HomeMy WebLinkAboutRESOLUTION 01-25 Technical Review CommitteeRESOLUTION 01-25
A RESOLUTION OF THE TECHNICAL REVIEW COMMITTEE OF THE STANLEY
HISTORIC DISTRICT MASTER PLAN APPROVING WITH CONDITIONS THE
PRELIMINARY PACKAGE FOR THE STANLEY HOTEL AND MANOR HOUSE
EXPANSION.
WHEREAS, the Preliminary Package of the project referenced in the title of this
resolution meets the requirements of the Stanley Historic District Master Plan for a
Preliminary Package; and
WHEREAS, while adequate for a Preliminary Package, the materials include
insufficient detail for the Technical Review Committee (TRC) to determine whether
the plans meet the Final Package requirements of the Master Plan and the applicable
development agreement with regard to the conditions listed below; and
WHEREAS, a Final Package in conformance with the Stanley Historic District
Master Plan shall be submitted for TRC review and decision.
NOW, THEREFORE, BE IT RESOLVED BY THE TECHNICAL REVIEW
COMMITTEE OF THE STANLEY HISTORIC DISTRICT MASTER PLAN:
The Stanley Hotel and Manor House Expansion project Preliminary Package
meets the standards and requirements in the Stanley Historic District Master Plan and
Estes Park Municipal Code Chapter 17.44, subject to the variances below:
1. Design Guidelines - C. Building Design #9 states, in part: "White walls are not
permitted." TRC approves a variance to allow white walls as a design solution
advantageous to, and in conformity with, the intent of the Master Plan.
2. Parcel 1 Development Standards - Special Conditions #10 states, in part:
"Additional parking for Parcel 1 will occur behind the front facade of the Stanley
Hotel complex unless otherwise noted." TRC approves a variance to allow
parking in front of the front facade of the Stanley Hotel complex as a design
solution advantageous to, and in conformity with, the intent of the Master Plan.
The Stanley Hotel and Manor House Expansion project Preliminary Package is
approved, conditioned upon submittal, review, and approval of the following items in
conjunction with submittal, review, and approval by TRC of the Final Package for the
Stanley Hotel and Manor House Expansion:
1. Details on materials used in and around drainage facilities shall be provided with the
Final Package to demonstrate river rock and cobbles are used rather than angular
rip-rap or exposed concrete.
2. The Final Package shall quantify the proposed loss of significant trees and how that
loss will be offset with new plantings.
3. The Final Package shall include additional information to ensure slopes greater than
3-to-1 are properly stabilized.
4. Sight distance shall be shown on Final Package landscape plan to ensure
compliance with Master Plan requirements.
5. Details on site furnishing and paving shall be provided with the Final Package
application.
6. Limits of disturbance and tree protection standards shall be shown on construction
plans.
7. Additional landscaping, to the maximum extent possible, shall be provided between
parking lots B and C to soften views of the new additions.
8. The Final Package shall address how the visual impact of retaining wall height in
excess of 5 feet will be mitigated.
9. All comments in the Kellar Engineering letter dated October 22, 2025, concerning
the Traffic Impact Study shall be addressed with the Final Package.
10. All comments in the Public Works letter dated October 23, 2025, shall be addressed
with the Final Package, including but not limited to:
a. Concrete curb and gutter shall be constructed to match adjacent construction
on Steamer Parkway along the Lot 1 frontage, with a gutter width of 24 inches
where possible.
b. The sidewalk at the northeast corner of the new entrance shall continue south
to Steamer Parkway, including a curb ramp.
•^