HomeMy WebLinkAbout07 Proposal-WhiteStone Construction_CompleteID Task
Mode
Task Name Duration Start Finish Predecessors
1 Notice to Proceed 1 day Thu 11/13/25Thu 11/13/25
2 Begin final design
documents
60 days Fri 11/14/25 Thu 2/5/26 1
3 Submit Final design
for review
1 day Fri 2/6/26 Fri 2/6/26 2
4 Enter into
Construction
Agreement
10 days Mon 2/9/26 Fri 2/20/26 3
5 Mobilization 1 day Wed 4/15/26 Wed 4/15/26 4
6 Site Prep and staging 2 days Thu 4/16/26 Fri 4/17/26 5
7 Demo existing stone
wall, clear and grub at
back wall
1 day Mon
4/20/26
Mon
4/20/26
6
8 Town of Estes to Set
Boulders
2 days Tue 4/21/26 Wed
4/22/26
7
9 Salvage signage and
pavers
1 day Tue 4/21/26 Tue 4/21/26 7
10 Excavate pond 1 day Thu 4/23/26 Thu 4/23/26 9,8
11 Trench for electric
and Water
2 days Fri 4/24/26 Mon
4/27/26
10
12 Rough in Electric and
Water
3 days Tue 4/28/26 Thu 4/30/26 11
13 Electrical Inspection 1 day Fri 5/1/26 Fri 5/1/26 12
14 Plumbing Inspection 1 day Fri 5/1/26 Fri 5/1/26 12
15 Backfill and install
pond liner
3 days Mon 5/4/26 Wed 5/6/26 13,14
16 Place stone for water
features
7 days Thu 5/7/26 Fri 5/15/26 15
17 Repair / Relay
Salvaged Paving
stones
4 days Thu 5/7/26 Tue 5/12/26 16SS
18 Reinstall / repair
existing irrigation
2 days Wed
5/13/26
Thu 5/14/26 17
19 Final Electrical &
PlumbingInspections
2 days Fri 5/15/26 Mon
5/18/26
18
20 Town to Install plantings3 days Tue 5/19/26 Thu 5/21/26 18,19
21 Fill New Pond 2 days Fri 5/22/26 Mon 5/25/26 20
22 Set Pond Equipment,
Skimmers, Pumps Etc.
3 days Tue 5/26/26 Thu 5/28/26 21
23 Site Cleanup 2 days Fri 5/29/26 Mon 6/1/26 22
24 Demobilization 1 day Tue 6/2/26 Tue 6/2/26 23
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Apr 12, '26 Apr 19, '26 Apr 26, '26 May 3, '26 May 10, '26 May 17, '26 May 24, '26 May 31, '26
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Schedule - Mrs Walsh's
Date: Thu 10/9/25