HomeMy WebLinkAboutINSPECTION Accessory Building 1802 Widfire Rd Building F 2023-01-24INSPECTION CARD
Estes Park
170 MacGregor Ave Suite 230, Estes Park, CO 80517
POST THIS CARD IN A SAFE CONSPICUOUS LOCATION. PLEASE DO NOT REMOVE THIS NOTICE UNTIL ALL REQUIRED INSPECTIONS ARE MADE AND SIGNED OFF BY THE APPROPRIATE
AUTHORITY AND THE BUILDING IS APPROVED FOR OCCUPANCY. STAMPED APPROVED PLANS MUST BE AVAILABLE ON THE JOBSITE.
APPLICATION NO.:20-B-00016 TYPE:
Accessory Building -
Commercial ISSUED DATE:01/08/2021 EXPIRATION DATE:07/23/2023
PROJECT ADDRESS:1802 Wildfire Rd Building F, Estes park, CO 80517 PARCEL NO.:
OWNER:Widlfire Homes CONTRACTOR:Treeline Construction CONTRACTOR PHONE:(970) 227-0403
DESCRIPTION OF WORK:
new condo units
2 floors
16 bedrooms
1st flr- 4815sqft
2nd fl- 4265 sqft
garages- 4620 sqft
porch -96sqft
deck w/o roof- 684sqft
INSPECTION INSP
DATE
PASSED COMMENTS
Setbacks GR 1/28/2022 See Notes
Footings GR 1/28/2022
Foundation GR 1/21/2021
Rough Plumbing GR 7/2/2021
Rough Frame JG 7/19/2021
Wall Sheathing JG 8/10/2021
Firestopping GR 6/15/2021
Above Ceiling
Mechanical
JG 8/13/2021
Gas Pressure Test GR 1/28/2022
Drywall KD 6/23/2021
Final Mechanical GR 1/28/2022
Final Building GR 1/28/2022
Final Public Works/CO JW 1/27/2022 See Notes
Final Water/CO SR 1/25/2022
Final Sanitation/CO SP 1/24/2022
Final Building/CO JG 1/24/2023
Slab GR 6/9/2021
Drywall JG 7/7/2021 See Notes
Drywall JG 9/3/2021
INSPECTION INSP
DATE
PASSED COMMENTS
Footings GR 2/15/2021 See Notes
Grounding GR 1/28/2022
Underground Plumbing GR 1/28/2022
Rough Mechanical GR 1/28/2022
Gas Test GR 1/28/2022
Fire Resistive Wall
Assembly
JG 7/23/2021
Above Ceiling Electric GR 9/21/2021
Above Ceiling
Plumbing
JG 8/24/2021
Insulation JG 10/28/2021
Final Plumbing GR 1/28/2022
Energy Code
Compliance
GR 1/28/2022
Final Fire JJ 1/27/2022
Final Planning/CO LB 11/30/2022
Final P&C/CO GR 1/28/2022
Final Fire/CO JJ 1/27/2022
Final/CO JG 1/24/2023
Drywall KD 6/28/2021 See Notes
Insulation GR 1/28/2022
CONSTRUCTION TYPE:VB OCCUPANT LOAD:
Page 1 of 2
To request an inspection:
INSPECTION INSP
DATE
PASSED COMMENTS
Fire Resistive Wall
Assembly
JG 9/10/2021
Above Ceiling
Plumbing
JG 9/10/2021
Rough Frame JG 9/28/2021
Drywall JG 9/29/2021
Rough Frame JG 9/29/2021
Insulation GR 1/28/2022
Drywall GR 1/28/2022
Final Planning/CO GR 1/27/2022
INSPECTION INSP
DATE
PASSED COMMENTS
Drywall JG 9/8/2021
Firestopping JG 9/10/2021
Insulation GR 1/28/2022
Above Ceiling
Plumbing
JG 9/28/2021 See Notes
Firestopping JG 9/29/2021
Drywall JG 10/5/2021
Drywall (rc channel)JG 11/1/2021 See Notes
Drywall JG 11/10/2021