NA NA NA Total
$760,000 $0 $0 $0 $0 $760,000
Funding Details:
Project Description and Justification
Replacement of approximately 2500 LF of pipe.
Sheet 78 of 85
Electrical Upgrades and Grounding
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jason Fredricks
Glacier Creek WTP and Mary's Lake WTP
20
Utilities
Water
2028
Infrastructure
Public Safety, Health & Environment
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$250,000 $45,000 $0 $0 $15,000$0 $0 $310,000
Funding Sources
Water Fund NA NA NA NA Total
$310,000 $0 $0 $0 $0 $310,000
Funding Details:
Project Description and Justification
Electrical and grounding improvements for site safety, protection of electrical service and emergency response power.
Sheet 79 of 85
Fall River Estates Pump House - Structure/Capacit*
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
80
Utilities
Water
2028
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$1,300,000 $195,000 $0 $15,000 $75,000$0 $0 $1,585,000
Funding Sources
Water Fund NA NA NA NA Total
$1,585,000 $0 $0 $0 $0 $1,585,000
Funding Details:
Project Description and Justification
New pump house driven by Fish Hatchery service, replace existing two 2-inch pumps currently located close to the river.
Sheet 80 of 85
New Water Treatment Plant
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
80
Utilities
Water
2029
Infrastructure
Public Safety, Health & Environment
Outstanding Community Services
New
Duration (Years):3
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$70,000,000 $0 $6,000,000 $0 $0$0 $4,800,000 $80,800,000
Funding Sources
Water Fund Bonds NA NA NA Total
$12,800,000 $68,000,000 $0 $0 $0 $80,800,000
Funding Details:
Project Description and Justification
Construct a new water treatment plant. Location to be determined in phase 1.
Sheet 81 of 85
Parking Garage Line Connection
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
Hwy 36 Parking Structure
80
Utilities
Water
2031
Infrastructure
New
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$270,000 $40,500 $0 $0 $27,000$15,000 $0 $352,500
Funding Sources
Water Fund NA NA NA NA Total
$352,500 $0 $0 $0 $0 $352,500
Funding Details:
Project Description and Justification
Install water main to loop dead end mains for fire flow protection.
Sheet 82 of 85
Strong Pumphouse Improvements
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jason Lang
Strong Ave and Spring Ln
40
Utilities
Water
2031
Public Safety, Health & Environment
Infrastructure
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$1,300,000 $195,000 $0 $0 $0$0 $0 $1,495,000
Funding Sources
Water Fund NA NA NA NA Total
$1,495,000 $0 $0 $0 $0 $1,495,000
Funding Details:
Project Description and Justification
Upgrade fire flow capacity and reliability to the Mary's pressure zone in the event that MLWTP is offline.
Sheet 83 of 85
Virginia Drive and East Riverside
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
80
Utilities
Water
2029
Replacement
Duration (Years):1
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$400,000 $60,000 $0 $0 $61,600$0 $15,000 $536,600
Funding Sources
Water Fund NA NA NA NA Total
$536,600 $0 $0 $0 $0 $536,600
Funding Details:
Project Description and Justification
Approximately 1600 LF of pipe.
Sheet 84 of 85
West Elkhorn waterline replacement
Project Information
Department:
Division:
Estimated Start:
Useful Life (Years):
Project Manager:
Location:
Capital Type:
Board Goals:
Annual Change in O&M:
Jacqui Wesley
West Elkhorn west of Moraine in downtown area
80
Utilities
Water
2031
Infrastructure
Public Safety, Health & Environment
Robust Economy
Replacement
Duration (Years):3
Project Costs
Construction Design Constr Mgmt Legal ROW Contingency Other Total
$1,425,000 $213,750 $0 $0 $150,000$0 $0 $1,788,750
Funding Sources
Water Fund NA NA NA NA Total
$1,788,750 $0 $0 $0 $0 $1,788,750
Funding Details:
Project Description and Justification
Replace approximately 5700 LF of galvinized pipeline in West Elkhorn from Moraine west to fall river.
Sheet 85 of 85