HomeMy WebLinkAboutDOCUMENTS Engery 453 E Wonderview B 2020-02-06COMcheck Software Version 4.1.1.0
Interior Lighting Compliance Certificate
Project Title:
2015 IECC
Project Type:New Construction
Construction Site:
453 E Wonderview Ave
Estes Park, CO 80517
Owner/Agent:Designer/Contractor:
Lawrence Smith
Electricon, LLC
37127 Cullison Ridge Rd
Severance, CO 80550
970-686-1004
larry@electricon-eng.com
Project Information
Energy Code:
PMCU - Estes Park
Reduced interior lighting power. Requirements are implicitly enforced within interior lighting allowance calculations.
Additional Efficiency Package(s)
Allowed Interior Lighting Power
A
Area Category
B
Floor Area
(ft2)
C
Allowed
Watts / ft2
D
Allowed Watts
(B X C)
1-Bank (Office)1615 0.74 1192
1192Total Allowed Watts =
Proposed Interior Lighting Power
E
(C X D)
D
Fixture
Watt.
A
Fixture ID : Description / Lamp / Wattage Per Lamp / Ballast
B
Lamps/
Fixture
C
# of
Fixtures
1-Bank (Office)
LED 1: A: Decorative LED Wall Sconce: Other:1 2 10 20
LED 2: B: Decorative LED Pendant: Other:1 4 11 44
LED 3: C: 6" LED Recessed Can: Other:1 2 13 26
LED 4: D: 6" LED Recessed Can: Other:1 19 20 380
LED 5: E: 2x2 LED Flat Panel Troffer: Other:1 7 32 224
LED 6: F: Decorative LED Pendant: Other:1 9 10 90
784Total Proposed Watts =
Interior Lighting Compliance Statement
Compliance Statement: The proposed interior lighting design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application. The proposed interior lighting systems have been
designed to meet the 2015 IECC requirements in COMcheck Version 4.1.1.0 and to comply with any applicable mandatory
requirements listed in the Inspection Checklist.
Name - Title Signature Date
Interior Lighting PASSES: Design 34% better than code
Project Title:
Data filename:
PMCU - Estes Park
C:\Electricon\20021 Premier Members CU\Design\PMCU.cck
02/06/20Report date:
51 ofPage
Inspection Checklist
Requirements: 73.0% were addressed directly in the COMcheck software
COMcheck Software Version 4.1.1.0
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 2015 IECC
Section
#
& Req.ID
Plan Review Complies?Comments/Assumptions
C103.2
[PR4]1
Plans, specifications, and/or
calculations provide all information
with which compliance can be
determined for the interior lighting
and electrical systems and equipment
and document where exceptions to
the standard are claimed. Information
provided should include interior
lighting power calculations, wattage of
bulbs and ballasts, transformers and
control devices.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C406
[PR9]1
Plans, specifications, and/or
calculations provide all information
with which compliance can be
determined for the additional energy
efficiency package options.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
PMCU - Estes Park
C:\Electricon\20021 Premier Members CU\Design\PMCU.cck
02/06/20Report date:
52 ofPage
Section
#
& Req.ID
Rough-In Electrical Inspection Complies?Comments/Assumptions
C405.2.1
[EL15]1
Lighting controls installed to uniformly
reduce the lighting load by at least
50%.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C405.2.1
[EL18]1
Occupancy sensors installed in
required spaces.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C405.2.1,
C405.2.2.
3
[EL23]2
Independent lighting controls installed
per approved lighting plans and all
manual controls readily accessible and
visible to occupants.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C405.2.2.
1
[EL22]2
Automatic controls to shut off all
building lighting installed in all
buildings.
Complies
Does Not
Not Observable
Not Applicable
Exception: Lighting controlled by occupancy sensors.
C405.2.3
[EL16]2
Daylight zones provided with
individual controls that control the
lights independent of general area
lighting.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement does not apply.
C405.2.3,
C405.2.3.
1,
C405.2.3.
2
[EL20]1
Primary sidelighted areas are
equipped with required lighting
controls.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement does not apply.
C405.2.3,
C405.2.3.
1,
C405.2.3.
3
[EL21]1
Enclosed spaces with daylight area
under skylights and rooftop monitors
are equipped with required lighting
controls.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement does not apply.
C405.2.4
[EL4]1
Separate lighting control devices for
specific uses installed per approved
lighting plans.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C405.2.4
[EL8]1
Additional interior lighting power
allowed for special functions per the
approved lighting plans and is
automatically controlled and
separated from general lighting.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
C405.3
[EL6]1
Exit signs do not exceed 5 watts per
face.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
PMCU - Estes Park
C:\Electricon\20021 Premier Members CU\Design\PMCU.cck
02/06/20Report date:
53 ofPage
Section
#
& Req.ID
Final Inspection Complies?Comments/Assumptions
C303.3,
C408.2.5.
2
[FI17]3
Furnished O&M instructions for
systems and equipment to the
building owner or designated
representative.
Complies
Does Not
Not Observable
Not Applicable
C405.4.1
[FI18]1
Interior installed lamp and fixture
lighting power is consistent with what
is shown on the approved lighting
plans, demonstrating proposed watts
are less than or equal to allowed
watts.
Complies
Does Not
Not Observable
Not Applicable
See the Interior Lighting fixture schedule for values.
C408.2.5.
1
[FI16]3
Furnished as-built drawings for
electric power systems within 90 days
of system acceptance.
Complies
Does Not
Not Observable
Not Applicable
C408.3
[FI33]1
Lighting systems have been tested to
ensure proper calibration, adjustment,
programming, and operation.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
PMCU - Estes Park
C:\Electricon\20021 Premier Members CU\Design\PMCU.cck
02/06/20Report date:
54 ofPage
Project Title:
Data filename:
PMCU - Estes Park
C:\Electricon\20021 Premier Members CU\Design\PMCU.cck
02/06/20Report date:
55 ofPage