HomeMy WebLinkAboutENGINEER LETTER B-10534 3501 Fall River Rd Della Terra pavilion 2016.11.16
November 16, 2016
Estes Park Building Department
Town of Estes Park
PO Box 1200
Estes Park, CO 80517
RE: Tuscan Pavilion, 3501 Fall River Rd., Estes Park, Colorado
Foundation Inspection
Dear Will,
A representative of CES made a site visit to 3501 Fall River Road, Estes Park, Colorado on November 1, 2016 for a
foundation inspection for the proposed pavilion.
Foundation Walls 2015 IRC Inspection:
• R106.4 Changes have been made not in compliance with the approved plan. Resubmit these changes to the
Division of Building Safety for review and approval by the CBO.
The column foundation supports have been formed and located per the engineered footing detail prepared by
Affinity Engineering stamped and dated 10/21/2016.
• R104.4, R109.1.5, R401.2 A geo soils engineering report required as per the approved plan has been reviewed
and approved by the CBO.
The foundation is located on undisturbed silty sandy loam and decomposed granite and will provide adequate
bearing capacity.
• R104.1; R403.1.6 Amended Anchor bolts and washers are onsite and sized as per approved plan.
• R106.1.1 Additional anchoring systems are properly sized and located as per the approved plan.
• R404.1.3.2 Corner rebar is continuous or is spliced with continuous rebar a minimum of 24” for each leg.
• R404.1.3.3.7.4 Concrete coverage over, under and around rebar within removable forms is a minimum of 1 ½”.
No structural items have been reviewed beyond those listed above.
If you have any questions, please do not hesitate to contact me.
Sincerely
Cornerstone Engineering & Surveying, Inc.
Michael S. Todd, P.E.
Principal
Digitally signed
by Michael
Todd, P.E.
Date:
2016.11.16
11:58:51 -07'00'