HomeMy WebLinkAboutMINUTES Public Works Committee 1995-08-24BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee
August 24, 1995
Committee:
Attending:
Also Attending:
Chairman Gillette, Trustees Doylen and Miller
All
Town Administrator Klaphake, Public Works
Director Linnane, Manager Sievers, Clerk
O'Connor
Absent: None
Chairman Gillette called the meeting or order at 8:01 A.M. and
advised that Agenda items would be shifted to accommodate CDOT
Representatives; however, the minutes correspond to the printed
Agenda.
BRONZE SCULPTURE SITE SELECTION - REFERRAL.
At their meeting held July 19, 1995, EPURA recommended the
installation of a life-size bronze cougar sculpture in Riverside
Plaza. EPURA and the Town would fund installation of the rock
base. Funding for the sculpture is being raised with leadership of
the Rotary Club. The Committee recommends approval of the
recommended site in Riverside Plaza, and the joint funding by EPURA
and the Town.
WATER DEPARTMENT WATER LINE PROJECT - REOUEST APPROVAL OF CHANGE
ORDERS.
To date, the Committee has approved $15,600 in change orders. At
the June 22nd Committee meeting, staff was to verify the change
order of $17,183.60 for additional asphalt. The change order
quantity has now been field -measured and the change order has been
reduced by $4,723.60 for a total of $12,460. The original contract
amount is $230,266; change order totals are $15,600 and $12,460 for
a final contract amount of $258,326. The budgeted amount is
$250,000, and the additional $8,326 will be funded from the Highway
7 Water Main Project which has been postponed. The Committee
recommends the change order for the amended amount of $12,460 be
approved.
WATER DEPARTMENT WATER TANK PROJECT (GLACIER CREEK AREA).
Staff requested authorization to bid the project for a one -million
gallon tank near Glacier Creek. The budget contains $750,000;
design will be complete in the next two weeks; and the bids are to
be returned in October. Staff is negotiating an Agreement with the
YMCA concerning construction start dates, and upon execution by the
YMCA, staff will submit the Agreement to Town Attorney White.
Staff anticipates the Committee will review the Agreement in
September. The Committee recommends staff be authorized to bid the
project as identified above.
CDOT HIGHWAY 7, HIGHWAY 34, AND ELKHORN AVENUE PROJECTS -
SCHEDULING UPDATE.
Pursuant to the Committee's recommendation concerning construction
during the summer season, Director Linnane prepared and requested
CDOT consider the following construction schedule during the "peak
season" (June 15 - Sept. 15):
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - August 24, 1995 - Page 2
Highway 7 Widening Project.
Begin construction
Temporarily halt construction
Begin construction
Complete construction
Highway 34 Widening Project
Begin construction
Temporarily halt construction
Begin construction
Complete construction
March 1, 1997 (weather
permitting)
June 15
September 15
November, 1997 (or later)
March 1, 1996 (weather
permitting)
June 15
September 15
November, 1996 (or later)
Highway 34/East and West Elkhorn Milling/Overlaying Project
Construction schedule is the same as the Highway 34 Widening
Project. Suggest milling and overlaying be performed at
night.
Doug Ramos, CDOT Regional Director, appeared before the Committee
and confirmed that CDOT will be sensitive to the concerns and needs
of the community, and he stated a plan would be presented to help
allay those concerns. He introduced Dave Forsyth, Design Engineer,
who presented drawings of the projects and identified construction
plans. Doug Pearson, Construction Office/Loveland, commented that
their contract could prohibit work after 6:00 P.M. on Friday until
6:00 A.M. on Monday; however, this stipulation will lengthen the
time of construction. Lou Garton/Regional Construction Engineer,
reported on CDOT's public relations program where telephone/fax
numbers are published, and partnership sessions are held with the
community. These sessions have proven to be very successful at
other construction sites.
Mr. Ramos presented a letter from Gary Wardell, Mayor/Town of
LaSalle which stated that LaSalle was completely satisfied with the
cooperation that CDOT and the general contractor provided the Town
and its citizenry.
Concerning the overlay on Elkhorn Avenue, the roto-milling and
paving may occur at night; however, due to anticipated night
temperatures, paving may be difficult. Staff requested the milling
match the curb and gutter and also that the extreme cross -slopes be
eliminated. CDOT will review and comment on cross -slope milling.
CDOT will bid all of Highway 34 and Elkhorn Avenue as one project,
with separate parameters for each. If construction is started in
April, CDOT anticipates completion in 80 working days (August 1±).
CDOT's general contractor is to contact all affected property
owners and advise them on how access will be accomplished and how
work is being done at their site.
Following additional discussion, the Committee recommends staff and
CDOT schedule meetings (while all business owners are in
operation), following the Scottish Festival to apprise everyone
(motel owners, downtown merchants, residents, and emergency
services) of CDOT's construction plans, with construction from
Memorial Day to Labor Day to cease at 6:00 P.M. on Fridays, and
begin at 6:00 A.M. on Mondays, including holidays (such time
constraints may be amended by the affected property owners).
Director Linnane is to coordinate the mailing effort for the public
notices.
Chairman Gillette expressed his appreciation to CDOT for their
presentation, stating CDOT has been responsive to the Town's
concerns.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - August 24, 1995 - Page 3
1995 STREET OVERLAY PROJECT - REOUEST AUTHORIZATION TO AWARD BID.
The 1995 Budget contains $150,000 for the improvement and
maintenance of the roadway infrastructure. The slurry seal
portion, $50,000, was previously approved. Bid packages were
issued to six paving companies and bids were received on August 22:
Company Bid
Bituminous Roadways, Longmont $109,372
Western Mobile, Boulder 122.550
Connell Resources, Ft. Collins 135,650
Bestway Paving, Greeley No Bid
Coulson Excavation, Loveland No Bid
Kehn Construction, Ft. Collins No Bid
A total of $14,363 was carried over from the 1994 Budget and it
will be added to the 1995 Budget which will allow for a 5%
contingency. Staff is researching references for Bituminous
Roadways. The Committee recommends accepting the low bid submitted
by Bituminous Roadways, and allowing expenditures of the budgeted
amount. Staff is to report on the reference check during the
September 12 Town Board meeting; should a problem arise, the bid is
to be awarded to the next lowest bidder, directing staff to reduce
the project scope accordingly.
E.V.R.P.D. GOLF COURSE MANAGEMENT AGREEMENT - APPROVAL.
In a letter dated June 15, 1995, Executive Director Gengler advised
that the District is seeking an amendment to the Operating
Agreement for the Estes Park Golf Course. The District desires to
renew the Agreement for an initial five-year period, with an option
to renew for an additional five-year period, including automatic
one-year renewals following the end of either five-year period. As
stated at the Committee meeting June 22, 1995, the request is based
upon the District's financial long-range planning, added security
for lease -purchase agreement, and the security of a long-term
agreement with the Town.
Chairman Gillette acknowledged a letter dated July 17, 1995
submitted by Henry F. Pedersen, Jr. which, in summary, urged the
Town to require the District to rid their areas of litter, spray
for weeds, remove trash and rotting boats, and exhibit sound
leadership. Consensus of the Committee was to deny the request,
stating further action is not required as the Agreement will
automatically renew on one-year intervals. If the District so
desires, the Town could issue a letter to assist EVRPD on their
financial planning with regard to purchases, etc.
REPORTS.
The Committee reviewed the Customer Service Response and Water
Reports for June.
There being no further business, Chairman Gillette adjourned the
meeting at 9:24 A.M.
YAPP 6VcD
SEP 1 2 1995
Vickie O'Connor, CMC/AAE, Town Clerk
TO m OF ESTES ES PARK
BOARD OF TUIS5 ES