HomeMy WebLinkAboutMINUTES Public Works Committee 1996-06-27BRAOFORO PUBLISHING CO.
RECORD OF PROCEEDINGS
/Public Works Committee
June 27, 1996
Committee:
Attending:
Also Attending:
Absent:
Chairman Doylen, Trustees Barker and Hix
All
Town Administrator Klaphake, Construction and
Public Facilities Manager Sievers, Streets and
Parks Superintendent Speedlin, Deputy Clerk
Kuehl
None
Chairman Doylen called the meeting to order at 8:00 a.m.
HIGH DRIVE WATER DISTRICT BULK WATER AGREEMENT APPROVAL
Manager Sievers explained that the High Drive residents contacted
the Town to provide bulk water to their area. The Agreement has
been reviewed by Attorney White and Town Staff. The Committee
recommends approval of the High Drive Water District Bulk Water
Agreement.
GLACIER WATER TANK CHANGE ORDER - APPROVAL
Duckels Construction submitted a change order as follows:
1. Additional 4' concrete ring installation on the sample
pump access manhole to stabilize the slope from the new
storage tank and match with the grade: $852.00.
2. Additional 3/4" rock installed on the access roadway:
$600.00.
3. Construction of a rock retaining wall north of
adjacent to the backwash pond to eliminate
encroachment into the pond: $2,000.00.
The Committee recommends approval of the change order
$3,452.00 as described above.
the tank
backfill
totaling
FUEL TANK ABANDONMENT PROJECT - APPROVAL OF AGREEMENT AND BID
Manager Sievers reported that the Agreement for the fuel tank
abandonment project has been reviewed by Attorney White, Larimer
County, and Town Staff. The only anticipated change is a reduction
in term length. The Committee recommends approval of the general
concept of the Agreement with the understanding that term length
may be amended. The contract will be awarded July 10 with
completion of the project by August 1.
Bids received for the removal of the Fleet Maintenance facility
fuel tank included demolition of the existing fuel tanks and
piping/asphalt patching (Schedule A) and a unit rate price for
excavation and disposal of contaminated soil (Schedule B) are as
follows:
Flint Engineering & Construction
Allwaste Environmental
Gallenstein & Associates
Schedule A
$22,254.15
$22,616.00
$29,579.00
The Committee recommends approval of the bid from Flint
and Construction for $22,254.15 with a maximum budgeted
Schedule B
$20.10/cy
$32.00"
$19.75"
Engineering
expenditure
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee, June 2/, 1996 - Page 2
of $80,000. It was noted that liability for any contaminated soil
will be the responsibility of the contractor.
RAVEN AVENUE/LONE PINE DRIVE BUDGETED DRAINAGE PROJECT
Manager Sievers explained
plan to the Town to share
developer of Storer Ranch.
design cost for the Town is
Staff finalize the costs for
9 for approval.
Van Horn Engineering has presented a
the cost of this project with the
The estimated preliminary survey and
$3,642.50. The Committee recommends
presentation to the Town Board on July
Sievers explained that an easement has been obtained from the Inn
of Estes Park, and an easement is expected from Sombrero Stables.
Administrator Klaphake explained that the historic flow will not
change, and most of the drainage will be underground. Coulson
Construction may be retained for construction if unit prices are
acceptable to Staff.
BIG HORN DRIVE PARKING
Manager Sievers explained that 9 to 12 additional parking spaces
are possible along Big Horn Dr. from Spruce Dr. to Cleave St. with
no physical change to the roadway, except the addition of striping
and removal of the No Parking signs. The Committee recommends
Staff stripe Big Horn Dr. as described to provide additional
parking spaces.
PAVEMENT MARKING
Manager Sievers explained that the budget includes $200,000 for
capital roadway improvements and requested that up to $30,000 of
this budget be allocated for street striping, including crosswalks,
stop bars, and outlining. It was suggested that epoxy striping and
pre -formed markings be used downtown due to the life expectancy
(approximately four years), reflectivity and esthetics. It is
further suggested the purchase of these products be sole sourced
through In -Line Traffic Marking Company because of their consistent
price structure. The Committee recommends up to $30,000 of the
$200,000 for street overlay be allocated to street striping.
Administrator Klaphake noted that the allocation of this money will
not alter the number of streets budgeted for overlay, because the
less expensive slurry seal process is being used in many areas.
Sievers noted that three streets planned for overlay will be
delayed awaiting completion of construction in the area and not
budget restrictions.
Administrator Klaphake requested Public Works Staff negotiate with
CDOT to remark: (1) the Hwy. 36 bridge area, allowing both lanes
of traffic access to downtown, and (2) the parking stalls in front
of Bond Park on Elkhorn Avenue to prohibit double parking.
REPORTS
The Committee reviewed the Customer Service Response Report for
May.
National River Clean -Up Update: Superintendent Speedlin noted that
the project was expanded this year and reported the participation
of 300+ volunteers and 40 organizations. Town staff included
Linnane, Speedlin, Goehring, Hulburt, and Franklin. The Town
donated trucks and A-1 Trash donated two dumpsters. Chairman
Doylen commended all participants for their efforts toward a
successful river clean-up and the Parks Department for landscaping.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public works Committee, June 27, 1996 - Page 3
Highway 7, Highway 34, Elkhorn Overlay Projects Update: Town
Staff continues to meet weekly with CDOT to review the status of
the Highway 34 project. The undergrounding is complete and paving
is planned for June 26. Steamer Dr. will remain closed until
paving and markings are in place in the area. Construction updates
are faxed directly to the Highway 34 businesses. Trustee Barker
commended the contractor for both cooperation and the willingness
to work with the business community. The utility engineering study
for Highway 7 will be complete July 31, which will allow subsurface
utility work to be started prior to the State widening project.
Chairman Doylen adjourned the meeting at 9:17 a.m.
Tina Kuehl, Deputy Town Clerk