HomeMy WebLinkAboutPERMIT.PLANS 23-035 1575 Fall River Road, deck 2023-02-20
Deck
Estes Park
170 MacGregor Ave Suite 230, Estes Park, CO
80517
23-EP-00035
Phone:(970) 577-3726Fax: (970) 586-0249
Date Issued:02/20/2023Property Owner:Nate Dale
Expiration Date:09/24/2023Mailing Address:1575 Fall River Road
Job Site Address:1575 Fall River Road, Estes Park, CO
80517
Estes Park, CO 80517
Category:Residential Alteration
Phone:(970) 481-0091
Permit Type:Deck
Email:
Valuation:$7,500.00
Description of Work:
We are replacing a existing wood deck using red pressure treated lumber
Subdivision:Required Setbacks:
Parcel ID:3523300009
Filing:
Lot:Actual Setbacks:
Block:
Total Sq Ft:
Contractors:Fee Items Amount
PrimaryAV Remodeling and Concrete Services
Building Permit Fees
$ 153.25
Use Tax
$ 30.00
Plan Review
$ 76.63
Building Permit Fees (manual)
$ 519.76
Total Fees:$ 779.64
NOTICE
Signature of Applicant/DateBuilding Department Signature/Date
02/01/2024
MUST BE POSTED ON JOB SITE
STRUCTURAL OBSERVATION REPORT
Job No. AVRM24-23005
Permit No. 23-EP-00035
Date signed: March 22, 2023
This is a verified password
secured signature
AV Services
327 Logan Ave.
Nunn, Colorado 80648
Attention: Rene Vasquez
Re: Structural observation at the deck addition at
1575 Fall River Rd., Estes Park
Dear Mr. Vasquez:
On this date I observed the subject structure regarding deck
framing regarding some building department issues. Following is a
list of those items and my comments and/or recommendations:
1. Will need engineer letter for deck piers that were poured before inspection was called in to
verify what plans are calling for. I observed the piers and approve the
installation as built. They were of the proper size and depth.
2. Missing connection for 4x4 post in back of deck on top and bottom on east side of deck. I
observe the post in question. It is existing and is buried in
the concrete. I approve of the installation as built.
3. Missing several nails to hangers for joist thru out deck. Missing screws. I observed that
all nails and screws have been installed.
4. Footers needs to be 12Ñ you left two which are 8Ñ and one is falling over. I observed
that particular footing pier. It is existing, and buried
adequately to resist any overturning from the light loads
imposed. I approve of the installation as built.
5. Did not install new 2x6 @ 24Ñ o.c. Between existing members. As per plan installed new 2x6s
but on non-matching spacing throughout southern section of front deck. I observed the
installation of all deck joists. Uneven spacing does not affect
the capacity of the joist to carry loads, as the tributary area
is the same. The east deck had additional joists installed to
be at 8Ñ o.c. I approve of all deck joists as installed.
6. Did not build eastern section of deck per plan. On your plans it shows new 2x6 joist at 16Ñ
o.c. Running east and west. You have installed them running north and south. I observed
the installation of this portion of the deck. The beams,
hangers, and joists as installed will support the maximum
design loads imposed. I approve of the installation as built.
7. There is no flashing on house side for deck as per plan. I observed the
installation of the deck flashing. A row of log siding was
removed and the flashing installed per the detail. I approve
of the flashing as built.
8. Missing DTT1Z as per plan for ledger. I observed the installation of the
Lateral load resisting system as designed, with (4) equal
spaced DTT1Z tension ties per south and east deck sections. I
approve of the installation as built.
Thank you for retaining us to perform this structural
evaluation service. Please feel free to contact our office if you
have any further questions.
Very truly yours,
MARK BENJAMIN, PE, MSCE, SECB, CPHC
Certified in the practice of structural engineering
Certified Passive House Consultant
INSPECTION CARD
Estes Park
170 MacGregor Ave Suite 230, Estes Park, CO 80517
POST THIS CARD IN A SAFE CONSPICUOUS LOCATION. PLEASE DO NOT REMOVE THIS NOTICE UNTIL ALL REQUIRED INSPECTIONS ARE MADE AND SIGNED OFF BY THE APPROPRIATE
AUTHORITY AND THE BUILDING IS APPROVED FOR OCCUPANCY. STAMPED APPROVED PLANS MUST BE AVAILABLE ON THE JOBSITE.
APPLICATION NO.:23-EP-00035TYPE:DeckISSUED DATE:02/20/2023EXPIRATION DATE:09/24/2023
PROJECT ADDRESS:1575 Fall River Road, Estes Park, CO 80517PARCEL NO.:3523300009
OWNER:Nate DaleCONTRACTOR:AV Remodeling and Concrete ServicesCONTRACTOR PHONE:
DESCRIPTION OF WORK:We are replacing a existing wood deck using red pressure treated lumber
CONSTRUCTION TYPE:OCCUPANT LOAD:
DATE DATE
INSPECTIONINSPPASSEDCOMMENTSINSPECTIONINSPPASSEDCOMMENTS
SetbacksJG3/28/2023See NotesFootingsJG3/28/2023See Notes
Rough FrameJG3/28/2023See NotesFinalJG3/28/2023See Notes
Engineering
Fire Approval:Date:Date:
Approval:
PW Approval:Date:Other ( ):Date:
To request an inspection:
Page 1 of 1