RECORD OF PROCEEDINGS
/ Public Works Committee
May 15, 1986
Committee: Chairman Brown, Trustees Barker and Hix
Attending: All
Also Attending: Mayor Dannels, Town Administrator Hill,
Public Works Director Widmer, Finance Officer
Vavra, Judy Hoxsey, Barbara Godbolt, Lois
Moor, Clerk O'Connor
Absent: None
ESTES PARK LIBRARY - UPDATE REGARDING SITE STUDY:
Judy Hoxsey, Library Director/Estes Park Public Library reported
on the site selection process and planning studies which had
occurred to date. A 10-member Site Survey Committee has been
formed to study various locations available upon which to con-
struct the new library. The Bond Park site was approved by the
Public Works Committee in February, 1986; however, the park will
not accommodate the proposed 14,000 square foot building. The
Library Board is in the process of determining boundaries to form
a Library District. The District boundaries would be placed
before the electorate, followed by a request for a $2 Million
Dollar bond issue to construct the building. The Committee
reviewed a sketch indicating the following sites: (1) Placing
the building on the eastern corner of Bond Park and onto
MacGregor Avenue - the possibility of allowing one-way traffic in
a northerly direction on MacGregor Avenue has yet to be explored;
(2) Placing the building on the parking area located directly
behind the Municipal Building which would result in a loss of 63
parking spaces; (3) Constructing the building on the southern
portion of Parking Lot #1, facing East Elkhorn Avenue - this site
would result in a loss of 46 parking spaces; and (4) Locating the
building on a portion of the Husky Service Station property
recently purchased by the Urban Renewal Authority. In determing
the size of the building, current population figures were used;
they indicated a 9,000 net square foot library was necessary
today. In projecting future use, the Library Board is proposing
a total building size of 14,000, with the possibility of adding a
second floor. Discussion followed regarding parking spaces,
including the loss of spaces, payment for each space deleted and
variance and financing. The Committee recommends priority be
given to constructing the library at the Husky Service Station
Site (a portion thereof), and that Bond Park be listed as the
second site location. The Committee also recommends reducing the
building to 9,000 net square feet, with the possibility of
expanding the library some time in the future.
1986 STREET IMPROVEMENT PROGRAM - REVIEW OF PROPOSED PROJECT:
Public Works Director Widmer presented the proposed 1986 Street
Improvement Program (a copy is attached and made a part of the
record of these proceedings by reference thereto). This year's
project proposes 2.75 miles of overlay, two areas of new paving
and miscellaneous areas of curbing at a total estimated cost of
$161,600. $200,000 was budgeted for this project. Should bid
prices vary significantly from the estimate, the project list
could be modified to bring the project in line with the budget.
The Estes Park Medical Center submitted a letter requesting the
Town pave a portion of the hospital access road from Stanley
Circle Drive south 200' to the hospital property. Discussion
followed with the Committee recommending approval of the 1986
Street Improvement Program, including the Medical Center request,
authorizing Public Works Director Widmer to begin the bid
process, returning to the Committee for further review.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - May 15, 1986 - Page two
TREGENT PARK DEDICATION CEREMONY - DISCUSSION:
The Committee recommends setting June 11, 1986 at 11:00 A.M. to
conduct a Dedication Ceremony for Tregent Park. Honored guests
will be Helen and Harold Tregent. The Committee also recommends
Director Widmer proceed with organizing the festivities.
ESTES PARK GOLF COURSE BOUNDARY - UPDATE:
Concerning the east boundary of the Golf Course Property, Public
Works Director Widmer reported a meeting was held with the Estes
Valley Recreation and Park District, Mr. Bill Van Horn and the
Town. Additional meetings will be conducted between the District
and Mr. Van Horn and the Recreation District will advise the Town
of any additional information.
OFFER TO SELL 1977 GMC SNOWPLOW - REVIEW OF BIDS:
The Committee reviewed two bids on the Town's offer to sell the
1977 GMC Snowplow: Asphalt Maintenance, Loveland - $5,777.00
and the Estes Valley Recreation and Park District - $6,000.00,
which included a "payment plan plus interest." The Committee
recommends selling the 1977 GMC Snowplow to the Estes Valley
Recreation District for a net bid price of $6,000.00.
REPORTS:
The American Public Works Association Annual Conference will be
held in New Orleans September 20 - 25, 1986.
The Tregent Park Restrooms were opened to the public May loth.
The Town has paid for 96% of the project.
Work has begun on the Prospect Mountain (NE) Drainage Project.
The Restroom Remodeling Project located in the east wing of the
Municipal Building is nearing completion and they should be in
operation by Memorial Day Weekend.
As requested by the Committee February 21, 1985, affected proper-
ty owners will be installing a sidewalk along 120/130 East
Riverside Drive.
There being no further business, the meeting adjourned.
Vickie O'Connor, Town Clerk
MAY 271986
:S1tS PARK
BOARD OF TRUSTEES
1986 Proposed Street Improvements
A. 2" Overlay Avg.
Length Width Area Est. Cost
Ft. Ft. SY. $
1. Peak View - Prospect Est. Dr. to City Limits 1575 '27 4725 $24,100 (2)
2. Stanley Ave. - Aspen to SH 7 1415 24 3773. 14,500
Sub Totals 2990 8498 $38,600
B. 11" Overlay
1. Virginia Dr. — Bank Alley No. to Vir. Lane 1175 27 3525 10,600
2. Black Canyon Drive 1424 24 3797 11,400
3. Columbine - Aspen to Birch 565 18 1130 3,400
4. Woodstock' 1175 24 3133 9,400
5. Virginia Lane 320 19 676 2,000
6. Courtney Lane - End to Lott 657 21 1533 4,600
7. Birch - Prospect to Aspen 1950 21 4550 13,700
8. Riverside Dr.- W. Prosp. Village Dr. to Crags 687 22 1679 5,000
9. Fall River Dr. - David Dr. to Blue Spruce 1960 21 4573 13,700
10. Manford Ave - Woodstock to Community
914 36 3656 11,000
11. Driftwood Ave. - High St. S. to new paving 575 20 1278 3,800
Sub -Totals 11402 29530 $88,600
TOTALS 2" & 12" 14392 38028 $127,200
1. Overlay costs estimated $31.00/Tn + 4% patching at $11.00/SY = $3.00/SY
for 11 ; $3..85/SY for 2".
2. Peak View estimated using 2" overlay + Petromat at $1.25/SY = $5.10/SY
C. New Paving (2")
1. Driftwood Avenue
Paving: 330' x 20' = 750 SY = 83 TN @ $45/Tn = $3,750
Curbing: 660 LF @ $2.50/LF = 1,650
Grading & Base: 1,500
TOTAL = $6,900
2. Bailey Lane
Paving: 900' x 18' = •± 1900 SY = 210 Tn @ $45/Tn = $9,500
Curbing: 1800 LF @ $2.50/LF $4,500
Curbing & Base: $3,500
$17,500
TOTAL NEW PAVING = $24,400
D. Curbing - 6" Asphalt Curb
Miscellaneous Areas: 2,000 LF @ $2.20/LF $ 4,400
E. Estimated Cost Recap
A. 2" Overlay
B. 12" Overlay
C. New Paving
D. Miscellaneous curbing
Admin/Insp/Engr
$38,600
$88,600
$24,400
$ 4,400
$ 5,600
TOTAL $161,600
BUDGET $200,000