HomeMy WebLinkAboutPACKET Town Board 2026-06-23 Part 4 of 4
The Town of Estes Park is committed to providing equitable access to our services. Contact us
if you need any assistance accessing material at 970-577-4777 or townclerk@estes.org.
Report
To: Honorable Mayor Hall & Board of Trustees
Through: Town Administrator Machalek
From: The Trailblazer Broadband Team - Director Bergsten, Superintendent
Lockhart, Manager Stiner & Manager Smith
Department: Utilities - Power & Communications Division
Date: June 23, 2026
Subject: BEAD Risk Report & Recommendation
Objective:
To provide the Town Board with a brief overview of the Broadband Equity, Access, and
Deployment grant opportunity, compare the BEAD-funded buildout option with a locally
controlled staff-recommended buildout plan, and request direction on whether to accept
the BEAD award or decline the award and use previously earmarked local match funds
to continue Trailblazer Broadband’s remaining Phase 4 buildout.
Present Situation:
Trailblazer Broadband began construction in 2019 with the long-term goal of bringing
high-quality, locally owned fiber internet service to all Power & Communications
customers within the Estes Valley service area. Construction paused in 2023 due to
lack of available funding, with approximately 18% of the buildout remaining. The
remaining locations are the lowest-density and highest-cost areas of the service
territory.
The BEAD program is a federal grant program designed to help providers extend
broadband service to rural and high-cost locations that are often not economically
attractive for private internet service providers. Trailblazer initially pursued BEAD
funding because the original grant framework appeared aligned with prior federal grant
terms the Town had successfully managed, and Trailblazer was preliminarily awarded
funding.
Under the direction of the current federal administration, previously announced BEAD
awards were rescinded for review and the grant process was reopened under revised
terms. Trailblazer submitted under the revised process; however, the application
window reopened before the full final agreement was available for review. Subsequent
draft agreements were reviewed by Town counsel, who identified significant concerns.
Staff and counsel met with the Colorado Broadband Office to discuss those concerns.
Some issues were addressed, but CBO indicated much of the agreement language is
pass-through federal language with limited opportunity for modification.
The final draft agreement released in April 2026 resolved many issues that were
inconsistent with municipal limitations; however, the inclusion of Exhibit G and
related federal award requirements created a level of long-tail compliance,
reimbursement, and clawback risk that staff and Town counsel believe materially
changes the risk profile of accepting the award.
The current staff analysis compares two options:
1. BEAD Grant Plan: Accept BEAD funding and build only BEAD-eligible locations
first.
2. Staff Recommended Local Plan: Decline BEAD funding and use the same
previously earmarked local match funds to build higher-density, higher-interest
areas first, many of which are not BEAD eligible.
The current staff analysis (Attachment 1) shows BEAD provides access to up to $5.74
million in potential federal reimbursement with a required $1.917 million local match,
while the internal plan uses the same $1.917 million directly for locally controlled
construction.
Proposal:
Staff recommends declining the BEAD award and proceeding with the staff-
recommended local buildout plan using the funds previously set aside for the BEAD
match.
The staff-recommended plan allows Trailblazer to maintain local control over project
scope, phasing, construction pace, cost management, and customer rollout. Rather
than being limited to BEAD-eligible locations, the staff plan prioritizes higher-density
areas closer to town and areas with stronger organic customer interest. These areas
are largely non-BEAD eligible, but are expected to generate active customers sooner
and create a stronger foundation for continued reinvestment into later phases of the
remaining buildout.
Based on the current comparison:
Item BEAD Grant Plan Staff Recommended Local Plan
Phase 4 portion locations*
remaining unbuilt
locations
next portion of Phase 4
construction
locations only - may pass
by ineligible locations
without grant funding
including non-BEAD eligible, higher
density areas; remaining locations
sequenced in the future
federal reimbursement plus
$1.917M local match
local funds
Primary sequencing driver Federal eligibility and grant-
defined location list interest, year-round residency
indicators, and construction
efficiency
conversion expected in lower-density
and more seasonal areas
activity expected in higher-interest,
more year-round areas
eligible locations,
reimbursement process,
milestones, and compliance
obligations
budget, pace, priorities, phasing,
and customer rollout
compliance,
reimbursement, and
potential clawback
exposure
grant compliance exposure;
preserves flexibility for future
funding opportunities
*Location totals in the report are based on current GIS/buildout planning data. Attachment tables use cabinet-level
pass/electric meter data as planning indicators and may not sum directly to BEAD BSL totals.
The staff-recommended plan reaches fewer locations in the next portion of Phase 4
construction than the BEAD plan; however, the purpose of the local plan is to make the
strongest near-term use of already-allocated local funds. Attachment 1 provides the
supporting planning indicators used in staff’s comparison, including organic interest,
estimated residency patterns, anticipated take-rate potential, and construction efficiency
by area. Staff’s analysis indicates the locally controlled plan sequences construction first
in areas more likely to convert into active, full-time, year-round customers sooner.
Neither the BEAD grant nor the staff-recommended local plan will complete the full
remaining Trailblazer buildout. Under either approach, completion will require phased
construction supported by future revenue, reserves, and potential future grant or
partnership opportunities. The remaining locations not included in the first local buildout
phase would become the next portion of Phase 4, including higher-cost and lower-
density areas along the broader Highway 7 corridor between Taharaa Mountain Lodge
and downtown Allenspark and the area east of downtown Allenspark off Taylor Road.
Remaining Buildout Strategy if BEAD is Declined
As neither the BEAD grant nor the staff-recommended local plan will complete the
buildout, completion will require phased construction supported by future revenue,
reserves, and potential future grant or partnership opportunities.
Staff recommends using the funds previously reserved for the BEAD match to complete
the next portion of Phase 4 construction in areas with higher density, stronger
demonstrated customer interest, and greater year-round residency indicators. This
sequencing is intended to make the best near-term use of already-allocated local funds
by prioritizing areas most likely to generate active customers sooner.
The supporting data is not intended to serve as a formal net revenue projection. Rather,
it compares the best available indicators for responsible buildout sequencing, including
organic customer interest, estimated year-round residency, anticipated take-rate
potential, and relative construction efficiency. Staff’s analysis indicates that the locally
controlled plan prioritizes areas with stronger demand and more year-round service
potential. By contrast, a BEAD-first approach would direct local match funds into BEAD-
eligible areas first, including some of the lowest-density and more seasonal areas
remaining in the buildout.
This distinction is important because seasonal or part-time customers generally
generate less annual revenue and have historically had a lower take rate than full-time,
year-round customers. Staff reviewed customer power meter usage as a residency
indicator to better understand how buildout sequencing may affect future revenue
growth. Areas with a higher percentage of seasonal or part-time occupancy are
expected to generate revenue more slowly than areas with stronger year-round
residency, even when those areas are more expensive to build, potentially further
delaying completion.
While BEAD would provide access to potential outside reimbursement, it would also
create additional long-term administrative and compliance costs that could reduce
revenue available for future construction. The staff-recommended plan avoids those
added grant-management risks and obligations, preserves local control, and allows the
Town to responsibly pursue future funding opportunities that may better align with
municipal operations and the remaining buildout needs.
Staff’s intent is to continue the buildout by first serving areas with lower initial
construction cost most likely to generate sustainable, year-round customer activity, then
using future revenue, available reserves, and other funding opportunities to support
construction into the remaining higher-cost areas while maintaining Trailblazer’s current
customer service levels and internal resources.
Advantages:
Proceeding with the staff-recommended local plan would:
● Preserve local control over construction timing, project phasing, scope, and cost
management.
● Use funds already earmarked for the project without adding BEAD
reimbursement or clawback exposure.
● Prioritize higher-density and higher-interest areas first, the majority of which are
not BEAD eligible.
● Generate customer revenue sooner to support continued buildout into harder-to-
serve areas.
● Avoid BEAD’s extensive long-tail federal reporting, documentation, audit, and
compliance obligations, which would add a grant-specific compliance layer
beyond Trailblazer’s existing federal, state, municipal, and internal operational
requirements and extend beyond the construction and funding period.
● Reduce risk to current Trailblazer operations and customer service quality by
avoiding the need to redirect staff capacity toward grant administration.
● Maintain flexibility to pursue future state, local, or federal funding opportunities
that may better align with municipal limitations and local priorities.
● Continue progress toward the Town’s original goal of completing the Trailblazer
buildout without assuming a risk profile that staff believes is disproportionate to
the expected benefit.
Disadvantages:
● Declining BEAD funding would mean the Town would not access up to $5.74
million in potential federal reimbursement currently associated with the award.
● The staff-recommended local plan also reaches fewer locations in the first portion
of Phase 4 than the BEAD plan. BEAD would allow construction to more BEAD-
eligible rural and high-cost locations first; however, those locations include areas
with lower density and more seasonal residency indicators, meaning lower
historic take rates, and lower expected revenue potential.
● Neither option completes the full remaining buildout. Both paths require a
second portion (sub-phase) to reach the remaining unbuilt areas. The primary
mitigating factor is that the staff-recommended plan is expected to create earlier
revenue from areas with higher demonstrated demand, improving Trailblazer’s
ability to continue reinvesting in the remaining buildout from a stronger position.
BEAD Grant Risk Considerations
While Power & Communications and Trailblazer have successfully managed prior
federal funding, staff and counsel identified several concerns with the BEAD agreement
that are materially different from prior grant experiences.
Key concerns include:
● Termination risk: The State may terminate the agreement at any time at its sole
discretion. In that event, the Town would only be entitled to payment for work
delivered and accepted as of the notice to terminate.
● Term uncertainty: There remains concern regarding how the initial two-year
agreement term aligns with the four-year project completion period and longer
term compliance requirements subject to audit and review.
● Exhibit G compliance burden: Exhibit G incorporates numerous federally
mandated requirements that the Town would be required to administer
throughout the project and, in some cases, well beyond construction closeout.
Failure to meet these requirements presents significant risk of non-
reimbursement, breach, or clawback.
● Breach and clawback exposure: Failure to meet any term of the federal award
may constitute a breach of the agreement. If the Town is unable to cure the
breach, potential damages may include return of grant funds.
● Administrative cost exposure: Internal administrative costs are predominantly
not reimbursable under BEAD, and staff anticipates significant outside grant
management support would most likely be necessary to manage the level of
reporting and compliance required.
● Operational burden: BEAD compliance would require substantial staff and
consultant capacity over the life of the grant, potentially limiting Trailblazer’s
ability to maintain current service levels and continue organic buildout work.
● Limits Future Funding Opportunities: Accepting BEAD may limit our ability to
apply for better-fitting, more manageable future funding opportunities due to the
agreement's restrictions.
Under the staff plan, the Town avoids BEAD’s extensive long-tail compliance burden,
which would convert existing and developing operational practices into federally
mandated requirements subject to documentation, audit, reimbursement review, and
potential clawback risk. These obligations include federal reporting and certifications,
Build America, Buy America (BABA) compliance, environmental and historic
preservation requirements such as NEPA/NHPA, cybersecurity and supply chain risk
management, low-cost service administration, outage reporting, federal interest filings,
and record retention. These requirements far exceed current existing federal, state,
municipal, and internal operational requirements and extend well beyond the
construction and funding period.
Action Recommended:
Staff recommends that the Town Board direct staff to decline the BEAD award and
proceed with the staff-recommended local buildout plan using the local funds previously
reserved for the BEAD match.
The recommended next step is for staff to notify the Colorado Broadband Office of the
Town’s decision regarding the BEAD award by June 24, 2026, then proceed with
finalizing the local Phase 4 buildout scope, budget, construction sequencing, and public
communication plan and using the earmarked Town funding to reopen construction.
Finance/Resource Impact:
The BEAD plan would require use of the $1.917 million local match allocation and would
provide access to up to $5.74 million in potential federal reimbursement. However,
reimbursement would be subject to eligible costs, accepted work, grant compliance,
reporting, closeout requirements, and potential retainage. The BEAD plan would also
create additional administrative and compliance costs, some of which are expected to
be non-reimbursable.
The staff-recommended local plan would use the same $1.917 million in previously
earmarked local funds directly for locally controlled construction. This option does not
provide external grant funding, but it avoids BEAD reimbursement risk, federal
compliance exposure, potential clawback, and anticipated non-reimbursable grant
administration costs.
Level of Public Interest:
Public interest in completion of the Trailblazer Broadband buildout remains high,
particularly in unbuilt areas where residents and businesses have continued to request
service availability updates since construction paused in 2023.
The staff-recommended plan prioritizes areas with stronger demonstrated organic
interest and higher expected take rates based on historical data, allowing Trailblazer to
bring service to more likely active, year-round residential and commercial subscribers
sooner while continuing to work toward the broader goal of completing the remaining
service area.
Because the remaining buildout affects residents and businesses who have waited
several years for service, staff anticipates continued public interest in the timing,
sequencing, and funding approach for Phase 4 construction.
Attachments:
1. BEAD vs. P&C Internal Plan Analysis & Recommendation
2. BEAD Location & Staff Plan Comparison Maps
3. State of Colorado Grant Agreement for BEAD Summary
4. Revised BEAD Grant Program Guidelines
5. FAQ: NTIA Benefit of the Bargain Round
BEAD
vs.
P&C INTERNAL
PLAN
TRAILBLAZER BROADBAND
Analysis & Review
Attachment 1
Cabinet Plus 400Kwh
(Feb usage)TB Passes, Total % Estimated 2nd
Homes
Client Leads
(Organic)
Leads to
Passes
Anticipated Yr 1
Customers —
40% FT
Anticipated Yr 1
Take Rate of
Total Passes
Construction Composition
Town Area - Not Covered in BEAD** Take Rates are estimated based on historical data
East Lane B 23 45 49%28 68%9 50%
Eagle Cliff:114 205 44%92 51%46 30%
West:68 139 51%50 42%27 19%
Glacier:60 162 63%83 44%24 30%
Copper Hill B 9 10 10%3 30%4 40%
Lockhart Mtn*17 45 62%5 30%7 16%*Expansion will be completed with EPHA housing project
HWY 34 - Olympus Heights to east edge of P&C service area
Big Thompson:59 133 56%54 41%24 18%
Brown Trout:53 118 55%25 22%21 18%
Bellevue:79 180 56%70 45%32 18%
Ski Rd area/Downtown Allenspark
Ski 137 242 43%100 37%55 30%
HWY 7 - Lily Lake to Taylor Rd (without Ski Rd area)
Big Owl 67 187 64%79 34%27 14%
Taylor:128 163 21%55 28%51 31%
Longs Peak:108 171 37%77 41%43 25%
Tahosa:75 186 60%46 25%30 16%
REMAINING CONSTRUCTION AREAS: BY THE NUMBERS
Primarily non-BEAD
eligible, non grant funded
Highest Organic Interest
Best Take Rate potential
Primarily BEAD eligible
Higher interest than other
BEAD funded areas
Included in both plans
BEAD eligible for service
Already built to the curb
Included in both plans
Most BEAD eligible
Most Seasonal premises
Lowest Organic Interest
Cabinet Cost to Build
Cabinet
TB Passes
(Electric
Meters), Total
BEAD Location
Coverage
BEAD Coverage
% of
Passes/Cabinet
Staff Plan
Coverage % of
Passes/Cabinet
Anticipated Yr 1
Customers —
40% FT
Estimated Cost
per Anticipated
Year-One
Customer
Construction Composition
Town Area - Not Covered in BEAD*
East Lane B, Copper
Hill B, Lockhart Mtn Trailblazer Covered 100 12 12%100%20 Included
Eagle Cliff:$430,681.00 205 2 1%100%82 $5,252.21
West:$195,511.00 139 2 1%100%56 $3,491.27
Glacier:$234,960.00 162 9 5%100%65 $3,614.77
HWY 34 - Olympus Heights to east edge of P&C service area
Big Thompson:$265,887.00 133 78 57%100%53 $5,016.74
Brown Trout:$358,907.00 118 90 76%100%47 $7,636.32
Bellevue:$440,550.00 180 53 29%100%72 $6,118.75
Ski Rd area/Dpwntown Allenspark
Ski Completed to Curb 242 242 100%100%55 *Curb to Premise
Only
HWY 7 - Lily Lake to Taylor Rd (without Ski Rd area)
Big Owl $729,031.00 187 187 100%Future 41 $17,781.24
Taylor:$673,478.00 163 163 100%Future 51 $13,205.45
Longs Peak:$726,887.00 171 171 100%Future 43 $16,904.35
Tahosa:$706,187.00 186 186 100%Future 30 $23,539.57
REMAINING CONSTRUCTION AREAS: BY THE NUMBERS
Lower cost per customer
to build
Highest Take Rate
potential
Included in Staff Plan
Future build with BEAD
Primarily BEAD eligible
Higher interest than other
BEAD funded areas
Included in both plans
BEAD eligible for service
Already built to the curb
Included in both plans
BEAD Covered
Lowest Take Rate Potential
Future build with Staff Plan
Highest Cost to Build
Planning estimates based on available Trailblazer lead data, February electric usage indicators, and historical take-rate assumptions. Not a formal revenue forecast.
Planning indicator BEAD-first approach Staff-recommended plan Why it matters
Primary build sequence Builds BEAD-eligible locations first Builds higher-interest, lower-cost areas first Both paths leave locations remaining, so
sequencing matters.
Use of local match funds
Local funds are used to unlock potential
reimbursement, subject to significant risk, grant
restrictions and compliance
Local funds are used directly for locally
controlled construction and release pace
Staff plan gives the Town more control over
where dollars create the greatest near-term
benefit.
Customer demand signal Includes lower-density areas with lower organic
interest
Prioritizes areas with stronger organic leads and
demonstrated interest
Higher demonstrated interest improves the
likelihood of customer conversion.
Residency / service stability signal Includes areas with more seasonal premises Prioritizes areas with more year-round
residency indicators
Full-time customers are more likely to maintain
year-round service.
Take-rate potential Lower anticipated take rate in several BEAD-
heavy areas
Greater anticipated take rate in higher density
areas
Better take rate improves the chance of more
active subscribers sooner and greater net
revenue potential.
Build efficiency Includes higher-cost, lower-density areas
earlier
Prioritizes areas with stronger demand relative
to construction cost
This maximizes the impact of the already-
allocated local funds.
Administrative burden
Adds long-term grant compliance,
reimbursement, and reporting obligations
requiring additional funds
Avoids BEAD-specific administrative overhead
More internal capacity remains available for
operations, customer service, and future
buildout planning.
Path to remaining buildout Future revenue must support remaining buildout
while also carrying grant compliance demands
Future revenue can be focused more directly on
reserves and continued internally paced
buildout
Staff plan better positions Trailblazer to keep
reinvesting locally.
Maximizing Local Match Funds
While BEAD remains tempting because of the potential outside funding, staff does not
believe the benefit outweighs the financial, operational, and long-term compliance risk
under the final agreement. The internal plan is the stronger business decision because it
reduces exposure, targets higher-return areas first, and keeps Trailblazer positioned to
continue expanding service responsibly.
Staff’s recommendation is to protect the Town’s investment,
build where revenue can begin working sooner, and continue the
broader buildout from a stronger and lower-risk position.
LAKE ESTES
MARYSLAKE
LILY LAKE
Taylor163 / 128
Ski242 / 137
Longs Peak171 / 108
Big Owl187 / 67
West2 / 68
BrownTrout90 / 53
Bellevue53 / 79
Glacier9 / 60 Eagle Cliff2 / 114
LockhartMountain1 / 17
Tahosa186 / 75
CopperHill B10 / 9
EastLane B1 / 23 BigThompson78 / 59
£¤36
£¤34
£¤36
£¤34
£¤34
£¤36
UV7
UV66
UV7
UV43
UV43
0 1 2
Miles
Updated: 6/9/2026
[
Town BoundaryTotal # of BEAD Eligible LocationsTotal # of Full-Time Electric Customers
Attachment 2