Loading...
HomeMy WebLinkAbout07 Proposal-WhiteStone Construction_CompleteID Task Mode Task Name Duration Start Finish Predecessors 1 Notice to Proceed 1 day Thu 11/13/25Thu 11/13/25 2 Begin final design documents 60 days Fri 11/14/25 Thu 2/5/26 1 3 Submit Final design for review 1 day Fri 2/6/26 Fri 2/6/26 2 4 Enter into Construction Agreement 10 days Mon 2/9/26 Fri 2/20/26 3 5 Mobilization 1 day Wed 4/15/26 Wed 4/15/26 4 6 Site Prep and staging 2 days Thu 4/16/26 Fri 4/17/26 5 7 Demo existing stone wall, clear and grub at back wall 1 day Mon 4/20/26 Mon 4/20/26 6 8 Town of Estes to Set Boulders 2 days Tue 4/21/26 Wed 4/22/26 7 9 Salvage signage and pavers 1 day Tue 4/21/26 Tue 4/21/26 7 10 Excavate pond 1 day Thu 4/23/26 Thu 4/23/26 9,8 11 Trench for electric and Water 2 days Fri 4/24/26 Mon 4/27/26 10 12 Rough in Electric and Water 3 days Tue 4/28/26 Thu 4/30/26 11 13 Electrical Inspection 1 day Fri 5/1/26 Fri 5/1/26 12 14 Plumbing Inspection 1 day Fri 5/1/26 Fri 5/1/26 12 15 Backfill and install pond liner 3 days Mon 5/4/26 Wed 5/6/26 13,14 16 Place stone for water features 7 days Thu 5/7/26 Fri 5/15/26 15 17 Repair / Relay Salvaged Paving stones 4 days Thu 5/7/26 Tue 5/12/26 16SS 18 Reinstall / repair existing irrigation 2 days Wed 5/13/26 Thu 5/14/26 17 19 Final Electrical & PlumbingInspections 2 days Fri 5/15/26 Mon 5/18/26 18 20 Town to Install plantings3 days Tue 5/19/26 Thu 5/21/26 18,19 21 Fill New Pond 2 days Fri 5/22/26 Mon 5/25/26 20 22 Set Pond Equipment, Skimmers, Pumps Etc. 3 days Tue 5/26/26 Thu 5/28/26 21 23 Site Cleanup 2 days Fri 5/29/26 Mon 6/1/26 22 24 Demobilization 1 day Tue 6/2/26 Tue 6/2/26 23 F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Apr 12, '26 Apr 19, '26 Apr 26, '26 May 3, '26 May 10, '26 May 17, '26 May 24, '26 May 31, '26 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Schedule - Mrs Walsh's Date: Thu 10/9/25