WEST RIVERSIDE PARK - PHASE III:
The bid opening for West Riverside Park - Phase III resulted in the
following bids being submitted:
1. Chief's Landscaping $44,972.25
2. Joseph D. Jatcko, General Contractor $49,211.00
3. Environmental Concerns $60,987.00
The Committee, along with Mr. Russ Butler of EDAW, Inc., examined
the bid document and have determined that the following items can
be eliminated:
ITEM AMOUNT TO BE DEDUCTED
FROM BID PRICE
1. Accept Chief Landscaping Gravel
Alternate for walks. $ 234.50
2. Fill under parking areas to be borrow
type fill except for sub -base for
asphalt paving, which shall be gravel
as specified.
3. Change timber curb to single tie from
double tie construction.
4. Eliminate 2 foot deadman tie on all
timber borders.
5. Eliminate center tie support on both
sets of timber steps.
6. Eliminate plant material and drip
irrigation line in planting area
between parking areas (maintain
connection for installation of drip
irrigation line in future).
7. Eliminate play structure
8. Eliminate 3 timber benches.
9. Eliminate park light (city to provide
wire for light and Chief Landscaping
to lay wire in irrigation trench to
light location shown on plans).
10. Eliminate rip -rap (until decision can
be made regarding actual quantity of
rip -rap required).
TOTAL
1,200.00
982.00
1,040.00
140.00
999.00
3,485.00
750.00
1,000.00
6,400.00
$16,230.50
BRADFORO PUBLISHING CO., DENVER
RECORD OF PROCEEDINGS
Public Works Committee - June 27, 1983 - Page 2
Chief Landscaping Bid
Less Deducted Items
Total Contract Price
$44,972.25
(16,230.50)
$28,741.75
With the elimination of the items listed above, the project will cost
about $28,741.75. The Committee recommends the agreement be approved
and the Mayor and Clerk be authorized to sign the contract.
There being no further business, the meeting adjourned.