HomeMy WebLinkAboutMINUTES Public Works Committee 1996-04-26BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee
April 26, 1996
Committee: Chairman Doylen, Trustees Barker and Hix
Attending: All
Also Attending: Administrator Klaphake, Public Works Director
Linnane, Clerk O'Connor, Construction Manager
Sievers, Street Foreman Johnson, GIS System
Analyst Kraft, Fleet Manager Shanafelt
Absent: None
Chairman Doylen called the meeting to order at 9:30 a.m.
ELKHORN AVENUE CURB AND GUTTER - REOUEST APPROVAL TO PROCEED WITH
CONSTRUCTION.
To maintain an expedient work schedule prior to the Elkhorn Avenue
repaving in May, earlier this month staff received approval from
Committee Chairman Doylen to immediately begin the curb, gutter and
concrete pan repairs and replacement. The project was concurrently
bid with an EPURA project which has overlapping scope and location.
The 1996 budget contains $25,000 for the Town's portion of the
project. Bids were received April 8, with G. L. Hoff being the low
bidder. The bid for the Public Works portion was $14,904.78.
Staff issued a purchase order for the project and are proposing to
increase the unit quantities up to, but not exceeding, the budget
of $25,000 to produce the maximum amount of repairs on Elkhorn
prior to its repaving by CDOT. The Committee recommends approval
(retroactive) on the aforestated work on Elkhorn Avenue, for
$14,904.78, authorizing staff to increase the unit quantities up
to, but not exceeding, $25,000.
/ STREET SLURRY SEAL PROJECT - AWARD CONTRACT.
Manager Sievers reported that the 1996 Budget contains $200,000 for
street improvements and he requested a portion for slurry seal. In
the past, the street improvement project consisted of overlaying
asphalt. In an effort to improve this system, staff researched
slurry seal. This seal is 1/4" thick, provides water proofing,
protects the asphalt from ultra violet rays, and helps prevent
deterioration.
In 1995, Quality Resurfacing was the low bidder, and staff desires
to add -on to the existing contract by increasing the quantity of
their contract by 55,000 sq. yds. This will reflect a $50,000
expenditure from the 1996 Budget. Quality Resurfacing is still
under contract for the 1995 job and both the 1995 and 1996 projects
will be completed by June 27th±. Staff reviewed the list of
proposed streets to receive the slurry seal application;
installation will cover approximately 24 additional streets.
Staff anticipates returning to the Committee in August for approval
to proceed with expenditure on the remainder of the project for
regular asphalt paving scheduled in September. The Committee
recommends approval of the request to expend $50,000 for the Street
Slurry Seal Project.
STREET VEHICLES - AUTHORIZATION TO PURCHASE.
Trustee Hix declared a conflict of interest, and stated he would
not participate in discussion nor recommendation.
The 1996 Budget includes $89,300 for a new street sweeper. Street
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - April 26, 1996 - Page 2
Foreman Johnson reported that the Street Dept. has one new vacuum
sweeper and one old mechanical sweeper, and that staff is proposing
to replace the existing mechanical sweeper with an Elgin Pelican
Street Sweeper. Roy gave the Committee an overview of the street
sweeping operation (amount of man hours, miles of streets, and
material reclaimed for 1995), and compared the mechanical v. the
vacuum -style sweeper. A committee was established to judge the
equipment that would best meet the Department's needs, and the
aforestated Elgin was recommended. This is due in part to the
Department already owning a vacuum sweeper.
Director Linnane reported that the cost of the sweeper, minus
$4,500 trade-in, is $82,535 and that the sweeper would be leased
and amortized over five years. The leasing price over five years
is $19,394.07. Financing bids were obtained, with The Estes Park
Bank offering an interest rate of 5.625%. Following discussion,
the Committee recommends staff be authorized to purchase the Elgin
Pelican Street Sweeper, accepting the lease/purchase bid from The
Estes Park Bank for payments of $19,394.07/year for five years.
✓ STREET DEPARTMENT VEHICLES - AUTHORIZATION TO PURCHASE.
Director Linnane reported that a multi -passenger vehicle (budgeted
at $25,000) is being requested to replace a standard pickup truck.
The multi -passenger vehicle would be utilized in snow removal as
well as transporting employees. The trade-in value of the pickup
truck is $3,000, and staff believes the truck is worth at least
$7,000 and that it would be most beneficial to retain the truck and
purchase a new vehicle outright.
Staff reviewed the 2% local discount policy, and following
discussion, the Committee recommends staff be authorized to
purchase a Ford Bronco, accepting the bid price of $20,562.17
submitted by Rains Motor Co., retaining the existing pickup truck
in the fleet. The local 2% discount policy results in Rains being
the low bidder. Administrator Klaphake directed staff to select an
unobtrusive color for this and all Town vehicles.
FUEL TANK ABANDONMENT PROJECT - PROPOSAL.
Director Linnane offered a review of this project, reiterating that
staff is requesting three underground fuel tanks located at the
Street Shop area be abandoned pursuant to new EPA guidelines for
this type of tanks. The new guidelines go into effect in 1998.
With the guidelines, all underground tanks must have sophisticated
monitoring systems and/or structure. The tanks could be retro-
fitted; however, pursuant to a Feasibility Study conducted by RMC,
such was considered too expensive. RMC earlier presented six
alternatives and the Town elected to enter into an agreement with
Larimer County that all Town vehicles would fuel at the Larimer
County Terminals site, adjacent and north of the Town Shops. The
Police Dept. will refuel at the School site in 1997.
Staff budgeted $80,000 this year to abandon the underground fuel
tanks and piping, and transferring the fuel site to the County
area. RMC prepared a scope of services for design and construction
management, and staff requested to bid the project with bids being
due in May/June. This process will allow the Town to meet
established regulation deadlines and obtain a contractor in a
timely fashion (1997). The Committee recommends staff be
authorized to request bids, returning to the Committee when bids
are received. Staff also intends to return to the Committee in the
near future with a long-term Use Agreement with Larimer County.
If the Town utilizes the existing Fleet Dept. data base, the system
must be upgraded to be compatible with the County's system. Based
BRADFOR❑ PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - April 26, 1996 - Page 3
on discussion with affected personnel, staff believes it would be
best to install a network pc that would communicate with most
department personnel (Water, L&P, Muni. Bldg.); however, a network
pc was not budgeted in 1996. It is estimated that the network
hardware and software would cost between $10,000 and $17,000.
Shawn Kraft, the Town's GIS Computer Analyst, briefed the Committee
on network systems, their flexibility, expansion capabilities,
improved interface, reduction of duplication in purchasing
software, and the ability to go "on line" immediately. Based upon
the efficiencies reported on above, the Committee directed staff to
solicit prices and return to the Committee with cost details.
-WATER PROJECT CHANGE ORDERS - REOUEST APPROVAL.
Director Linnane presented change order estimated as prepared by
RMC for the following Projects:
1. Interconnection of Summit Dr. and Highway 34 - Change
order to facilitate the actual location of the existing
8" water line - $715.00±.
2. Hillside Ln. - the Town requested BTC Const. excavate an
existing service line to allow the new 12" water line -
$480.00±.
3. Pine Lane and Portion of Grand Estates Dr. - the water
line at both locations had to be relocated into the
asphalt portion of the roadway due to interference with
the new natural gas line - $22,860±.
4. The Town requested BTC Const. mobilize another pipeline
excavation crew to expedite the construction schedule -
$2,500.00±.
Cost of all four items above will be shared with CDOT (42%), thus
the Town will pay $15,400± and CDOT will pay $11,150±. As the
projects are well within budget, the Committee recommends approval
of all four change orders for the estimated amount of $26,550.
TRAFFIC SIGNS - REOUEST BY CITIZEN TO REVIEW/AMEND.
Sally Anderson, citizen, submitted two traffic sign requests: (1)
change the existing "yield" sign to a "stop" sign at the
intersection of Spruce and Big Horn Drives. Staff confirmed that
this site is nearly a blind corner for on -coming traffic due to
site distance, steepness, and trees. Director Linnane reviewed the
Manual on Uniform Traffic Control Devices (MUTCD), confirmed that
the restricted site distances could warrant a stop sign. Street
Foreman Johnson will inspect the area to determine whether or not
the trees could be trimmed. Property owners are to be contacted
prior to any trimming. The Committee believes the request is
warranted, and staff was directed to proceed. (2) install a
"continuous lane" sign for those turning right off Riverside Dr.
onto Elkhorn Ave., going east. Staff advised that a "continuous
lane" sign is illegal and that a similar sign, which is legal, is
an "added lane" international symbol sign (MUTCD W4-3). Staff
referred to the Manual, and does not believe this sign is warranted
due to the intersection's existing "right turn on green" sign with
the right turn red and green traffic signal being contradictory to
the requested added lane sign. Summer installation of the bollards
and striping will assist traffic in the turning lane, and based
upon public safety and liability issues, the Committee this request
be denied.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - April 26, 1996 - Page 4
/LAKE ESTES HIKE/BIKE TRAIL - PRESENTATION OF "CAUSEWAY" PORTION AND
REOUEST APPROVAL OF SCOPE OF SERVICES.
Director Linnane briefed the Committee on the former grant
application process utilized in obtaining State/Federal funding for
the recently completed Lake Estes Hike/Bike Trail. Staff was
contacted in late February 1996 by Elaine Spencer/Larimer County
Engineer and Jeff Manual/CDOT Engineer, who reported that funding
for enhancement projects in the amount of $162,500 was recently
made available (Weld County canceled their project). The Lake
Estes Causeway Trail was initiated, and an application was filed.
The Causeway Trail begins at the fisherman parking area west of the
causeway, along the north side, and ends/blends by transitioning
into Mall Road. A Master Plan of the entire lake, prepared in-
house, was displayed. The plan includes the aforementioned 10'-
wide concrete walkway which is 10'± lower than the highway, along
the causeway, a bridge across the Big Thompson, downstream of the
Dam, and a trail through the Power Plant property. RMC prepared a
survey and quantity estimates of $380,672, not including the cost
for design and construction management ($44,760). The total
project is estimated at $425,000; federal funding would be
approximately $162,500. Staff was informed by Will Tully of the
Bureau of Reclamation, that a formal environmental assessment will
not be required for this phase, thus a permit could possibly be
issued within six weeks and the project could begin as early as
September 1. Staff advised that construction could possibly begin
as late as December 1, 1996.
Staff reported on the funding approval process which requires a
recommendation from the Upper Front Range Transportation Committee
(UFRTC). Members of this Committee verbally advised Town staff
that they would recommend the project via a May UFRTC meeting, with
a recommendation letter to follow.
Administrator Klaphake reported on the Larimer County Open Space
sales tax revenues which are calculated based upon population or
sales tax generation --each city will receive the higher of the two.
The Town's actual return for January was $9,286.87, and staff is
estimating revenues as high as $200,000 for the year. These
revenues are to be utilized only for trails and open space, thus
the Causeway Trail would be eligible. The 8-year appropriation
could be shared between trails and open space. Staff is suggesting
the Town leverage the Open Space revenues for grants, such as
ISTEA.
RMC submitted a design, coordination, and construction management
scope of services for $44,760 which includes a bridge design which
can be deleted depending upon funding. Staff confirmed that Light
and Power will install conduit in the concrete walkway that should
not restrict the BOR in accessing their plant or dam sites. RMC
and the Town have talked to WAPA and they have no objection to the
project. WAPA and staff will meet at the site on May 1 to finalize
the previously -mentioned discussion. The Committee commended staff
for their effort on this project, recommends staff be authorized to
use the aforestated sales tax revenues as a match with ISTEA
funding, and also recommends accepting the Scope of Services
submitted by RMC in the amount of $44,760. Staff also praised
Larimer County Engineer Spencer and CDOT Representative Manual for
notifying the Town on the availability of State/Federal funds.
REPORTS.
The Committee reviewed the Citizen Service Response and Water
Reports for March.
Director Linnane briefed the Committee on the Hwy. 34/Hwy.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - April 26, 1996 - Page 5
7/Elkhorn Ave. CDOT Projects, reporting that the curb, gutter,
etc., east of the Hwy. 34/36 intersection, will not be completed on
the south side of Hwy. 34 by May 25 as scheduled; the utility work
will delay the curb and gutter installation scheduled completion
date by at least 2-3 weeks. The Elkhorn Ave. Project west of the
Hwy. 34/36 intersection is on schedule and should be completed by
Memorial Day Weekend.
The Annual River Clean up is scheduled May 18. Town employees are
volunteering their time, and the Town is volunteering trucks - the
public is being asked to help by meeting at the Marina at 10:00
a.m. and clean-up the rivers and lakes until Noon. All volunteers
will then be treated to a barbecue lunch.
The Glacier Water Tank Project is on schedule and there have been
no change orders thus far. Completion is scheduled May 17 and this
new tank will double fire protection in the Estes Valley.
There being no further business, Chairman Doylen adjourn the
meeting at 11;20 a.m.
MAY 1 4 1996
Town ��tn ppyyr7 ESIrc.
0r
Vickie O'Connor, CMC/AAE, Town Clerk