HomeMy WebLinkAboutMINUTES Public Works Committee 1994-07-28BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee
July 28, 1994
Committee: Chairman Gillette, Trustees Doylen and Miller
Attending: All
Also Attending: Trustee Marshall, Town Administrator Klaphake,
Public Works Director Linnane, Clerk O'Connor
Absent: None
Chairman Gillette called the meeting to order at 9:30 A.M.
UTILITY EASEMENT VACATION REOUEST FOR LOT 1, VALLEY VISTA ADDITION.
Several years ago, the Town installed a water line in Moccasin
Circle Dr. (borders this site on the north) and abandoned a 2"
water line that extends east and west across this lot. The utility
easement was required to be vacated when the Planning Commission
and Town Board conditionally approved the Development Plan for this
site. The Water Dept. no longer needs the easement; however, staff
expects the Developer to circulate a routing slip for approval by
all affected utility agencies. The Committee recommends approval
of the request contingent upon the owner paying Town Attorney fees
(preparation of an ordinance) and approval by affected utility
agencies.
EASEMENT VACATION, BLOCK 1, MOUNTAIN GOLF VILLAS SUBDIVISION.
Following approval of a development plan for multi -family units,
ownership changed, and new floor plans for the golf course units
were lengthened by 2'. The engineering firm was unaware of these
changes, and thus Units 1 and 2 were partially located on an
existing easement. Therefore, the owner is requesting the Town
vacate the north 2' of the easterly 35' of the easement. There are
no utilities within the easement at this time and the existing
bicycle path falls within the southerly 10' of the easement. The
Developer must also circulate a routing slip for any affected
utility agencies for this request. As the integrity of the
easement remains intact, the Committee recommends the request be
approved contingent upon the owner paying Town Attorney fees
(preparation of an ordinance) and approval by affected utility
agencies.
STANLEY HISTORIC DISTRICT - REOUEST APPROVAL OF STREET NAME.
Administrator Klaphake reported that EPURA requested names be
submitted for the official name of the Stanley Historic District
roadway, and that "Steamer Parkway" is being recommended.
Discussion followed, with the Committee recommending said roadway
be officially named Steamer Parkway.
NEIGHBORHOOD MAIL DELIVERY, PHASE II - REOUEST AUTHORIZATION TO BID
AND AWARD CONTRACT.
The 1994 Budget includes $23,000 for the construction and
maintenance of cluster boxes for Phase II (continues to the south,
along the Highway 7 corridor). This amount matches Phase I.
Following discussion with postal personnel, eight sites were
selected. Public comments have been requested and received. Phase
I has been completed and 380 of the 700 units have been utilized.
Due to time -schedule constraints, staff requested authorization to
bid and award the contract if the bids do not exceed the budget.
The Comittee recommends staff be authorized to bid the project,
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 28, 1994 - Page 2
submitting the bids directly to the Town Board
1994 WATER LINE PROJECT - REQUEST AUTHORIZATION
Three bids were received for the 1994 Water
follows:
for approval.
TO AWARD CONTRACT.
Line Projects, as
BT Construction
Kitchen & Company
U. S. Contractors, Inc.
$141,910
158,305
234,571
BT constructed large water line projects for the Town in 1988, '91
and '93, and they have an excellent record. The budget is $142,000
and contingencies for potential change orders could be financed
from an equipment item for a water plant that will not be purchased
due to a recent change in the water treatment process. Staff will
closely monitor the project, particularly concerning any change
orders. Standard procedure requires Committee approval for any
change order. The Committee recommends accepting the low bid in
the amount of $141,910 submitted by BT Construction and that any
change orders be funded from the equipment line item as described
above.
REPORTS.
The Committee reviewed the Customer Service Response and Water
Reports for June. Water plant production has increased 17% over
the same period in 1993.
Staff, including Town Attorney White, have been working on the
Water Augmentation Plan and the report and legal plea will be
submitted to the Water Court by August 1. Staff anticipates that
the Plan, which serves as the Town's Water Use Plan (describes the
quantity of water taken out and returned to the river), will be
submitted to the Court and that the Water Court Judge will,
hopefully, reach a favorable decision concerning the Plan by March,
1995. The Committee will receive updates as additional information
is received.
In an effort to assist Estes Park residents in water conservation,
the Department is providing free water conservation plumbing
fixture kits. The kit contains a low use shower head which limits
water usage to 2.5 gallons/minute, 2 low use sink aerators which
limit water usage to 2 gallons/minute, and a toilet dye tablet
packet to check for leaks. One kit will be allowed per family and
motels may have kits equal to the number of their units. The
Department will maintain an accounting system on all kits requested
for statistical information.
CDOT has held public meetings for the Highway 7 and 36 Projects.
The Project should be bid in October/November 1995, with
construction to begin the end of 1995 and completion Spring/Summer
1996. The Town's 1995 Budget will include funding for the proposed
Highway 7/Manford Avenue Intersection right-of-way acquisition and
possible driveway relocation for Estes Park Lumber.
Staff has spent numerous hours obtaining permits for the Lake Estes
Hike/Bike Trail, and anticipates going to bid the end of September,
1994. Construction will begin as soon as possible following the
award of the contract. It is possible that the funding will be
encumbered in 1994 for construction in 1995.
EPURA Executive Director Anderson briefed the Committee on the
Riverwalk Project, Phase III which is located in the area from the
Nagl Walkway bridge to the east side of the Park Theater Mall. The
Project involves approximately 150' of Fall River and EPURA has
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 28, 1994 - Page 3
received easements for the area of construction. The river wall on
the north and south banks of the Fall River will be stacked
sandstone and the walkways will be structurally supported due to
the limited space in which to work. A public bridge will be
constructed adjacent to the Park Theater Mall to the complete the
circulation pattern. The south side of the river will have a
platform area to provide views of the north side and the river.
The Nagl bridge will have a new railing installed to match the
existing bridges in the Plaza. Construction is anticipated to
begin in late September and work in the river completed in
November. The walkway work will begin as the river wall is
completed. The Project will be completed in May, 1995. Parking
spaces will be realigned to gain two additional handicapped spaces
per ADA guidelines; however, the total number of available spaces
remains the same.
There being no further business, Chairman Gillette adjourned the
meeting at 10:40 A.M.
'GC %�x.� 4/
Vickie O'Connor, CMC, Town Clerk
AUG 91994
xJ -s t iir ESTES A-R4
BOARD OF TRUSFZ:S