DATE: February 21, 2008 No. of Pages:
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please
comment
RE: BP 8470 Della Terra
Pam,
I have attached the IBC commentary regarding Accessible Entrances (1105) and Accessible
Means of Egress (1007). Your concern as I understand it is the exits located at the north of
the building to be considered for the required 50% of entrances. Are the exits to the north
intended to be entrances for guests or will they be used for egress exit purposes? I believe
the codes intent is for 50% of entrances to be accessible. Please note for the 2 means of
egress from each space be accessible. Hope this helps.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Revised 10/25/04
COMMUNITY DEVELOPMENT DEPARTMENT
PO Box 1200 • Estes Park, CO 80517
Building Phone: 970-577-3735 • FAX: 970-586-0249
Planning Phone: 970-577-3721 • FAX: 970-586-0249
DATE: April 21, 2008 No. of Pages: 1
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please comment
RE: BP 8470 Della Terra
Pam,
In looking at the Suite 3, fully accessible unit, Detail 1/A-28 we have the following comments:
1. In the water closet area there is a wall shown cutting off part of the 56”x60” clear floor
space.
2. The bathtub would need to comply with ANSI 117.1 607. A clear floor space per 604.2
and grab bars per 607.4.2 if not providing a seat. There are no exemptions for a fully
accessible unit.
3. The seat in the shower as shown does not meet the intent of transferability. Basically a
space next to the seat is required in order for a side transfer. You might take a look at
608.4 for alternate roll-in-type showers and 610.3 shower compartment seats.
4. The location of the hand shower does not comply with 608.5. Look at 608.3.1 the control
wall is opposite the seat.
5. The control wall where the controls and hand shower is located require a horizontal and
vertical grab bar. See 608.3.1.
Steve might want to sketch up a few options to fax to us for review before any changes to the
plans are made. It’s a difficult configuration to get to comply. If you have any ideas, we are
more than willing to review them.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Revised 10/25/04
COMMUNITY DEVELOPMENT DEPARTMENT
PO Box 1200 • Estes Park, CO 80517
Building Phone: 970-577-3735 • FAX: 970-586-0249
Planning Phone: 970-577-3721 • FAX: 970-586-0249
DATE: February 26, 2008 No. of Pages: 3
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please comment
RE: BP 8470 Della Terra
Pam,
Will B. and I would be willing to meet with your Architect and you to review the issue of
continuity. I have not completed my re-review of the submitted drawings, but since you had a
question on the rated wall assembly in-between the sleeping units and mechanical area, I
wanted to clarify the Town’s interpretation of IBC 711 Horizontal Assemblies. The plans
submitted stop the rated horizontal assembly (floor/ceiling) located at the sleeping units. This
in not in compliance with IBC 711.4 which requires horizontal assemblies to be continuous
except as permitted by shaft enclosures (707.2), penetrations (712.4) or joints (713). To stop
the rated horizontal assembly at non-rated rooms would require the walls to be built as shaft
enclosures. Fireblocking does not meet this requirement. Shaft Enclosures per 707 are to be
continuous from the top of the floor/ceiling below to the underside of the floor or deck above.
The floor joists would have to be hangered off the shaft walls in order not to penetrate the
assembly.
Regarding your question on the sleeping unit/mechanical room walls, the sleeping unit walls
could be rated as detailed on IBC Table 720.1, 14.1.3 and be continuous to the floor/ceiling
deck to create a shaft wall. This would allow the mechanical room walls to have penetrations
and be fire blocked, but only protect the membrane or through penetrations into the shaft
walls and other rated assemblies. Please see attached.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Revised 10/25/04
COMMUNITY DEVELOPMENT DEPARTMENT
PO Box 1200 • Estes Park, CO 80517
Building Phone: 970-577-3735 • FAX: 970-586-0249
Planning Phone: 970-577-3721 • FAX: 970-586-0249
DATE: April 21, 2008 No. of Pages: 1
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please comment
RE: BP 8470 Della Terra
Pam,
Sheet A-8 question: Was this sheet changed? Arc of 10’? We did not receive a revised
sheet.
Sheet A-25 questions:
1. Detail 7/A-25 calls for WP-1407 listing for a 2x6 exterior walls rated one hour. Unable to
locate. Provide copy of listing.
2. Will WP-1407 be the listing for the exterior walls at the north exit Basement and 1st Floor
that are required to be one hour rated? If not, provide listing.
3. Detail 10, 12, and 13/A-25 shows shaft enclosure with 7/16” OSB on the inside of shaft
walls. Provide listing with this assembly for a one hour wall. Or, which listing on A-25 are
these walls to be constructed as?
Sheet A-30 questions:
1. Storage areas under stair are noted as one hour construction. Are walls to be constructed
as listing noted on A-25? There does not seem to be a ceiling listing that would work at
this condition on A-25. One layer of 5/8” type ‘x’ is not sufficient for a one hour rating.
Provide instruction or listing.
Sheet A-21 question: Detail added for floor/wall tile installation. IBC 1210.1 requires the floor
surface material to extend up the wall a minimum of 6”. The 90 degree corner shown does
not comply. A grout line at the floor/wall is not compliant with the intent of 1210.1. Justify or
revise.
If you have any questions, please contact me.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Revised 10/25/04
COMMUNITY DEVELOPMENT DEPARTMENT
PO Box 1200 • Estes Park, CO 80517
Building Phone: 970-577-3735 • FAX: 970-586-0249
Planning Phone: 970-577-3721 • FAX: 970-586-0249
DATE: April 21, 2008 No. of Pages: 1
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please comment
RE: BP 8470 Della Terra
Pam,
In looking at the stair enclosure from the basement to the reception (Detail on A-30) we have
the following questions:
1. The stair is a required mean of egress; it is required to be enclosed per 1019.1. It is to be
constructed as a one hour shaft enclosure IBC 707.
2. One layer 5/8” type ‘x’ gypsum board is shown on the ceiling. Provide listing that shows a
one hour rating for the assembly shown. Per 707.12 a shaft enclosure is allowed not to
extend to the underside of the roof deck if the shaft is enclosed at the top with same fire-
resistance-rating of the shaft. Justify.
3. Are these one hour walls to be constructed per the listing on A-25, detail 3/A-25? Provide
note.
4. Provide headroom as required by IBC 1009.2. Detail on sheet A-16 shows 6’ -8 ½”
horizontal from edge of nosing to ceiling/floor above. Code requires 6’-8” “measured
vertically from a line connecting the edge of the nosing”. Please verify required headroom.
If you have any questions, please contact me.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Revised 10/25/04
COMMUNITY DEVELOPMENT DEPARTMENT
PO Box 1200 • Estes Park, CO 80517
Building Phone: 970-577-3735 • FAX: 970-586-0249
Planning Phone: 970-577-3721 • FAX: 970-586-0249
DATE: April 23, 2008 No. of Pages: 6
To: Della Terra, LLC
From: Carolyn McEndaffer
Hill Country Custom Homes, Inc.
Attn: Pam Amelang
Plans Examiner/Code Compliance
Officer
Phone #: 970-493-5639 Phone #: (970) 577-3726
Fax #: 970-498-9837 Fax #: (970) 586-0249
cc: e-mail: cmcendaffer@estes.org
REMARKS: Urgent X For your review Reply ASAP Please comment
RE: BP 8470 Della Terra
Pam,
Sheet A-24:
1. Details for accessible ramps are not showing handrail extensions. IBC 1010.8 requires
handrails complying with 1009.11 if rise greater than 6”. 1009.11.5 Requires ramps and
stairways to have handrail extensions. Justify or revise.
I have included sections or ANSI and IBC commentary for your review.
If you have any questions, please contact me.
Sincerely,
Carolyn McEndaffer
Plans Examiner/Code Compliance Officer
Date: 02/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della plan review comments 2008.02.11.doc Page 1
• The plans and specifications submitted have been reviewed for conformance with
the following codes as amended and adopted by the Town of Estes Park.
Estes Valley Development Code (EVDC); adopted November 3, 1999; effective
Feb. 2000
• Applicant shall identify any variances granted by the Board of Adjustment.
Estes Park Municipal Code (EPMC)
Estes Park Municipal Code (EPMC), Chapters 14.12 and 14.20, adopt the
following codes including codes referenced therein (NFPA 13, NFPA 72, ASME
A17.1, ANSI A117.1-2003, etc.):
International Building Code (IBC), 2003 Edition
International Mechanical Code (IMC), 2003 Edition
International Fuel Gas Code (IFGC), 2003 Edition
International Plumbing Code (IPC), 2003 Edition
International Energy Conservation Code (IECC), 2003 Edition
National Electrical Code (NEC), 2005 Edition
Accessibility requirements of the Americans with Disability Act of 1991 are not part
of this review. The U. S. Department of Justice is the final authority for enforcement
of ADA requirements. It is the responsibility of owners, designers and contractors to
provide access to this facility and to comply with ADA requirements. This review has
addressed compliance with chapter 11 of the 2003 International Building Code and
the 2003 ANSI A117.1 standard for accessibility.
Date: 02/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della plan review comments 2008.02.11.doc Page 2
1. Sheet P2.2--Reviewer could not locate kitchen area gas service details. The gas line
system was sized on the assumption the kitchen area would be serviced from the
1.25” line upstream from the 1” line that tees into to the West. See Sheet P3.1.
Please comment.
2. Sheet P2.3—General Notes references Solar Panels. Provide detail on panels;
Location, specifications, etc.
3. Sheet P3.1--The total gas demand should be revised to include all kitchen
equipment, including appliances under the type 1 hood. To allow for future
demands, staff recommends the service demand should be a minimum 7,000MBH.
Please comment.
4. Sheet 3.1--Specifications for kitchen equipment under the type 1 hood have not
been provided. The gas line system was sized on the assumption all kitchen
equipment will not exceed 400,000 BTU of demand. Provide specs on type 1 hood,
grease duct, appliances, make-up air, fire suppression system, etc. ASAP. The
Town of Estes Park, Department of Building Safety requires type 1 hoods and
grease duct details to be stamped by a Colorado Design Professional. Design build
details will not be accepted for review, unless wet-stamped.
5. Sheet P5.1, Flag Note 2-- Reference to 4” gas line drops to the Potable Water
Heaters is not consistent with the 2’ drops shown on the schematic on Sheet P6.1.
Please comment.
6. Sheet5.1--The gas system design does not comply with the sizing requirements of
2003 IFGC, Table 402.4(1), which limits the pressure drop to 0.3 inch water
column. The system design does comply with Table 402.4(2) which allows a
pressure drop of 0.5 inch water column. The Engineer’s stamp on the plans has
been interpreted as his approval to use Table 402.4(2). If this is not accurate, please
comment.
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
2nd Review Original question numbers referenced. Commentary in blue +/or
highlighted items requiring clarification or justification. Please update plan with
changes made by Civil. I have included an email from Scott Zurn and Dave Shirk
for items they are still waiting on.
1. Application
a. It is the Department of Building Safety policy to require a fire-stop specialty
contractor when fire-resistive construction is involved. A fire-stop contractor
will be required. Submittal of Fire stop system listings for review and approval
is required prior to release of the permit. Owner is to specify if providing a fire-
stop contractor or fire-stop inspector and provide credentials of professionals for
review and approval. Submit all fire-stop systems for review and approval prior
to release of full permit.
7. Building Code Analysis – Fire Resistive Requirements
a. Per IBC 711.3 (exception) Horizontal floor assemblies separating dwelling
units or sleeping units shall be a minimum of ½ hour fire-resistance rated
construction for a fully sprinklered VB type of construction. Justify or revise. As
discussed with Pam, the horizontal floor/ceiling assemblies are required by IBC
711.4 to be continuous. Revise or justify termination and/or penetration of the
horizontal assembly as shown on A-25.
b. Corridors in R occupancy are required to have a ½ hour fire-resistance rating
per IBC Table 1016.1. Justify or revise. It is agreed that the Basement is the
only corridor per 1016. The basement corridor is required to be rated per Table
1016.1 (R occupancies greater than 10 occupant load) for .5 hours. The corridor
walls and ceiling are to be constructed as fire barriers. The reference to
exception #2 is for corridors within a sleeping unit. Justify or revise.
10. Building Code Analysis – Fire-Resistance Rated Construction
a. Provide copies of listings for all fire-resistance-rated assemblies, per IBC
703.2. (Concealed areas without sprinklers- per NFPA 13; Elevator shaft per
IBC, 707.14 and 707.4; Machine room per IBC 3006.4; Stair enclosures per
IBC, 1019.1.5; etc.)
• Listing provided on 2/A25 for the floor/ceiling assembly (L518) requires (2)
layers ½” gypsum board. Plan calls for 5/8” type ‘x’ gypsum board. Per
UL requirements (UL does not know what the effect of a modification may
have on the safety of the product or the continued validity of the UL
certification mark unless the field modifications have been specifically
investigated by UL. Unless UL investigates a modified product, UL cannot
indicate that the product continues to meet UL's safety requirements.)
Justify or provide alternative listing for horizontal floor/ceiling assemblies
that include insulation and resilient channel.
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
• Listings provided on 1/A25 and 3/A25 for interior one hour rated walls does
not include insulation or resilient channel as shown on 6/A25. These listing
are from the IBC Table 720.1 for prescriptive fire resistance. Per IBC 720.1
where materials that change the capacity for heat dissipation are
incorporated into a fire-resistance-rating assembly, fire test results or other
substantiating data shall be made available to the building official to shown
that the required fire-resistance-rating time period is not reduced. Justify
or provide listing that includes all components.
• Listing provided on 7/A25 for the exterior 1 hour rated wall 720.1 16-1.2
calls for mineral wool insulation. Per IBC 720.1 if the Owner is going to
use fiberglass insulation batts, submit fire test results or other substantiating
data to show that the required fire-resistance-rating time period is not
reduced. (Check the 2006 tables, I believe they added fiberglass and we can
accept the 2006 table as alternative method) Justify or revise.
• Will the shaft enclosure walls (Mechanical chases, Elevator and Elevator
Mechanical room be constructed per the listings on 3/A25 and 7/A25?
• Provide a listed assembly for the Roof/Ceiling of shaft enclosures
(Mechanical chases, Elevator and Elevator Mechanical room)
b. Note: Shaft enclosures are constructed as fire barriers Section 706. Shaft
enclosure walls extend from the top of the floor/ceiling assembly below to the
underside of the floor or roof deck above and are continuous through concealed
spaces per IBC 707.5. The wall is continuous deck to deck. Rated wall or
floor/ceiling assemblies can not be penetrated by non rated walls or non rated
floor/ceilings. Details shown on A10 and A25 do not extend to the underside of
the floor or roof deck above and the roof detail does not extend to the bottom of
the roof deck. Justify or revise.
c. Shaft enclosures for vertical fireplace flues with a fire-resistance rating of 1
hour penetrate the sleeping units floor/ceiling assemblies which have a ½ hour
fire-resistance rating, therefore IBC 712.4.3.1 (refers to non fire-resistance-
rated assemblies) does not apply. Justify or revise. Details and listed
assemblies for compliant construction are required. Fireplace Flues will not be
a shaft enclosure. Fireplace B Vents to be provided with a listed fire-stop
system at the ceiling and at the floor penetration. Submit listed assemblies to be
used. The fireplace enclosure walls are not to penetrate the floor/ceiling
assembly. If they do, equal protection for the walls and supporting construction
will be required.
d. Shaft enclosures are required for stairways that do not meet the exceptions of
IBC 707.2. The stairway from the basement to the main floor lobby area (This
stair is a vertical exit enclosure per IBC 1019 constructed as a fire barrier.
Detail on A16 does not show the fire barrier wall extending to the roof deck.
Justify or revise for compliance with IBC 706.4 Continuity of fire barrier walls),
the stairway from the kitchen to the basement exit access hallway (Agreed that
the Kitchen and main lobby stairs from the basement to the 1st floor are not shaft
enclosures, but both penetrate the horizontal assembly separating the Basement
from the 1st floor. The walls of the stairways to be constructed the same as
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
horizontal assemble penetrated. Justify or revise), and the accessible ramp to
the Wedding Room (The Basement level has a rated corridor that is continuous
through the ramp. Either provide a separation from the rated corridor or
construct the ramp as the corridor fire barrier. IBC 707.2 #7 Justify or revise)
are all required to be enclosed by a shaft enclosure, constructed as a fire
barrier to separate the basement from the 1st Story. Justify or revise. Details,
listed assemblies and opening protectives per Section 715 are required for
compliant construction.
e. Shaft enclosures with a fire-resistance rating of 1 hour are required for the
elevator shaft and mechanical chase. Details and listed assemblies are
required for compliant construction. Elevator shaft, Elevator mechanical room
and Mechanical Chases are to be constructed as Fire barriers IBC 707. Details
shown on A10, A11 and A25 do not extend to the underside of the floor/ceiling
deck above or terminate at the roof deck per IBC 707.12. Justify or revise.
f. Note: Per Fire Partition Continuity IBC 708.4, fire partitions are to extend
from the top of the floor assembly below to the underside of the floor or roof
deck above or to a fire-resistance-rated floor/ceiling or roof/ceiling assembly.
Rated wall or floor ceiling assemblies can not be penetrated by non rated walls
or floor/ceilings. Details shown on A25 and A29 have walls penetrating the
rated horizontal assembly. Any wall that penetrates a rated assembly is to
afford the same rating as the assembly penetrated. IBC 708.4. Justify or revise.
g. Walls separating sleeping units per IBC 708.3 (2) Fire Partitions are required
to have a ½ hour fire-resistive construction for fully sprinklered VB type of
construction. These walls per IBC 708.4 Continuity, are to extend from the top
of the floor assembly below to the underside of the floor or roof deck above or
to a fire-resistance-rated floor/ceiling or roof/ceiling assembly. Provide details
and listed assemblies for compliant construction. See above questions on
assemblies and compliant construction. Justify or revise.
h. Corridors in R occupancy are to be constructed as Fire Partitions IBC 708.1
(4) and have a fire-resistance rating of ½ hour per Table 1016.1. Provide
details for compliant construction. Provide detail if the corridor ceiling is
constructed as the walls 708.4 (3) or if they will be continuous per 708.4.
Provide detail on opening protectives Section 715 and penetrations Section
712. See 7b above. Justify or revise.
i. Horizontal Assemblies per IBC 711 should read floor/ceiling. Corrected.
j. Horizontal Floor/Ceiling IBC 711.3 assemblies are required to have a
minimum ½ hour fire-resistance rated construction separating dwelling units or
sleeping units for fully sprinklered VB type of construction. Continuity of
Horizontal Assemblies IBC 711.4 requires supporting construction to be
protected to afford the required fire-resistance rating of the horizontal assembly
supported and can not be penetrated by non rated walls. Provide detail and
listed assemblies for compliant construction. See above questions on assemblies
and compliant construction. Justify or revise.
k. Penetrations per IBC 712 should include walls (712.3) and floor/ceiling
penetrations (712.4). Noted on drawings.
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
l. Provide detail for Opening Protectives Section 715. Opening protectives has
specific requirements for door assemblies in rated assemblies. Submit a door
schedule that addresses all door requirements, including rated door
requirements and door operations per IBC 1008.1.8. Provided door schedule
on A29. Please refer to IBC 715 Opening Protectives and 1008.1.8 Door
Operations. Rated doors are required to be labeled, have rated frame and
hardware.
11. Building Code Analysis – Means of Egress
a. Corridors are listed as not required to be fire rated for group A. Nonseparated
uses per IBC 302.3.1 require all other code requirements to apply to each
portion of the building based on the use of the area, except that the most
restrictive applicable provisions of Chapter 9 shall apply to the nonseparated
uses. Means of Egress and all other code requirements except Chapter 9 is
calculated by the occupancy of the use area. Justify or revise. See above notes
on Basement Corridor.
b. Vertical Exit Enclosures IBC 1019, constructed as fire barriers with a fire-
resistance rating of 1 hour are required for stair from basement to reception
entry. Details for compliant construction including penetrations (1019.2),
ventilation (1019.1.3) and opening protectives (715.3.4 & Table 715.3) are
required. See above notes on stair from Basement to Reception Area.
c. Justify Accessible Ramp from basement to Wedding Room not constructed as a
Shaft Enclosure IBC 707.2? The ramp connects the basement to the Main Level
which is open to the Upper Level. See above notes on continuation of the rated
Basement Corridor.
d. Justify Exterior Exit Access stair from basement to north exit at grade
compliance with IBC 1022.6 (3). Separation from the interior of the building is
not required unless required by 1019.1. Per 1019.1 the basement is required to
be separated from the 2 stories above. Therefore, the exterior stairs have to be
separated as the interior stairs, or provide separation from the interior portions
of the building per IBC 1019.1.4. Justify or revise. A rated fire door was added
to the interior north exit access door. This does not comply in our opinion with
the protection requirements of 1022.6. I have attached a copy of the
commentary for your review. The exterior walls for a distance of 10’, both
horizontally and vertically, surrounding the exit access stair is required to have a
one hour fire-resistance-rating. All window and door openings that fall within
the 10’ distance from the stair edge as well as all window and door openings 10’
above the topmost landing must be protected with a minimum of ¾ hour fire-
resistive-rated opening protectives. Justify or revise.
e. Provide locations and detail for Accessible Means of Egress required per IBC
1007. Where more than one means of egress is required from any accessible
space, each accessible portion of the space shall be served by not less than two
accessible means of egress. A review will be required on submitted
documentation. 2 accessible means of egress are required for each floor. The
proposed exits for each floor will also be the accessible means of egress. The
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
Wedding room was redesigned with civil drawings for the footing and
foundation permit.
12. Building Code Analysis – Accessibility
a. A Detailed listing of the total number of existing units on this site, including
which ones are fully accessible, type A and type B units is required for review.
A site inspection of existing accessible units for compliance with code will be
required prior to acceptance. IBC Table 1107.6.1.1 Noted on plan is the
requirement for (1) Type A dwelling unit. IBC Table 1107.6.1.1 requires (1)
fully accessible unit for 1-25 total units on site. Group R-1 1107.6.1.1 requires
compliance with Table 1107.6.1.1. Type A dwelling units are for Group R-2
occupancy with more than 20 dwelling units. Justify or revise.
b. Insufficient detail provided to do a complete review of the accessible features.
Enlarged floor plans and elevations are required for review and compliant
construction. Submit enlarged floor plans for accessible features including
elevations for accessible toilet and bathing rooms and snack/serving areas. A
review is required of submitted details. See review for sheets A-26, A-27 and A-
29.
c. Per IBC 1103.1 Buildings and facilities on a site are to be accessible. Per IBC
1107.3 Rooms and spaces available to the general public or available for use by
residents are accessible spaces. This review is based on all facilities available
to the general public or residents will be accessible. Complies
d. Provide detail on the exterior accessible route. IBC 1104.1 Civil submitted
e. Provide detail on Accessible Entrances 1105.1. At least 50% of all public
entrances are to be accessible. Civil submitted
f. Provide detail on the interior accessible route for each floor. IBC 1104.3
Provided CA3
g. Provide door schedule that details compliance with 309 Operable Parts,
404.2.4 Thresholds at Doorways, 404.2.8 Door-Opening Force, and 404.2.9
Door Surface. Note added to A29 and CA1
h. Provide detail on IBC 1109.13 Controls, operating mechanisms and
hardware and IBC 1109.13.1 Operable windows. Note added
i. Provide detail on 703 Signs and IBC 1110.1 Signs. Note added
13. Building Code Analysis – Interior Environment
a. Provide detail showing compliance with IBC 1207 Sound Transmission. See
question above regarding fire-resistance assembly to include sound transmission
b. Provide detail showing compliance with IBC 1210 Surrounding Materials.
Clarify note added to A21 for compliant installation that floor surface is to
continue onto the walls at least 6 inches. No grout seams permitted at the
floor/wall intersection.
14. Building Code Analysis – Elevators
a. The elevator and the elevator machine room IBC 3002.1 are required to have a
1 hour fire-resistance-rated construction as a shaft enclosure. Shaft enclosures
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
are constructed as fire barriers Section 706. Shaft enclosure walls extend from
the top of the floor/ceiling assembly below to the underside of the floor or roof
deck above and are continuous through concealed spaces per IBC 707.5.
Rated wall or floor/ceiling assemblies can not be penetrated by non rated walls
or non rated floor/ceilings. Provide detail for compliant construction. Shafts
detailed on A-10 and A-25 does not comply with fire barrier continuity IBC
706.4. See notes above. OSB is shown as an alternative. Provide fire-resistive-
assembly for shaft walls for OSB option. Engineered truss shown at 12/A25
cannot penetrate the shaft enclosure wall per IBC 707.8.1 Prohibited
penetrations. If the shaft enclosure does not extend to the underside of the roof
deck of the building the shaft shall be enclosed at the top with construction of
the same fire-resistance-rating as the shaft IBC 707.12. Provide fire-resistive-
assembly for said construction. Justify or revise.
17. Exiting/Fire Partition Sheet
a. The mechanical room in-between sleeping units on all 3 floors is shown on the
floor plans as 1 hour fire rated walls. The Exiting/Fire Partition plan does not
reflect that. Justify or revise. Each boiler is 198.MBT. Walls adjacent to rated
corridor and horizontal floor/ceiling assembly are required to be rated. Justify
or revise.
b. Basement area marked as Wedding Storage only shows protection for part of
the room. The total area open to the area under the stairs is required to be
protected per IBC 1019.1.5. Justify or revise. Noted
c. Rating for stair from Kitchen to basement exit access area is showing the shaft
enclosure on the main floor walls. Per IBC 707.5 Continuity, the supporting
construction shall be protected to afford the required fire-resistance rating of
the element supported. Provide details showing compliance. See questions
above regarding penetration of the floor/ceiling assembly.
d. Provide required exiting from each accessory space. Provided
21. Sheet A-4, Main Floor Plan (These were not noted on the first review)
• The door shown for the north exit from the breakfast room requires 12”
clearance at the latch side if providing closer and latch. Will this door have
panic hardware? Justify or revise.
• Label Breakfast room.
• Verify door swing for vertical exit enclosure from basement to reception. If
furniture is located in the reception area this might be a problem for people to
get to the exit.
• Egress width per occupant added to CA1 states 1st floor hallway width to be
44”. Hallway width by central stair noted as 43 ½”. Justify or revise.
22. Sheet A-4, Main Floor Plan – Accessibility ANSI 117.1 (2003)
e. The Wedding Balcony is shown with a step up. Justify balcony area not
accessible as required by IBC 1103.1. All building facilities shall be accessible to
persons with physical disabilities. Provide location of detail for ramp shown to
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
Wedding Balcony that shows landings, length of ramp run, rise for each ramp run,
including dimensions etc. to demonstrate compliance with IBC 1010 and ANSI
117.1 405 Ramps. Will it be the same as A-24? If slope, handrail, width the same
could mark as typical. Clarify.
26. Sheet A-10, Section B & C
a. Structural & Energy not reviewed yet. Energy Compliance Documentation calls
for R-23 insulation in walls. Justify or revise note for R-20 insulation.
b. Shaft enclosures are constructed as fire barriers Section 706. Shaft enclosure
walls extend from the top of the floor/ceiling assembly below to the underside of
the floor or roof deck above and are continuous through concealed spaces per
IBC 707.5. The wall is continuous deck to deck. Rated wall or floor/ceiling
assemblies can not be penetrated by non rated walls or non rated floor/ceilings.
See questions above for shaft continuity. Detail on sheet A10 is not in
compliance.
d. These sections show the drywall stopping at the bottom of each floor/ceiling
assembly. The shaft wall assembly is required to continue to the deck of the
floor/ceiling assembly or the floor/ceiling assembly has to be rated to provide
equal protection. IBC 707.5 Justify or revise. See questions above for
horizontal assemblies continuity. Detail on sheet A10 is not in compliance.
e. These sections show the shaft enclosure stopping at the upper floor ceiling. Per
IBC 707.12 Enclosure at the top, the shaft enclosure is to extend to the
underside of the roof deck or be enclosed at the top with construction of the
same fire-resistance rating as the topmost floor or not less than required for the
shaft. Justify or revise. As noted above provide fire-resistance-rated assembly
for roof /ceiling of shaft enclosure or continue wall to roof deck. Detail on sheet
A10 is not in compliance.
27. Sheet A-11, Section D
b. Shaft enclosures are constructed as fire barriers Section 706. Shaft enclosure
walls extend from the top of the floor/ceiling assembly below to the underside of
the floor or roof deck above and are continuous through concealed spaces per
IBC 707.5. The wall is continuous deck to deck. Rated wall or floor/ceiling
assemblies can not be penetrated by non rated walls or non rated floor/ceilings.
See questions above for shaft continuity. Detail on sheet A11 is not in
compliance
c. Section for Solar trunk line/Boiler flue chase is to be a shaft enclosure. Provide
listed shaft wall assembly that complies with 1 hour fire-resistance rating. See
question above for one hour assembly.
d. This section shows the drywall stopping at the bottom of each floor/ceiling
assembly on Lodge Room side. The shaft wall assembly is required to continue
to the deck of the floor/ceiling assembly or the floor/ceiling assembly has to be
rated to provide equal protection IBC 707.5. Justify or revise. See questions
above for shaft continuity. Detail on sheet A11 is not in compliance
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
f. Revision of sections is required to show compliant details on fire-resistance-
rated construction as required for fire-barriers and fire-partitions. (Sleeping
unit separations and floor/ceiling assemblies) Revision of applicable sheets and
details is required for compliant construction.
31. Sheet A-15, Section I
a. A minimum of one section is required to show fire partition details as required
for walls separating sleeping units, corridors, and floor/ceiling assemblies.
• Detail Fire Partition Continuity IBC 708.4, fire partitions are to extend
from the top of the floor assembly below to the underside of the floor or roof
deck above or to a fire-resistance-rated floor/ceiling or roof/ceiling
assembly. Rated wall or floor ceiling assemblies can not be penetrated by
non rated walls or floor/ceilings.
• Detail Walls separating sleeping units per IBC 708.3 (2) Fire Partitions
are required to have a ½ hour fire-resistive construction for fully
sprinklered VB type of construction. These walls per IBC 708.4 Continuity
are to extend from the top of the floor assembly below to the underside of
the floor or roof deck above or to a fire-resistance-rated floor/ceiling or
roof/ceiling assembly. Provide details and listed assemblies for compliant
construction.
• Detail Corridors in R occupancy are to be constructed as Fire Partitions
IBC 708.1 (4) and have a fire-resistance rating of ½ hour per Table 1016.1.
Provide details for compliant construction. Provide detail if the corridor
ceiling is constructed as the walls 708.4 (3) or if they will be continuous per
708.4. Provide detail on opening protectives Section 715 and penetrations
Section 712.
• Detail Horizontal Floor/Ceiling IBC 711.3 assemblies are required to have
a minimum ½ hour fire-resistance rated construction separating dwelling
units or sleeping units for fully sprinklered VB type of construction.
Continuity of Horizontal Assemblies IBC 711.4 requires supporting
construction to be protected to afford the required fire-resistance rating of
the horizontal assembly supported and can not be penetrated by non rated
walls. Provide detail and listed assemblies for compliant construction.
• See notes above regarding Fire Partition Continuity for sleeping unit and
corridor walls. See notes above for horizontal floor/ceiling assemblies.
Details A-25 does not meet these requirements. Justify or revise.
32. Sheet A-16, Section J
a. Detail for vertical exit enclosure from Reception to Basement is required to
show compliant construction for a rated vertical exit enclosure.
b. Provide listed wall assembly that complies with 1 hour fire-resistance rating.
c. Note: Vertical exit enclosures are constructed as fire barriers Section 706.
Vertical exit enclosure walls extend from the top of the floor/ceiling assembly
below to the underside of the floor or roof deck above and are continuous
through concealed spaces per IBC 707.5. The wall is continuous deck to deck.
Date: 03/11/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra 2nd Review 2008.03.11.doc
Rated wall or floor/ceiling assemblies can not be penetrated by non rated walls
or non rated floor/ceilings.
d. This section does not show the top of the Vertical exit enclosure. Per IBC
707.12 Enclosure at the top, the exit enclosure is to extend to the underside of
the roof deck or be enclosed at the top with construction of the same fire-
resistance rating as the topmost floor or not less than required for the shaft.
Justify or revise.
• See notes above regarding Fire Barrier Continuity for walls and ceiling of
vertical exit enclosure. Details A-16, A-25 does not meet these requirements.
Justify or revise.
Sheets added to permit set for items not reviewed with 1st review:
1. Sheet A-26 Accessible Details
a. Detail for Men’s and Women’s Basement Accessible Bathroom do not comply
with the clear floor space required by ANSI 117.1 604.3. The rear wall is
required to have 60” minimum clear without any fixtures or obstructions and the
side wall is to have 56”. These distances are to facilitate transfer. Justify or
revise.
b. Please note grab bar locations below.
2. Sheet A-27 & A28 Accessible Details
a. 1/A27 and 2/A27 detail the top or rim of sink at 2’-10 ½”? ANSI 117.1 804.4
require sinks to comply with 606 which requires 34” maximum to rim of sink.
Justify or revise.
b. Side wall grab bars on these sheets do not comply with ANSI 117.1 604.5.1.
The distance from the back wall to the start of the 42” grab bar is required to be
12” maximum. Justify or revise.
c. Rear wall grab bars on these sheets do not comply with ANSI 117.1 604.5.2.
The minimum 36” grab bar is to be centered on the water closet with 12” on the
wall side and 24” on the other. This placement depends on where the Water
Closet is set at 16” to 18” off the wall. Justify or revise.
d. Provide a dimension for the Wheelchair Accessible Compartment wall a
minimum of 9” A.F.F. per 605.8.5.
e. Verify dimension for the Wheelchair Accessible Compartment door clearance
as shown in detail 604.8.3. 3 1/8” shown, code requires 4”. Justify or revise.
f. Justify location of door for Wheelchair Accessible Compartment door shown in
Men’s Toilet room. 604.8.3 Requires the door to be located farthest from the
water closet. Justify or revise.
3. Sheet A-30 Stair Detail
a. Provide dimensions for landings showing compliance with IBC 1009.4 the
width of the landing shall not be less than the stairway served measured in the
direction of travel. Justify or revise.
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PROJECT CONTACTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 1
OWNER & GENERAL CONTRACTOR Della Terra, LLC
Hill Country Custom Homes, Inc.
Contact: Pamela Amelang
3501 Fall River Road
Estes Park, CO 80517
Phone: 970-586-4563
Phone: 970-493-5639
Cell: 970-566-9424
Fax: 970-498-9837
Email: pamelang1@yahoo.com
ARCHITECT Architecture West, LLC
Stephen J Steinbicker, AIA
Phone: 970-207-0424
Fax: 970-207-9191
Email: archwest@comcast.net
CIVIL ENGINEER Shear Engineering Corporation
Contact: Brain W. Shear, Mike Cole
4836 So. College Ave. Suite 12
Fort Collins, CO 80525
Phone: 970-226-5334
Phone: 970-226-4451
Fax: 970-282-0311
Email: mcole@shearengineering.com
STRUCTURAL ENGINEER Weeks & Associates
Contact: Gary Weeks
4700 South College Ave. #1
Fort Collins, CO 80525
Phone: 970-225-2422
Fax: 970-225-2622
Email:
MECHANICAL & PLUMBING ENGINEER Integrated Mechanical, LLC
Contact:
223 Linden Street, Suite 204
Fort Collins, CO 80524
Phone: 970-556-0570
Cell: 970-498-9837
Fax: 800-656-4359
Email:
ELECTRICAL ENGINEER APS, Inc. Electrical Engineers
Contact:
7726 Park Ridge Circle
Fort Collins, CO 80528
Phone: 970-206-0369
Fax:
Email:
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
APPLICABLE CODES
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 2
• The plans and specifications submitted have been reviewed for conformance with
the following codes as amended and adopted by the Town of Estes Park.
Estes Valley Development Code (EVDC); adopted November 3, 1999; effective
Feb. 2000
• Applicant shall identify any variances granted by the Board of Adjustment.
Estes Park Municipal Code (EPMC)
Estes Park Municipal Code (EPMC), Chapters 14.12 and 14.20, adopt the
following codes including codes referenced therein (NFPA 13, NFPA 72, ASME
A17.1, ANSI A117.1-2003, etc.):
International Building Code (IBC), 2003 Edition
International Mechanical Code (IMC), 2003 Edition
International Fuel Gas Code (IFGC), 2003 Edition
International Plumbing Code (IPC), 2003 Edition
International Energy Conservation Code (IECC), 2003 Edition
National Electrical Code (NEC), 2005 Edition
Accessibility requirements of the Americans with Disability Act of 1991 are not part
of this review. The U. S. Department of Justice is the final authority for enforcement
of ADA requirements. It is the responsibility of owners, designers and contractors to
provide access to this facility and to comply with ADA requirements. This review has
addressed compliance with chapter 11 of the 2003 International Building Code and
the 2003 ANSI A117.1 standard for accessibility.
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 3
I. OCCUPANCY CLASS(ES) &
USE(S)
IBC, Chapter 3
R-1/A-2/A-3 Non-separated Uses
Designed for A-3 requirements.
Approved
II. TYPE OF CONSTRUCTION
IBC, Chapter 6
VB
Approved
III. HEIGHT LIMITATION
IBC, TABLE 503 ( 40+20 )
EVDC MAXIMUM 30’
Height increase per 504.2 =60’
Actual Height 40’
Approved
IV. STORY LIMITATION
IBC, TABLE 503 (1 )
Story increase per 504.2 = 2
2 Stories & Basement
Approved
V. AREA LIMITATION
IBC, TABLE 503
(6000 s.f./floor)
R-1 6480 s.f. Basement
5377 s.f. 1st floor
5516 s.f. 2nd floor
A-2 2024 s.f. 1st floor
A-3 2746 s.f. 1st floor
15663 total s.f. (w/o Base)
Building Total = 22143 s.f.
Approved
A. INCREASE FOR
SEPARATION Section 506
Not taken Approved
B. INCREASE FOR SPRINKLER
Section 506
Yes 6000 + (6000 x 200%) = 18000
any one story max.
36000 total s.f.
No reduction in requirements
from 601 (d) allowed if used.
Approved
2 stories
VI. FIRE-RESISTANCE
IBC, 302.1.1.1/ Table 302.1.1
Incidental Uses =
IBC Table 601 = (0 hrs.)
IBC Table 602 = (0 hrs.)
Incidental Use areas per plan
Areas over 100 s.f. = smoke seal &
self closing door per 302.1.1.1.
VB = 0
VB > 30’ to property line all sides.
Approved
VII. INTERIOR FINISHES
IBC, Chapter 8 Table 803.5
Decorations and Trim
805.1
Approved
A. SPRINKLERED
A-2 & A-3 B/B/C
R-1 B/C/C
VIII.
FIRE PROTECTION
SYSTEMS
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 4
A. AUTO SPRINKLER SYSTEM
IBC Table 302.1.1
1 HR./Sprinklered
IBC 903.2.1.3 NFPA 13
Provided
Per 903.3.1.1 NFPA 13 System
Approved
B. FIRE ALARM SYSTEM
IBC, Section 907 NFPA 72
907.2.1 Group A
907.2.8 Group R-1
Provided
Approved
IX. MEANS OF EGRESS
IBC, Chapter 10
Approved
A. OCCUPANT LOAD
Table 1004.1.2
Basement R-1 200 gross
1st floor R-1 200 gross
1st floor A-3 7 net
1st floor A-2 15 net
2nd floor R-1 200 gross
509 total occupants
30 Occupants
27 Occupants
289 Occupants
135 Occupants
28 Occupants
Approved
B. EXIT WIDTH
IBC, Table 1005.1
Stairs = .2”x 509 = 101.8”
Other = .15”x 509 = 76.35”
Min. Door Exit Width 36”
Min. Stair Width 44” 1009.1
Serving <50 = 36” 1009.1 (1)
Basement 36”
1st & 2nd floor 44”
Approved
Door schedule
A-29
C. EXIT TRAVEL DISTANCE
IBC, Table 1015.1
Sprinklered 250’ max.
IBC, 1013.3 Common Path
A-3/R-1 75’ max.
<250’ from furthest point
<75’
Approved
D. CORRIDORS
IBC 1016.1/ Table 1016.1
Width IBC 1016.2
A-3 0 hours w/sprinkler
R-1 .5 hours w/sprinkler
44” minimum unless occupant
capacity <50 = 36”
Basement
Corridor is a fire
partition.
E. # OF EXITS REQUIRED
IBC, Table 1018.1 (2) per level
IBC, Table 1018.2 (2) per level
IBC, Section 1014 (2) per level
2 exits/exit access per floor
provided R-1
+2 exits/exit access provided A-3
+2 exits/exit access provided A-2
Approved
F. EXITS SEPARATION
IBC, 1014.2.1 (2 Exits)
1/3 Distance 1014.2.1 (2)
Mech. Rm. <500 sq. ft.
Approved
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 5
G. STAIRWAYS
IBC, 1009
IBC, 1009.8 Winders
IBC, 1009.11 Handrails
Minimum Width 44”
Not permitted
Detail on A-30
Approved
H. VERTICAL EXIT
ENCLOSURE
IBC 1019
IBC 1023.1 (1) Exit Discharge
1019.1 (8) 2 Floors Only
1019.1 (9) 2 Means of Egress Each
floor
707.2 (7.4) Open to Corridor – R
707.2 (7.6) Sep. from Floor
Opening serving other floors.
Exit Enclosure to Reception Area
Basement Stair to
Reception is a
Vertical Exit
Enclosure
required being a
fire barrier.
Approved
X. ACCESSIBILITY
1 type B staff quarters
1 Fully Accessible Sleeping Unit
Approved
A. ROUTES TO (EXTERIOR) See Site Approved
B. ENTRANCES Reception Area Accessible
Wedding Room 2 accessible
Approved
50% required
C. MEANS OF EGRESS Accessible egress 2 each floor
R = >10 (2) exits each floor
Approved
D. ROUTES THROUGH Provided
Approved
E. RESTROOMS Provided
Unisex within 500’ of Wedding
Room facilities
Approved
Approved
F. REACH RANGES noted Approved
G. FEATURES Provided Approved
H. RAMP (INTERIOR) Details on A-24 Approved
XI. PLUMBING FIXTURES
Table 2902.1
Provided on Code Analysis
Approved
XII. ENERGY COMPLIANCE
IECC 2003
Submitted
Approved
XIII. ROOF COVERING
Min. Class C Table 1505.1
Class A Asphalt Approved
Date: 04/29/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Code Anaylsis 2004.04.29.doc Page 6
XIV. DEFERRED SUBMITTALS
A. Air Balance Report
B. Automatic Sprinkler System
NFPA 13
Approved by State of Colorado
Submit plans to State for review
C. Fire Alarm System NFPA 72 Submit plans to Will Birchfield,
CBO for review and approval
D. Type 1 Hood suppression system
& Duct Construction
Submit Drawings specific to this
Type 1 Hood installation for
review and approval.
E. Interior Finishes
F. Elevator Approved by State of Colorado
Submit plans to State for review
Michael Stewart
303-318-8530
G. Truss Specifications
H. Solar Specifications
I. As-Built Plans
XV. SPECIAL INSPECTORS
A. Elevator
B. Fire Protection Engineer
Sprinkler System
C. Concrete/Masonry Required per Structural Engineer
D. Welding Required per Structural Engineer
E. Bolting/Anchors Required per Structural Engineer
F. Health Department & State
Engineer Approval of Well
Water
G. Fire Alarm Special Contractor to Commission
the System.
Date: 02/19/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra plan review comments 2008.02.19.doc
Pam,
In order to expedite any revisions that may be required I wanted to fax questions for
each sheet as soon as I have them. I have included copies from the 2003 ANSI 117.1
for clarification of what the code requires.
A review will be done on the submitted responses to the questions for this review.
Additional plan review fees will be assessed for items requested at 1st review.
1. Civil Sheet 1 of 1– Exterior Accessibility Dated 02/11/2008
a. Details provided are insufficient:
1. Accessible route (ANSI 117.1 2003, 402) location, dimensions, slope
a. Provide width of accessible route sidewalk shown east side of
building in front of (3) accessible parking spaces. 2.0% slope is
shown at south end. Is the entire sidewalk and porch entry not to
exceed the 2% slope?
b. An accessible route is required from the accessible parking space
shown at the east parking group to the building entrance. Slope on
driveway is shown at 5.16%. This exceeds the allowed 1:20 or 5%
maximum for an accessible route. Justify. The elevation listed at
driveway next to Entry Porch is 305.00. Are you going to need a
curb ramp to get from the driveway to the Porch? If a curb ramp is
going to be provided as noted in Architectural, details including
slope, cross slope, dimensions, and landings are required. See
Attached.
c. Provide elevation of Entry Porch and Entry Vestibule. Architectural
plans show step. These both are required to be on an accessible
route. Threshold maximum is ½”. Will both slabs be at 305.33?
Clarify.
d. Accessible route at Wedding Chapel shows the Wedding Chapel slab
to be at 305.33 and the sidewalk to be at 305? Provide maximum
slope and cross slope if greater than 1:48(2%) around Wedding
Chapel exits. Provide elevation at exits, a landing is required with a
maximum slope and cross slope of 1:48.
2. Van accessible & vehicle parking space/spaces (ANSI 117.1 2003,
502.2) dimensions, slope & marking
a. A van accessible space is required for every 6 accessible spaces.
(IBC 1106.5) Provide location, dimensions, access aisle, marking
and signage of Van Accessible space. Existing spaces shown do not
comply with 502.2 Van Accessible Space. See Attached
b. Pavement marking is required with the international symbol of
accessibility. Provide detail.
3. Access aisle (ANSI 117.1 2003, 502.4) dimensions, slope & marking
a. Provide width dimension. See Attached.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
4. Signage (ANSI 117.1 2003, 502.7 & IBC 1110.1 2003)
a. Provide required height of signage for Van Accessible space and
reference for compliance for other parking signage with ANSI 117.1
703.6.3.1
5. Curb ramp details (ANSI 117.1 2003, 406) if part of accessible route
a. See accessible route above. See Attached.
6. Ramp details (ANSI 117.1 2003, 405) width, landings, rise, run, slope,
handrails & edge protection
a. It is understood there will be no ramps for exterior accessibility.
7. What is the total number of parking spaces provided? How many
Accessible spaces are provided? (IBC 1106)
a. Provided sheet 1 of 9
8. Will there be a passenger loading space at the Wedding Room? (IBC
1106.7)
a. Provide compliance with IBC 1106.7 which refers to ANSI 117.1
503. Provide access aisle, width dimensions, slope, marking and
connection to accessible route. See Attached.
9. Will there be an accessible route on the exterior to the Wedding Room?
a. Provide width dimension and maximum slopes.
b. The exit is not shown at north side? Exit discharge is to provide direct and
unobstructed access to a public way. IBC 1023.6
c. The TOW shown for ‘D’ walls at this north exit is different than sheet A23
Grade Plane. TOW shown at 8.83’ for patio & retaining wall vs. ‘D’ (A23)
TOW shown at 2.33’. Quick calculations do not seem to impact the grade plane
significantly. Please verify if the TOW shown on site 1 of 1 for these locations
is correct.
d. There is a retaining wall detail provided on Grading Permit G-011-07 page 8 of
9. The sheet was not wet stamped. Provide (2) wet stamped details for
retaining walls >4 feet. All retaining wall over 4 feet require a permit and
engineering. This can be included on site sheet 1of 1 or you can provide an 8
½” x 11”.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PROJECT CONTACTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 1
OWNER & GENERAL
CONTRACTOR
Della Terra, LLC
Hill Country Custom Homes, Inc.
Contact: Pamela Amelang
3501 Fall River Road
Estes Park, CO 80517
Phone: 970-586-4563
Phone: 970-493-5639
Cell: 970-
Fax: 970-498-9837
Email: pamelang1@yahoo.com
ARCHITECT Architecture West, LLC
Stephen J Steinbicker, AIA
Phone: 970-207-0424
Fax: 970-207-9191
Email: archwest@comcast.net
CIVIL ENGINEER Shear Engineering Corporation
Contact: Brain W. Shear, Mike Cole
4836 So. College Ave. Suite 12
Fort Collins, CO 80525
Phone: 970-226-5334
Phone: 970-226-4451
Fax: 970-282-0311
Email: mcole@shearengineering.com
STRUCTURAL ENGINEER Weeks & Associates
Contact: Gary Weeks
4700 South College Ave. #1
Fort Collins, CO 80525
Phone: 970-225-2422
Fax: 970-225-2622
Email:
MECHANICAL & PLUMBING
ENGINEER
Integrated Mechanical, LLC
Contact:
223 Linden Street, Suite 204
Fort Collins, CO 80524
Phone: 970-556-0570
Cell: 970-498-9837
Fax: 800-656-4359
Email:
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PROJECT CONTACTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 2
ELECTRICAL ENGINEER APS, Inc. Electrical Engineers
Contact:
7726 Park Ridge Circle
Fort Collins, CO 80528
Phone: 970-206-0369
Fax:
Email:
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PRE-CONSTRUCTION MEETING
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 3
A Pre-construction meeting is required prior to permit issuance. The Permit
Applicant or General Contractor is responsible to schedule the Pre-construction meeting.
Town Staff will provide the location and facilitate the meeting. (Claude Traufield 970-
577-3722).
It is recommended all contractors attend; including, but not limited to:
General, Excavating, Infrastructure, Concrete/Masonry, Plumbing, Framing, Mechanical,
Fuel Gas, Electrical, Exterior Flashing/Veneer, Fire Alarm, Sprinkler, Roofing,
Insulation, Drywall, and Fire Stop Systems.
Project Designers and owners are welcome and strongly encouraged to attend.
All parties involved in the project will be accountable for information discussed at the
Pre-construction meeting, whether or not they attend.
Plan Review Comments and Department Policies will be discussed at the Pre-
construction Meeting. The Pre-construction meeting notes identify some important
information on the plans and Town policies. They require no designer/owner response.
However, the Code Review and Plan Review Comments require Designer response and
Town approval prior to permit issuance.
While it is recognized and understood that the final authority for interpretation and
enforcement of the provisions of the building codes rest with the Chief Building Official,
open discussion of differing interpretations is encouraged and welcomed.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
APPLICABLE CODES
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 4
• The plans and specifications submitted have been reviewed for conformance with
the following codes as amended and adopted by the Town of Estes Park.
Estes Valley Development Code (EVDC); adopted November 3, 1999; effective
Feb. 2000
• Applicant shall identify any variances granted by the Board of Adjustment.
Estes Park Municipal Code (EPMC)
Estes Park Municipal Code (EPMC), Chapters 14.12 and 14.20, adopt the
following codes including codes referenced therein (NFPA 13, NFPA 72, ASME
A17.1, ANSI A117.1-2003, etc.):
International Building Code (IBC), 2003 Edition
International Mechanical Code (IMC), 2003 Edition
International Fuel Gas Code (IFGC), 2003 Edition
International Plumbing Code (IPC), 2003 Edition
International Energy Conservation Code (IECC), 2003 Edition
National Electrical Code (NEC), 2005 Edition
Accessibility requirements of the Americans with Disability Act of 1991 are not part
of this review. The U. S. Department of Justice is the final authority for enforcement
of ADA requirements. It is the responsibility of owners, designers and contractors to
provide access to this facility and to comply with ADA requirements. This review has
addressed compliance with chapter 11 of the 2003 International Building Code and
the 2003 ANSI A117.1 standard for accessibility.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
CODE REVIEW
REQUIRED PROPOSED COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 5
I. OCCUPANCY CLASS(ES) &
USE(S)
IBC, Chapter 3
R-1/A-3Non-separated Uses
Designed for A-3 requirements.
Approved
A-2?
II. TYPE OF CONSTRUCTION
IBC, Chapter 6
VB
Pending
III. HEIGHT LIMITATION
IBC, TABLE 503 ( 40+20 )
EVDC MAXIMUM 30’
Height increase per 504.2 =60’
Actual Height 40’
Pending Planning
sign off
IV. STORY LIMITATION
IBC, TABLE 503 (1 )
Story increase per 504.2 = 2
3 Stories shown? Or
2 Stories & Basement
Pending
Basement does not
comply w/ 502.1
definitions.
V. AREA LIMITATION
IBC, TABLE 503
(6000 s.f./floor)
R-1 6837 s.f. 1st floor
5809 s.f. 2nd floor
A-3 2746 s.f. 1st floor
15392 total s.f.
+ R-1 basement 6593 s.f.
Building Total = 21985 s.f.
Pending
determination of
basement or story.
Verify square
footages shown.
A. INCREASE FOR
SEPARATION Section 506
Not taken Approved
B. INCREASE FOR SPRINKLER
Section 506
Yes 6000 + (6000 x 200%) = 18000
any one story max.
54000.00 total s.f. shown
No reduction in requirements
from 601 (d) allowed if used.
Approved
X # of stories
x2=36000 total s.f.
+ basement.
VI. FIRE-RESISTANCE
IBC, 302.1.1.1/ Table 302.1.1
Incidental Uses =
IBC Table 601 = (0 hrs.)
IBC Table 602 = (0 hrs.)
Incidental Use areas per plan
Areas over 100 s.f. = smoke seal &
self closing door per 302.1.1.1.
VB = 0
VB > 30’ to property line all sides.
Approved
VII. INTERIOR FINISHES
IBC, Chapter 8 Table 802.5
Not Noted on plan
Provide detail
A. SPRINKLERED
A-3 B/B/C
R-1 B/C/C
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
CODE REVIEW
REQUIRED PROPOSED COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 6
VIII.
FIRE PROTECTION
SYSTEMS
A. AUTO SPRINKLER SYSTEM
IBC Table 302.1.1
1 HR./Sprinklered
IBC 903.2.1.3 NFPA 13
Provided
Per 903.3.1.1 NFPA 13 System
Approved
B. FIRE ALARM SYSTEM
IBC, Section 907 NFPA 72
907.2.1 Group A
907.2.8 Group R-1
Not noted on plan
Pending
Most restrictive
applies
IX. MEANS OF EGRESS
IBC, Chapter 10
Pending
A. OCCUPANT LOAD
Table 1004.1.2
Basement R-1 200 gross
Basement A-3 TV 15 net
1st floor R-1 200 gross
1st floor A-3 7 net
1st floor A-2 15 net
2nd floor R-1 200 gross
343 total occupants
33 Occupants
?
34 Occupants
247 Occupants
?
29 Occupants
Pending –
Occupant load
calculations for
use area
B. EXIT WIDTH
IBC, Table 1005.1
Stairs = .2”x 343 = 6.3”
Other = .15”x 343 = 4.2”
Min. Door Exit Width 36”
Min. Stair Width 44” 1009.1
Serving <50 = 36” 1009.1 (1)
Pending occupant
load revision
Door schedule
w/req’d hardware
C. EXIT TRAVEL DISTANCE
IBC, Table 1015.1
Sprinklered 250’ max.
IBC, 1013.3 Common Path
A-3/R-1 75’ max.
<250’ from furthest point
<75’
Approved
D. CORRIDORS
IBC 1016.1/ Table 1016.1
Width IBC 1016.2
A-3 0 hours w/sprinkler
R-1 .5 hours w/sprinkler
44” minimum unless occupant
capacity <50 = 36”
Pending
Fire Partitions are
required for
corridors
E. # OF EXITS REQUIRED
IBC, Table 1018.1 (2) per level
IBC, Table 1018.2 (2) per level
IBC, Section 1014 (2) per level
2 exits per floor provided R-1
+2 exits provided A-3
Review of spaces required.
Pending
Occupant load by
use area is
required.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
CODE REVIEW
REQUIRED PROPOSED COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 7
F. EXITS SEPARATION
IBC, 1014.2.1 (2 Exits)
1/3 Distance 1014.2.1 (2)
Mech. Rm. <500 sq. ft.
Approved
G. STAIRWAYS
IBC, 1009
IBC, 1009.8 Winders
IBC, 1009.11 Handrails
Minimum Width 44”
Not permitted
No detail provided
Pending
Landings required
at change of
direction.
Details required.
H. VERTICAL EXIT
ENCLOSURE
IBC 1019
IBC 1023.1 (1) Exit Discharge
1019.1 (8) 2 Floors Only
1019.1 (9) 2 Means of Egress Each
floor
707.2 (7.4) Open to Corridor – R
707.2 (7.6) Sep. from Floor
Opening serving other floors.
Exit Enclosure to Reception Area
Pending –
Basement Stair
open to floor
opening of 1st
Story.
Approved
X. ACCESSIBILITY Pending
A. ROUTES TO (EXTERIOR) Insufficient detail Pending
B. ENTRANCES Reception Area
Wedding Room?
Pending
50% required
C. MEANS OF EGRESS Insufficient detail Pending
D. ROUTES THROUGH Insufficient detail Pending
E. RESTROOMS Insufficient detail Pending
F. REACH RANGES Insufficient detail Pending
F. FEATURES Insufficient detail Pending
XI. PLUMBING FIXTURES
Table 2902.1
Insufficient information
Pending
XII. ENERGY COMPLIANCE
IECC 2003
Documentation submitted is for
Residential projects only. Submit
COMcheck or alternative
compliance documentation.
Pending
XIII. ROOF COVERING
Min. Class C
Class A Asphalt Approved
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
CODE REVIEW
REQUIRED PROPOSED COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 8
XIV. DEFERRED SUBMITTALS
A. Air Balance Report
B. Automatic Sprinkler System
NFPA 13
C. Fire Alarm System NFPA 72
D. Hood suppression system
E. Interior Finishes
F. Elevator
G. Truss Specifications
XV. SPECIAL INSPECTORS
A. Elevator
B. Fire Protection Engineer
Sprinkler System
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 9
1. Application
a. It is the Department of Building Safety policy to require a fire-stop specialty
contractor when fire-resistive construction is involved. A fire-stop contractor
will be required. Submittal of Fire stop system listings for review and approval
is required prior to release of the permit.
b. This review is based on the assumption that changes will be made to meet the
definition of a basement plus 2 stories, VB construction. Some aspects of the
review can not be completed until revised plans are submitted.
c. This review includes life safety and interior accessible routes as noted below.
Review of Structural, Mechanical, Plumbing, etc. has not been completed yet.
d. A review will be done on the submitted responses to the questions for this
review. Need for additional plan review may require additional fees.
2. Civil – Exterior Accessibility
a. Insufficient detail provided for exterior accessible requirements for review and
compliant construction. Provide details and sections where necessary to
communicate requirements for:
1. Accessible route (ANSI 117.1 2003, 402) location, dimensions, slope
2. Van accessible & vehicle parking space/spaces (ANSI 117.1 2003,
502.2) dimensions, slope & marking
3. Access aisle (ANSI 117.1 2003, 502.4) dimensions, slope & marking
4. Signage (ANSI 117.1 2003, 502.7 & IBC 1110.1 2003)
5. Curb ramp details (ANSI 117.1 2003, 406) if part of accessible route
6. Ramp details (ANSI 117.1 2003, 405) width, landings, rise, run, slope,
handrails & edge protection
7. What is the total number of parking spaces provided? How many
Accessible spaces are provided? (IBC 1106)
8. Will there be a passenger loading space at the Wedding Room? (IBC
1106.7)
9. Will there be an accessible route on the exterior to the Wedding Room?
b. Provide detail showing compliance with Exit Discharge IBC 1023 and IBC
1023.6 Access to a public way. Every exit discharge from the building shall
have a direct and unobstructed access to a public way.
c. Provide detail showing compliance for exterior landings at doors IBC 1008.1.5.
d. Provide detail showing compliance for exterior landing at stairways IBC
1009.4.
3. Building Code Analysis – Actual Area Calculations
a. First Floor Level – Wedding Chapel is classified as A-3. Will this space be
used also for banquets? Justify.
b. First Floor Level – Bed & Breakfast square footage is different than calculated
at plan review. Please verify. Is the Wedding Balcony square footage
included?
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 10
c. Provide the square footages for exterior porch (Patios & Entrance) areas.
4. Building Code Analysis – Occupant Load
a. Occupant load calculations are required to be calculated based on the
occupancy of each space per IBC 1004.9. Example: The basement TV room
has a different floor area allowance per occupant than the Sleeping units.
Means of Egress is based on the occupant load of each space. Justify or revise
Occupant load calculations for each area on each floor.
b. The net square footage for the Wedding Chapel is different than calculated at
plan review. Is there a platform or other type of separation from the rest of the
Wedding Chapel at the West bump out? Section or Floor plan does not clarify
what will be located here. Justify or revise.
c. Per IBC 1004.3 every room or space that is an assembly occupancy shall have
the occupant load of the room or space posted in a conspicuous place. Justify
or provide information for compliant construction.
5. Building Code Analysis – Const. Type, Allowable Floor Area, Actual Stories
a. The Basement does not meet the definition of basement. (#1 & #2) as shown. It
is required to be counted as a story. See e-mail dated 12/20/07 Justify.
The site plan sheet 1 of 2, November 14, 2007 by Shear Engineering shows
the Lower Level Slab at 8303.33. The grade around the building is shown at
8305. This is a difference of 1.67 feet. The finished floor surface above the
lower level is shown at 8314.09, which makes it 9.09 feet above the finished
ground level for more than 50% of the building (502 Basement #2). The
grade plane (average grade 6 feet away from the exterior walls) looks to be
the same as 8305 finished ground level, so again the floor above the lower
level would exceed the 6 feet above grade plane (502 Basement #1)
The Architectural Elevations show top of foundation at 3’-0” (2.5’ with 6“to
finished grade). The finished floor surface above the lower level at 9’-6
5/8” would put finished grade at 7’-0 5/8” below that floor. (502 Basement
#2) I would need more contours labeled on the civil to do an accurate grade
plane calculation (502 Basement #1). It looks to me like the plan is to have
the finished grade consistent all around the building.
b. Type VB maximum stories with increase for sprinkler system is 2. Justify
classification of 2 Stories & Basement.
c. Total Allowable Building Area; this figure would be x2 stories for a total of
36,000 s.f. + basement. The basement would not be included in the allowable
area per IBC 503.1.1.
6. Building Code Analysis – Fire Protection Systems
a. An NFPA 13 complying automatic sprinkler system shall be installed
throughout the building and shall be permitted, inspected, and approved by the
Colorado Department of Public Safety, Division of Fire Safety. (720-852-6739).
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 11
b. Prior to installation, provide a set of Colorado Division of Fire Safety approved
plans of the automatic sprinkler system to the Department of Building Safety for
review and approval, per IBC, 106.1.1.1.
c. An NFPA 72 complying fire alarm system is required. See IBC 3006.5, IBC
907.2.1, 907.2.8., NFPA 13, 8.16.1.1, NFPA 72, 6.15.3, etc.
d. The Colorado State Electrical Board, Department of Regulatory Agencies, is
responsible for permits, inspections and approval of the electrical installation of
Fire Alarm Systems.(Dave Cearlock 970-577-3589; 970-223-9838). The
Department of Building Safety is responsible for plan reviews and inspections of
fire alarm systems.
e. Prior to system installation, Fire Alarm Plans shall be submitted to the
Department of Building Safety for review and approval, per IBC, 106.1.1.1.
(For minimum qualifications of fire alarm systems Designers, Installers, and
Maintenance personnel, see Attachment A).
f. Provide location and number of Visible and Audible alarms per IBC Table
907.9.1.3. Are these the horn/strobe shown on E1.0 for basement level units?
7. Building Code Analysis – Fire Resistive Requirements
a. Per IBC 711.3 (exception) Horizontal floor assemblies separating dwelling
units or sleeping units shall be a minimum of ½ hour fire-resistance rated
construction for a fully sprinklered VB type of construction. Justify or revise.
b. Corridors in R occupancy are required to have a ½ hour fire-resistance rating
per IBC Table 1016.1. Justify or revise.
8. Building Code Analysis – Interior Finishes
a. Provide Interior Finish requirements per IBC Table 803.5 for compliant
construction.
b. Provide Decorations and Trim requirements per IBC 805.1. Interior
specifications can be submitted as a deferred submittal.
9. Building Code Analysis – Accessory Use Areas
a. Accessory Use area 1st Floor Breakfast at 1473 square feet exceeds 10% of the
story in which it is located per IBC 302.2 and it is over 750 square feet per IBC
302.2.1. Justify.
b. Add 1st Floor Wedding Balcony area.
c. Add Basement Exercise Room.
d. Add Upper Floor Massage, Salon and Library.
10. Building Code Analysis – Fire-Resistance Rated Construction
a. Provide copies of listings for all fire-resistance-rated assemblies, per IBC
703.2. (Concealed areas without sprinklers- per NFPA 13; Elevator shaft per
IBC, 707.14 and 707.4; Machine room per IBC 3006.4; Stair enclosures per
IBC, 1019.1.5; etc.)
b. Note: Shaft enclosures are constructed as fire barriers Section 706. Shaft
enclosure walls extend from the top of the floor/ceiling assembly below to the
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 12
underside of the floor or roof deck above and are continuous through concealed
spaces per IBC 707.5. The wall is continuous deck to deck. Rated wall or
floor/ceiling assemblies can not be penetrated by non rated walls or non rated
floor/ceilings.
c. Shaft enclosures for vertical fireplace flues with a fire-resistance rating of 1
hour penetrate the sleeping units floor/ceiling assemblies which have a ½ hour
fire-resistance rating, therefore IBC 712.4.3.1 (refers to non fire-resistance-
rated assemblies) does not apply. Justify or revise. Details and listed
assemblies for compliant construction are required.
d. Shaft enclosures are required for stairways that do not meet the exceptions of
IBC 707.2. The stairway from the basement to the main floor lobby area, the
stairway from the kitchen to the basement exit access hallway, and the
accessible ramp to the Wedding Room are all required to be enclosed by a shaft
enclosure, constructed as a fire barrier to separate the basement from the 1st
Story. Justify or revise. Details, listed assemblies and opening protectives per
Section 715 are required for compliant construction.
e. Shaft enclosures with a fire-resistance rating of 1 hour are required for the
elevator shaft and mechanical chase. Details and listed assemblies are
required for compliant construction
f. Note: Per Fire Partition Continuity IBC 708.4, fire partitions are to extend
from the top of the floor assembly below to the underside of the floor or roof
deck above or to a fire-resistance-rated floor/ceiling or roof/ceiling assembly.
Rated wall or floor ceiling assemblies can not be penetrated by non rated walls
or floor/ceilings.
g. Walls separating sleeping units per IBC 708.3 (2) Fire Partitions are required
to have a ½ hour fire-resistive construction for fully sprinklered VB type of
construction. These walls per IBC 708.4 Continuity, are to extend from the top
of the floor assembly below to the underside of the floor or roof deck above or
to a fire-resistance-rated floor/ceiling or roof/ceiling assembly. Provide details
and listed assemblies for compliant construction.
h. Corridors in R occupancy are to be constructed as Fire Partitions IBC 708.1
(4) and have a fire-resistance rating of ½ hour per Table 1016.1. Provide
details for compliant construction. Provide detail if the corridor ceiling is
constructed as the walls 708.4 (3) or if they will be continuous per 708.4.
Provide detail on opening protectives Section 715 and penetrations Section
712.
i. Horizontal Assemblies per IBC 711 should read floor/ceiling.
j. Horizontal Floor/Ceiling IBC 711.3 assemblies are required to have a
minimum ½ hour fire-resistance rated construction separating dwelling units or
sleeping units for fully sprinklered VB type of construction. Continuity of
Horizontal Assemblies IBC 711.4 requires supporting construction to be
protected to afford the required fire-resistance rating of the horizontal assembly
supported and can not be penetrated by non rated walls. Provide detail and
listed assemblies for compliant construction.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 13
k. Penetrations per IBC 712 should include walls (712.3) and floor/ceiling
penetrations (712.4).
l. Provide detail for Opening Protectives Section 715. Opening protectives has
specific requirements for door assemblies in rated assemblies. Submit a door
schedule that addresses all door requirements, including rated door
requirements and door operations per IBC 1008.1.8
11. Building Code Analysis – Means of Egress
a. Corridors are listed as not required to be fire rated for group A. Nonseparated
uses per IBC 302.3.1 require all other code requirements to apply to each
portion of the building based on the use of the area, except that the most
restrictive applicable provisions of Chapter 9 shall apply to the nonseparated
uses. Means of Egress and all other code requirements except Chapter 9 is
calculated by the occupancy of the use area. Justify or revise.
b. Vertical Exit Enclosures IBC 1019, constructed as fire barriers with a fire-
resistance rating of 1 hour are required for stair from basement to reception
entry. Details for compliant construction including penetrations (1019.2),
ventilation (1019.1.3) and opening protectives (715.3.4 & Table 715.3) are
required.
c. Justify Accessible Ramp from basement to Wedding Room not constructed as a
Shaft Enclosure IBC 707.2? The ramp connects the basement to the Main Level
which is open to the Upper Level.
d. Justify Exterior Exit Access stair from basement to north exit at grade
compliance with IBC 1022.6 (3). Separation from the interior of the building is
not required unless required by 1019.1. Per 1019.1 the basement is required to
be separated from the 2 stories above. Therefore, the exterior stairs have to be
separated as the interior stairs, or provide separation from the interior portions
of the building per IBC 1019.1.4. Justify or revise.
e. Provide locations and detail for Accessible Means of Egress required per IBC
1007. Where more than one means of egress is required from any accessible
space, each accessible portion of the space shall be served by not less than two
accessible means of egress. A review will be required on submitted
documentation.
12. Building Code Analysis – Accessibility
a. A Detailed listing of the total number of existing units on this site, including
which ones are fully accessible, type A and type B units is required for review.
A site inspection of existing accessible units for compliance with code will be
required prior to acceptance. IBC Table 1107.6.1.1
b. Insufficient detail provided to do a complete review of the accessible features.
Enlarged floor plans and elevations are required for review and compliant
construction. Submit enlarged floor plans for accessible features including
elevations for accessible toilet and bathing rooms and snack/serving areas. A
review is required of submitted details.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 14
c. Per IBC 1103.1 Buildings and facilities on a site are to be accessible. Per IBC
1107.3 Rooms and spaces available to the general public or available for use by
residents are accessible spaces. This review is based on all facilities available
to the general public or residents will be accessible.
d. Provide detail on the exterior accessible route. IBC 1104.1
e. Provide detail on Accessible Entrances 1105.1. At least 50% of all public
entrances are to be accessible.
f. Provide detail on the interior accessible route for each floor. IBC 1104.3
g. Provide door schedule that details compliance with 309 Operable Parts,
404.2.4 Thresholds at Doorways, 404.2.8 Door-Opening Force, and 404.2.9
Door Surface.
h. Provide detail on IBC 1109.13 Controls, operating mechanisms and
hardware and IBC 1109.13.1 Operable windows.
i. Provide detail on 703 Signs and IBC 1110.1 Signs.
13. Building Code Analysis – Interior Environment
a. Provide detail showing compliance with IBC 1207 Sound Transmission.
b. Provide detail showing compliance with IBC 1210 Surrounding Materials.
14. Building Code Analysis – Elevators
a. The elevator and the elevator machine room IBC 3002.1 are required to have a
1 hour fire-resistance-rated construction as a shaft enclosure. Shaft enclosures
are constructed as fire barriers Section 706. Shaft enclosure walls extend from
the top of the floor/ceiling assembly below to the underside of the floor or roof
deck above and are continuous through concealed spaces per IBC 707.5.
Rated wall or floor/ceiling assemblies can not be penetrated by non rated walls
or non rated floor/ceilings. Provide detail for compliant construction.
b. Prior to installation, provide plans and specifications for elevator to the
Department of Building Safety for review and approval.
c. A special inspector, hired by the building owner and approved by the Building
Official, shall certify the elevator complies with all applicable requirements
which include, but are not limited to ASME A17.1, IBC, ANSI A117.1, ADA,
etc.
d. The Special Inspector shall be approved prior to permit issuance.
15. Building Code Analysis – Plumbing Systems
a. Provide number of plumbing fixtures required based on type of occupancy and
occupant load use of areas shown. IBC 2902.1
16. Building Code Analysis – Energy Compliance
a. The Energy Prescriptive Package submitted with application is for Building that
can be constructed under the IRC. Submit documentation for compliance with
2003 IECC Chapter 5. A review of the energy compliance documentation and
building sections will be done after submittal.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 15
17. Exiting/Fire Partition Sheet
b. The mechanical room in-between sleeping units on all 3 floors is shown on the
floor plans as 1 hour fire rated walls. The Exiting/Fire Partition plan does not
reflect that. Justify or revise.
c. Basement area marked as Wedding Storage only shows protection for part of
the room. The total area open to the area under the stairs is required to be
protected per IBC 1019.1.5. Justify or revise.
d. Rating for stair from Kitchen to basement exit access area is showing the shaft
enclosure on the main floor walls. Per IBC 707.5 Continuity, the supporting
construction shall be protected to afford the required fire-resistance rating of
the element supported. Provide details showing compliance.
e. Provide required exiting from each accessory space.
18. Sheet A-2, Basement Floor Plan
a. Will the TV room have fixed seating, chairs only (not fixed) or tables and
chairs?
b. The door shown in the TV room and north exit access has two swinging door
leafs. Per IBC 1008.1.1 the minimum clear opening width of one leaf is
required to be 32”. Justify or revise.
c. Some doors to occupied rooms or spaces (Exercise) are shown with a 2’10”
door. Per IBC 1008.1.1 the minimum clear opening width is required to be
32”. The door schedule (as required by #10) should address the dimension
from the door face open at 90 degrees to the stop to be a minimum of 32”.
d. Windows shown from suites looking out to patios may be required to be safety
glazing. Sheet A-20 Window Schedule does not list the rough opening height of
the window. Per IBC 2406.3 (9) safety glazing is required when the bottom
edge of the glazing is within 60” of walking surface of the spa side and within
60” of horizontally of the water’s edge. Justify or revise.
e. Label storage room next to elevator. Enclosures under stairways per IBC
1019.1.5 are required to be protected by 1-hour fire-resistive-rated construction
or required rating of stairway. Provide detail.
f. Wedding Storage area is required by 1019.1.5 to be protected as noted above
also. Provide detail.
g. No storage is allowed under exterior stairs per IBC 1019.5. Provide note.
h. Landings at stairs to reception and basement to main level (center area) do not
comply with IBC 1009.4 (2) door opening into stairway landings. Justify or
revise.
i. Sprinkler (Valve) Rooms should not be used for storage purposes other than fire
protection systems.
j. Do type ’B’ staff quarters have a room numbers for identification?
19. Sheet A-2, Basement Floor Plan – Accessibility ANSI 117.1 (2003)
a. As noted in #12, provide interior accessible route. IBC 1104.3
b. As noted in #11, provide accessible means of egress. IBC 1007
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 16
c. The entrance to the exercise room is required per 404.2.3 to have 12” minimum
if both closer and latch is provided from the push/latch side of the door. Justify
or provide door schedule detailing hardware at door.
d. As noted in #12, provide elevations of Snack Bar area for review and compliant
construction with 904.5, 902.3 and 804.4.
e. As noted in #12, a review of the accessible bathrooms shown will be done when
enlarged floor plans and elevations are submitted.
f. The accessible bathroom next to suite #12 is shown with an automatic opener as
an alternative method for compliance with 404.2.3; the automatic opener will
be required on the interior for maneuvering clearances also. Provide this
information on the door schedule.
g. Both type ‘B’ staff quarters have a closet with an appliance that is not labeled
and a kitchenette that is not labeled. Laundry Equipment is to comply with
1004.10. The kitchenette is to comply with 1004.12.. Label all appliances and
Show clear floor space.
h. Both type ‘B’ staff quarters are to comply with 1004.9 Operable Parts.
i. Provide which option the toilet and bathing rooms are to comply with the
enlarged floor plans and elevations for type ‘B’ units.
j. North type ‘B’ staff quarter primary entrance door is required to have
maneuvering clearances according to 404.2.3 on the corridor side. Justify or
revise.
k. Provide additional detail on ramp to Wedding Room that shows landings,
length of ramp run, rise for each ramp run and required area at turns, including
dimensions etc. to demonstrate compliance with IBC 1010 and ANSI 117.1 405
Ramps.
l. Width reduction shown at ramp to Wedding Room is not in compliance with
1010.5.3 Restrictions. Justify or revise.
m. Turns shown on ramp without required landings are not in compliance with
1010.6.4 Change in Direction. Justify or revise.
20. Sheet A-3 Wedding Room Floor Plan – Accessibility ANSI 117.1 (2003)
a. Provide enlarged floor plans and elevations for accessibility review of Men’s
and Women’s restrooms.
b. Doors shown into the Men’s, Woman’s and accessible ramp from the basement
are required to have a minimum of 18” on the pull side of the door 404.2.3.1.
Justify
c. Bar area service counters are shown at 42”AFF. Per 902 Dining Surfaces
and Work Surfaces, accessible surfaces are required per 902.2 and 902.3 and
IBC 1108.2.9.1. Justify or revise.
21. Sheet A-4, Main Floor Plan
d. Will there be a check in desk? Provide detail for accessibility ANSI 117.1 904
Sales & Service Counters.
e. Label the use for areas shown on other drawings as Office, Reception Area,
Lodge Room, Suites, etc.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 17
f. Provide a dimension for the stair shown from the Reception Area to the Lodge
Room.
g. Windows shown from suites looking out to patios may be required to be safety
glazing. Sheet A-20 Window Schedule does not list the rough opening height of
the window. Per IBC 2406.3 (9) safety glazing is required when the bottom
edge of the glazing is within 60” of walking surface of the spa side and within
60” of horizontally of the water’s edge. Justify or revise.
h. Some doors are shown with a 2’10” door. Per IBC 1008.1.1 the minimum
clear opening width is required to be 32”. The door schedule (as required by
#10) should address the dimension from the door face open at 90 degrees to the
stop to be a minimum of 32”.
i. Provide planned use of Show Kitchen. Will guests be allowed to use
equipment? Will buffet food items be available in this area?
j. Winder stairways are not permitted per IBC 1009.8. Change in direction
requires a landing per IBC 1009.4. Justify or revise all center stair runs from
basement to upper floor and kitchen stair.
k. Landings at stairs from kitchen to basement exit access area do not comply with
IBC 1009.4 (2) door opening into stairway landings. Justify or revise.
l. Landings at exterior stairs from upper level show at 3’-9” does not comply with
IBC 1009.4 the width of the landing shall not be less than the stairway served
measured in the direction of travel. Justify or revise.
22. Sheet A-4, Main Floor Plan - Accessibility ANSI 117.1 (2003)
a. As noted in #12, provide interior accessible route. IBC 1104.3
b. As noted in #11, provide accessible means of egress. IBC 1007
c. If Office is used for registering guest, it will be required to be accessible. Justify
or provide detail.
d. The Lodge Room is shown with a step down. Justify Lodge Room area not
accessible as required by IBC 1103.1. All building facilities shall be accessible
to persons with physical disabilities.
e. The Wedding Balcony is shown with a step up. Justify balcony area not
accessible as required by IBC 1103.1. All building facilities shall be accessible
to persons with physical disabilities.
f. Show compliance in Breakfast Area with IBC 1108.2.9.1 Dining Surfaces and
1109.11 Seating at tables…
g. As noted in #12, provide elevations of Serving Bar area for review and
compliant construction with ANSI 117.1 904.5, 902.3.
h. As noted in #12, a review of the accessible bathroom shown by the Elevator will
be done when enlarged floor plans and elevations are submitted.
i. A review of the required # of plumbing facilities for this floor will be done when
the requested (#15) analysis is submitted.
j. The maneuvering clearance for the accessible bathroom shown by the Elevator
requires 48” minimum width at the hinge approach push side. 404.2.3.1 Justify
or revise.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 18
k. Suite 3 is shown as a type ‘A’ unit. The primary entrance door is required to
have maneuvering clearances according to 404.2.3 for both sides and 404.2.3.3
for opening off corridor. Justify or revise.
l. As noted in #12, a review of the accessible type ‘A’ bathroom 1003.11 shown in
Suite 3 will be done when enlarged floor plans and elevations are submitted.
23. Sheet A-5, Upper Floor Plan
a. Landing at interior stairs to exterior stair at upper level show at 3’-10” does
not comply with IBC 1009.4 the width of the landing shall not be less than the
stairway served measured in the direction of travel for both directions. Justify
or revise.
b. Landings at stair from this level to exterior stair does not comply with IBC
1009.4 (2) door opening into stairway landings. Justify or revise.
c. Windows shown from suites looking out to patios may be required to be safety
glazing. Sheet A-20 Window Schedule does not list the rough opening height of
the window. Per IBC 2406.3 (9) safety glazing is required when the bottom
edge of the glazing is within 60” of walking surface of the spa side and within
60” of horizontally of the water’s edge. Justify or revise.
d. Some doors are shown with a 2’10” door. Per IBC 1008.1.1 the minimum
clear opening width is required to be 32”. The door schedule (as required by
#10) should address the dimension from the door face open at 90 degrees to the
stop to be a minimum of 32”.
e. Doors to the Suites on this floor are shown with a 2’- 8” door. Per IBC
1008.1.1 the minimum clear opening width is required to be 32”. Justify or
revise. The door schedule (as required by #10) should address the dimension
from the door face open at 90 degrees to the stop to be a minimum of 32”.
24. Sheet A-5, Upper Floor Plan - Accessibility ANSI 117.1 (2003)
a. As noted in #12, provide interior accessible route. IBC 1104.3
b. As noted in #11, provide accessible means of egress. IBC 1007
c. As noted in #12, provide elevations of Snack Bar area for review and compliant
construction with 904.5, 902.3 and 804.4.
d. The Corridor shown outside the salon door to meet maneuvering clearances per
404.2.3.1 is required to have a 42” minimum clear opening. Verify
e. As noted in #12, a review of the accessible bathroom shown by the Massage
Room will be done when enlarged floor plans and elevations are submitted.
25. Sheet A-9, Section A
a. Structural & Energy not reviewed yet.
b. Detail for vertical exit enclosure from Reception to Basement is not detailed as
shown on floor plan. Section is required to show compliant construction for a
rated vertical exit enclosure. Justify or revise.
c. Guard detail shown notes 4” between balusters. IBC 1012.3 Opening
limitations require a 4” sphere can not pass through any opening. Justify or
revise. Please note height of guard is from finished floor to top of rail.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 19
26. Sheet A-10, Section B & C
a. Structural & Energy not reviewed yet.
b. Shaft enclosures are constructed as fire barriers Section 706. Shaft enclosure
walls extend from the top of the floor/ceiling assembly below to the underside of
the floor or roof deck above and are continuous through concealed spaces per
IBC 707.5. The wall is continuous deck to deck. Rated wall or floor/ceiling
assemblies can not be penetrated by non rated walls or non rated floor/ceilings.
c. These sections show the 5/8” quiet rock 525 for gypsum board. Provide listed
shaft wall assembly that complies with 1 hour fire-resistance rating.
d. These sections show the drywall stopping at the bottom of each floor/ceiling
assembly. The shaft wall assembly is required to continue to the deck of the
floor/ceiling assembly or the floor/ceiling assembly has to be rated to provide
equal protection. IBC 707.5 Justify or revise
e. These sections show the shaft enclosure stopping at the upper floor ceiling. Per
IBC 707.12 Enclosure at the top, the shaft enclosure is to extend to the
underside of the roof deck or be enclosed at the top with construction of the
same fire-resistance rating as the topmost floor or not less than required for the
shaft. Justify or revise.
27. Sheet A-11, Section D
a. Structural & Energy not reviewed yet.
b. Shaft enclosures are constructed as fire barriers Section 706. Shaft enclosure
walls extend from the top of the floor/ceiling assembly below to the underside of
the floor or roof deck above and are continuous through concealed spaces per
IBC 707.5. The wall is continuous deck to deck. Rated wall or floor/ceiling
assemblies can not be penetrated by non rated walls or non rated floor/ceilings.
c. Section for Solar trunk line/Boiler flue chase is to be a shaft enclosure. Provide
listed shaft wall assembly that complies with 1 hour fire-resistance rating.
d. This section shows the drywall stopping at the bottom of each floor/ceiling
assembly on Lodge Room side. The shaft wall assembly is required to continue
to the deck of the floor/ceiling assembly or the floor/ceiling assembly has to be
rated to provide equal protection IBC 707.5. Justify or revise.
e. This section does not show the top of the shaft enclosure. Per IBC 707.12
Enclosure at the top, the shaft enclosure is to extend to the underside of the
roof deck or be enclosed at the top with construction of the same fire-resistance
rating as the topmost floor or not less than required for the shaft. Justify or
revise.
f. Revision of sections is required to show compliant details on fire-resistance-
rated construction as required for fire-barriers and fire-partitions. (Sleeping
unit separations and floor/ceiling assemblies)
28. Sheet A-12, Section E
a. Structural & Energy not reviewed yet.
b. Detail for compliant construction is required for Handrails IBC 1009.11.
Provide additional enlarged typical detail for exterior stairways that shows
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 20
compliance with both sides required, height, graspability, continuity, and
extensions.
c. Detail for compliant construction is required for exterior stairways IBC 1009.1.
Provide additional enlarged typical detail for exterior stairways that shows
compliance with Profile 1009.3.2 (no open risers), landings 1009.4 and outdoor
conditions 1009.5.2
29. Sheet A-13, Section F
a. Detail for compliant construction is required for Ramps IBC 1010.1 & ANSI
117.1 405 Ramps. Provide additional enlarged typical detail for interior ramp
to Wedding Room that shows compliance with slope, cross slope 1010.3,
maximum vertical rise 1010.4, width 1010.5.1, headroom 1010.5.2, restrictions
1010.5.3, and landings 1010.6. Show compliance with 1010.8 Handrails
including extensions.
30. Sheet A-14, Section G & H
a. Detail for compliant construction is required for Handrails IBC 1009.11.
Provide additional enlarged typical detail for interior stairways that shows
compliance with height, graspability, continuity, extensions and # required.
b. Detail for compliant construction is required for guards IBC 1012.1. Provide
additional enlarged typical detail for interior stairways that shows compliance
with height and opening limitations.
c. Detail for compliant construction is required for interior stairways IBC 1009.1.
Provide additional enlarged typical detail for interior stairways that shows
compliance with profile 1009.3.2 and landings 1009.4.
31. Sheet A-15, Section I
a. A minimum of one section is required to show fire partition details as required
for walls separating sleeping units, corridors, and floor/ceiling assemblies.
• Detail Fire Partition Continuity IBC 708.4, fire partitions are to extend
from the top of the floor assembly below to the underside of the floor or roof
deck above or to a fire-resistance-rated floor/ceiling or roof/ceiling
assembly. Rated wall or floor ceiling assemblies can not be penetrated by
non rated walls or floor/ceilings.
• Detail Walls separating sleeping units per IBC 708.3 (2) Fire Partitions
are required to have a ½ hour fire-resistive construction for fully
sprinklered VB type of construction. These walls per IBC 708.4 Continuity
are to extend from the top of the floor assembly below to the underside of
the floor or roof deck above or to a fire-resistance-rated floor/ceiling or
roof/ceiling assembly. Provide details and listed assemblies for compliant
construction.
• Detail Corridors in R occupancy are to be constructed as Fire Partitions
IBC 708.1 (4) and have a fire-resistance rating of ½ hour per Table 1016.1.
Provide details for compliant construction. Provide detail if the corridor
ceiling is constructed as the walls 708.4 (3) or if they will be continuous per
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 21
708.4. Provide detail on opening protectives Section 715 and penetrations
Section 712.
• Detail Horizontal Floor/Ceiling IBC 711.3 assemblies are required to have
a minimum ½ hour fire-resistance rated construction separating dwelling
units or sleeping units for fully sprinklered VB type of construction.
Continuity of Horizontal Assemblies IBC 711.4 requires supporting
construction to be protected to afford the required fire-resistance rating of
the horizontal assembly supported and can not be penetrated by non rated
walls. Provide detail and listed assemblies for compliant construction.
32. Sheet A-16, Section J
a. Detail for vertical exit enclosure from Reception to Basement is required to
show compliant construction for a rated vertical exit enclosure.
b. Provide listed wall assembly that complies with 1 hour fire-resistance rating.
c. Note: Vertical exit enclosures are constructed as fire barriers Section 706.
Vertical exit enclosure walls extend from the top of the floor/ceiling assembly
below to the underside of the floor or roof deck above and are continuous
through concealed spaces per IBC 707.5. The wall is continuous deck to deck.
Rated wall or floor/ceiling assemblies can not be penetrated by non rated walls
or non rated floor/ceilings.
d. This section does not show the top of the Vertical exit enclosure. Per IBC
707.12 Enclosure at the top, the exit enclosure is to extend to the underside of
the roof deck or be enclosed at the top with construction of the same fire-
resistance rating as the topmost floor or not less than required for the shaft.
Justify or revise.
33. Sheet A-20, Window Schedule
a. Verify windows shown comply with IBC Section 2406 Safety Glazing.
b. Windows shown next to doors at Wedding Room may be required to be safety
glazing. Per IBC 2406.3 (6) within a 24” arc of either vertical edge of the door
in a closed position… Justify or revise.
c. Windows shown next to doors at Reception Room may be required to be safety
glazing. Per IBC 2406.3 (6) within a 24” arc of either vertical edge of the door
in a closed position… Justify or revise.
34. Sheet A-23, Grade Plane (submitted 01-09-08)
a. Total perimeter numbers shown on left side of sheet are the calculations to
verify basement meets the definition of basement, exception #2 IBC 502?
Please verify we are interpreting this correctly.
b. I believe the line 52% of exterior walls have a grade plane… should be 52% of
exterior walls have a finished ground level…
c. Finished Floor: 8312.66 - Please verify Grade at 6’4” foundation walls 6’
from building is 8207.83’? Average Grade Plane lists this at 8307.83? Clarify.
Date: 01/09/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra project contacts 2008.01.09.doc Page 22
d. Average Grade Plane numbers shown in center of sheet are the calculations to
verify basement meets the definition of basement, exception #1 IBC 502?
Please verify we are interpreting this correctly.
e. The Average Grade Plane numbers used to multiply by the lowest grade within
6 feet of the foundation walls seems to be the number of walls not the liner feet
of those walls. Please recalculate using the lowest grade within 6 feet of the
foundation walls by the liner feet of those walls or Justify.
f. After reviewing the patio areas with Will Birchfield, its our interpretation that
the patios are actually covered by the roof, see IBC 502 Area, Building,
therefore the calculations for grade can be taken at the patio area foundation
walls or the lowest grade within 6 feet of patio area foundation walls.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.01.28.doc Page 1
• The plans and specifications submitted have been reviewed for conformance with
the following codes as amended and adopted by the Town of Estes Park.
Estes Valley Development Code (EVDC); adopted November 3, 1999; effective
Feb. 2000
• Applicant shall identify any variances granted by the Board of Adjustment.
Estes Park Municipal Code (EPMC)
Estes Park Municipal Code (EPMC), Chapters 14.12 and 14.20, adopt the
following codes including codes referenced therein (NFPA 13, NFPA 72, ASME
A17.1, ANSI A117.1-2003, etc.):
International Building Code (IBC), 2003 Edition
International Mechanical Code (IMC), 2003 Edition
International Fuel Gas Code (IFGC), 2003 Edition
International Plumbing Code (IPC), 2003 Edition
International Energy Conservation Code (IECC), 2003 Edition
National Electrical Code (NEC), 2005 Edition
Accessibility requirements of the Americans with Disability Act of 1991 are not part
of this review. The U. S. Department of Justice is the final authority for enforcement
of ADA requirements. It is the responsibility of owners, designers and contractors to
provide access to this facility and to comply with ADA requirements. This review has
addressed compliance with chapter 11 of the 2003 International Building Code and
the 2003 ANSI A117.1 standard for accessibility.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.01.28.doc Page 2
1. S0-1 General Notes
a. Live loads noted at 3.0 B for Upper Floor is at 40 psf. Per IBC Table
1607.1(27) Public Rooms and corridors serving them, require 100 psf. Clarify
and provide design live loads for portions of the building as applicable.
b. Locally required minimum live loads for exterior decks with hot tubs are 100 psf
and decks without hot tubs are 60 psf. Provide design live load.
c. Wind loads noted at 3.0 D (3 second gust) is noted as 100 mph. Locally
adopted minimum wind speed (3 second gust) is 105 mph. Justify or revise.
d. Submit for review the Geotechnical Report dated 3/5/07 by Earth Engineering
Company.
e. Special Inspectors as required by note 6.0 Special Structural Inspections are to
be pre-approved by the Building Official. IBC 1703.1
2. S1-1 Foundation Plan
a. Verify foundation plan scale listed at ¼”?
b. Are you providing a sub-slab radon depressurization system? If applicable,
details are required.
c. Provide elevation of slab for basement and wedding room.
d. Provide top of foundation elevations.
e. Verify exterior stair enclosure wall area to the north has moved per documents
submitted for grade plane calculations. Justify or revise.
3. S2-1 Main Floor Framing Plan
a. Structural Engineer has specified an I-Level Trus Joist product for I joist.
Substitutions per Building Department Policy require revised plans and review.
b. Provide section marks on framing plans to show location of sections in
Architectural Drawings.
c. Provide framing for site constructed roofs at suites.
d. A-17 shows LVL headers at suite windows, no notation on structural so would
default to (3) 2x10’s. Clarify.
e. Glu lam beams specified at exterior deck/porches are required to be listed for
exterior use. Protection with a surface applied product is not sufficient per
Building Department Policy. Justify or revise.
f. 2x6 exterior stud walls at several locations are shown with a laterally
unsupported height exceeding 10’ per IBC Table 2308.9.1. All exterior walls
are considered bearing walls. Justify or revise.
4. S3-1 Upper Floor & Lower Roof Framing Plan
a. Provide framing for site constructed roofs at suites.
5. S3.2 Lower Roof Framing Plan
a. Over frames are required to be on 2x sleepers per Building Department Policy.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.01.28.doc Page 3
b. 2x8’s @ 24” o.c. for over frames with a maximum span of 12’ fails I level
software for a 50 psf snow load. Justify or revise.
c. All roof rafters and trusses are to be connected to resist uplift. Provide type of
connector & fasteners.
d. All roof rafters and trusses are to be laterally blocked at bearing. Provide note
to ensure compliance.
e. Provide size and spacing of lookouts. Lookouts are to be connected at bearing,
starting at the lowest point and @ 48”o.c. maximum. Provide note.
6. S5.1 Details
a. Sill plate and sealer not noted on plans. Section A12 details studs against
foundation wall. Provide compliance with IBC 2304.11.2.2 Framing
Wood framing members, including wood sheathing, which rest on exterior
foundation walls and are less than 8 inches (203 mm) from exposed earth,
shall be of naturally durable or preservative-treated wood. Wood framing
members and furring strips attached directly to the interior of exterior
masonry or concrete walls below grade shall be of approved naturally
durable or preservative-treated wood.
7. S5.1 Lower Roof Framing Plan
a. Sill plate and sealer not noted on plans. Section A12 details studs against
foundation wall. Provide compliance with IBC 2304.11.2.2 Framing
8. MPO.1 General HVAC Notes
a. Provide an enlarged floor plan with dimensions of kitchen cooking appliances
and Type 1 hood. Provide clearances to combustibles required by IMC 507.9.
b. Provide elevation detail of ductwork, duct enclosure, hood, cooking surface, air
supply, exhaust system and structural support through the roof assembly
detailing compliance with IMC 506.3 Ducts serving Type 1 hoods.
c. Provide hood specifications.
d. Provide kitchen equipment specifications.
e. Provide hood fire wrap specifications.
f. Plenums are not permitted in combustible construction. Please delete note.
9. MP2.1 Basement HVAC Plan
a. Penetrations or openings in fire-resistance-rated assemblies require protection
IBC 712 & 716. Provide listings on fire dampers and/or fire-stop systems.
(Exhaust fans, dryer ducts, etc.)
10. MP2.2 Main Floor HVAC Plan
a. See review #9a above.
11. MP2.2 Flag Notes
a. Note 2; see review #8 above.
b. Note 3; see review #8 above.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.01.28.doc Page 4
c. Note 4; provide specifications and installation detail for Residential Range
Hood exhaust system. (Local Amendment)
d. Note 5; provide specifications on range.
12. MP2.3 Upper Floor HVAC Plan
a. See review #9a above.
13. MP2.3 Flag Notes
a. Note 4; see review #8 above.
14. MP2.4 Wedding Room HVAC Plan
a. See review #9a above.
15. M5.1 Enlarged Mechanical Room HVAC Plan
a. See review #9a above.
b. Provide listed fire-stop system(s) or listed shaft for Flag Note # 6 & 7 A11
16. M6.3 Sequence of Operations
a. Fan Coil FC-2: Hood suppressions system specifications are to be submitted to
the Department of Building Safety for review and approval prior to installation
as a deferred submittal.
17. Energy Compliance Documentation
a. As noted on life safety review dated 01/09/08, #16 submit documentation for
compliance with 2003 IECC Chapter 5.
18. Plumbing
a. The Health Department is to approve well water and State Engineer to approve
new wells.
19. P2.1 Basement Floor Waste and Vent Plan
a. Penetrations or openings in fire-resistance-rated assemblies require protection
IBC 712 & 716. Provide listings on fire dampers and/or fire-stop systems.
20. P2.2 Main Floor Plumbing Plan
a. See review #19a above.
21. P2.3 Upper Floor Plumbing Plan
a. Submit specifications for solar panels for review and approval prior to
installation.
b. See review #19a above.
22. P6.1 Grease Interceptor Detail
a. Vent Grease Interceptor per State of Colorado regulations.
Date: 01/28/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.01.28.doc Page 5
b. Increase size of GI to 500 gallon, per conversations with Upper Thompson
Sanitation District and Chief Building Official.
23. Electrical Plans
a. Electrical permits and inspections are the responsibility of the Colorado State
Electrical Board, Department of Regulatory Agencies. (Dave Cearlock 970-
577-3589). Plans have not been reviewed by the Town of Estes Park
Department of Building Safety.
24. Electrical Plans
a. Illumination is not shown at the exterior doors. Justify compliance with
IBC 1006.1 Illumination required
The means of egress, including the exit discharge, shall be illuminated at all
times the building space served by the means of egress is occupied.
b. The Estes Valley Development Code regulates all exterior lighting. Please refer
to EVDC 7.9 for specifics.
25. Plumbing Gas
a. The gas schematic is still under review. The Department of Building Safety is
having difficulty getting the sizing to work for Della Terra’s altitude. A review
will be completed as soon as possible.
26. Plumbing Fixtures
a. A review of the plumbing fixtures can not be completed until revised occupant
load numbers are submitted.
Date: 03/13/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
PLAN REVIEW COMMENTS
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.03.13.doc
2nd Review - Commentary in blue +/or highlighted items requiring clarification or
justification.
1. S3.2 Lower Roof Framing Plan
a. Over frames are required to be on 2x sleepers per Building Department Policy.
This was not addressed that I could see?
b. 2x8’s @ 24” o.c. for over frames with a maximum span of 12’ fails I level
software for a 50 psf snow load. Justify or revise. This was not addressed that I
could see?
2. MPO.1 General HVAC Notes
a. Provide an enlarged floor plan with dimensions of kitchen cooking appliances
and Type 1 hood. Provide clearances to combustibles required by IMC 507.9.
Owner is to submit enlarged floor plan for Kitchen layout. What needs to be
clarified by submitting the enlarged floor plan is the requirement for clearances
to combustibles (stud wall and wood floor/ceiling).
• The Type 1 Hood grease duct enclosure is required to have an 18” clearance
from the duct to the interior surface of enclosures of combustible
construction per IMC 506.3.10. M5.1 Grease Duct /Fan Detail refer to a
shaft enclosure on A-25, which I believe is wood stud construction and
would not be considered noncombustible construction. Also noted is 3’
minimum to 12” Max air gap. This would not comply with the requirement
of IMC 506.3.10. Justify or revise.
• The Type 1 Hood is required to have an 18” clearance from the hood to any
combustible interior surface per IMC 507.9. All surfaces within 18” of the
cooking surface and exhaust hood opening must be smooth, readily
cleanable, noncombustible and nonabsorbent. The note on page M5.1 calls
for a noncombustible wall with stainless steel. Metal studs with gypsum
board meet the exception of IMC 507.9 for the wall if the construction
continues for 18” in all directions from the hood. Provide location of detail
on Architectural plans that show non-combustible construction. This
exception is not applicable to grease ducts IMC 506.3.10. The 18”
clearance is still required for the floor/ceiling combustible construction.
Justify.
b. Provide elevation detail of ductwork, duct enclosure, hood, cooking surface, air
supply, exhaust system and structural support through the roof assembly
detailing compliance with IMC 506.3 Ducts serving Type 1 hoods.
• Provide location of detail for structural support of Grease Duct/Fan?
3. M2.1, M2.2, M2.3 HVAC Plan
a. Penetrations or openings in fire-resistance-rated assemblies require protection
IBC 712 & 716. Provide listings on fire dampers and/or fire-stop systems.
(Exhaust fans, dryer ducts, etc.)
Date: 03/13/08 Permit #: 8445
By: Carolyn McEndaffer &
Will Birchfield, CBO
Job Address: 3501 Fall River Road
Della Terra
L:\Comm Dev\AddressFiles\Fall River Rd\3501 FRR_Della Terra\PLANNING 3501 Fall River Rd Della Terra 2008\3501 Fall River
Road Della Terra Struct, Review 2008.03.13.doc
• Owner is to either provide copies of all fire-stop assemblies specific to the
assembly penetrated and penetrating item prior to release of permit or will
hire a special inspector for fire-stop systems.
4. P2.1, P2.2, P2.3Waste and Vent Plan
a. Penetrations or openings in fire-resistance-rated assemblies require protection
IBC 712 & 716. Provide listings on fire dampers and/or fire-stop systems.
• Owner is to either provide copies of all fire-stop assemblies specific to the
assembly penetrated and penetrating item prior to release of permit or will
hire a special inspector for fire-stop systems.
5. P2.3 Upper Floor Plumbing Plan
a. Submit specifications for solar panels for review and approval prior to
installation.
• Manufacturers’ installation instructions and specifications are required to be
submitted as a deferred submittal prior to start of installation for review and
approval from the building department.
Gas Review response from Integrated Mechanical dated 2/12/08 has not been reviewed
yet. Comments from the building department will be submitted for your consideration
as soon as possible.