HomeMy WebLinkAboutMINUTES Public Works Committee 1997-07-24BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee
July 24, 1997
Committee:
Attending:
Chairman Doylen, Trustees Barker and Hix
Chairman Doylen, Trustee Hix
Also Attending: Town Administrator Klaphake, Public Works
Director Linnane, Water Supt. Goehring,
Const. Manager Sievers, Ass't. Street Supt.
Johnson, Clerk O'Connor
Absent: Trustee Barker
Chairman Doylen called the meeting to order at 8:00 a.m. and
announced the Agenda sequence would be amended to allow a
"consent format" for Items 8 through 12 listed below.
Administrator Klaphake reviewed each item, and the Committee
recommends approval of Items #8 through 12 as presented.
1. STREET DEPARTMENT 1-TON SNOWPLOW
PURCHASE.
In a memorandum dated July 23, 1997,
reported on the following bids:
Burt Chevrolet
Rains Motor Co.
Transwest Trucks
Hajek Chevrolet
Fogle GMC
AUTHORIZATION TO
Fleet Manager Shanafelt
$38,840.41
38,746.00
39,900.00
40,477.00
No response
The budgeted amount is $46,000. Ass't. Johnson explained
that employees tested a Ford truck owned by the YMCA and
this vehicle, as well as other makes and models, did not
meet job and/or driver requirements. The Chevrolet was
stronger structurally, and had the necessary power. He also
confirmed the specifications were written for a competitive
bid. Rains Motor Co. did not meet 6 specs.
The Committee recommends accepting the Burt Chevrolet bid in
the amount of $38,840.41.
2. BIG HORN DRIVE WATER LINE - APPROVAL OF SCOPE OF SERVICES
AND BIDDING PROCEDURE.
Director Linnane reported that approximately 700' of steel
8" water main will be replaced with a 12" line at the upper
portion of Big Horn Dr. This site is a maintenance problem
area. RMC has submitted a scope of services in the amount
of $7,270. Total construction cost, including repairing the
road, is estimated at $51,400.
In addition, staff is negotiating with Kearney & Co. to
reach an acceptable unit price, that matches or is
comparable to the 1996 unit price. If negotiations are not
successful, this project would be bid out with the results
being returned to the Committee for additional review.
The Committee recommends approval of RMC's Scope of Services
in the amount of $7,270, authorizing staff to continue
negotiations with Kearney for the unit pricing. Should
negotiations fail, staff is authorized to solicit bids.
Staff was directed to contact other utility agencies to
determine whether there is mutual gain in performing any of
their work in this area during the same construction period.
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 24, 1997 - Page 2
3. SOUTHERN INTERCONNECT PROJECT (BLUEBELL DR.) - AUTHORIZATION
TO ENTER INTO COST -PARTICIPATION AGREEMENT.
RMC, on behalf of Jerry Solomon/Prospect highlands
Subdivision, is requesting cost participation from the Town
on construction of a water line that would interconnect the
Marys Lake Water Treatment Facility pressure zone into the
Prospect Estates and Peak View areas. Approval would allow
for improved water flow in the area, elimination of pumping
costs and pressure loss in the water system during pump
operation, and better system operation.
The level of Town participation is proposed at 84% of the
construction cost based upon the conclusion that the
Prospect Estates water system has existing benefits which
offset the benefits of the new 8" water main extension. The
developer would provide 16% of the construction cost, obtain
an easement across the Watson property, and design and
construction -related engineering services. Staff time would
be minimal; benefits well exceed the expense. Director
Linnane added that during peak periods, the water system
cannot keep up with demand; with the interconnect, water
pressure could be increased, the existing pump station and
tank would be abandoned; affected residents would be removed
from the pump rate; and fire protection to the east would be
increased.
The cost estimate for 1,000 1.f. is $55,000 of which $47,000
would be paid by the Water Dept. Although this project is
not budgeted, it could be funded from excesses in the Hwy. 7
fund. The project is a significant portion of the Water
Master Plan, and staff time would be minimal, thus staff is
in favor or proceeding.
Construction will cross the Watson property and Mr. Watson
will not be required to share in the cost of the new water
line. If Mr. Watson desires to obtain Town water, he could
do so by purchasing a water tap. The Committee recommends
approval of the Agreement.
4. SPUR LANE WATER LINE EXTENSION AGREEMENT (Revised) -
APPROVAL.
Director Linnane reported that the Committee previously
approved oversizing of the Spur Lane water line, plus
reimbursement for the second party, consisting of five
property owners (Dersham, Sishler, Friehe, Donhowe, and
Sully). The Second Party is now seeking approval for
reimbursement from potential private property owners
desiring to connect to the new line in the amount of
$2,834.50/ea. (adjacent five lots, not originally included
in the Second Party extension). The term of the Agreement
is for twenty years. The Committee recommends approval of
the Revised Agreement as presented.
5. AUGMENTATION PLAN - NEGOTIATIONS & SETTLEMENT OF SCOPE OF
SERVICES.
The RMC Water Rights Group in Longmont submitted a total
project estimate of $23,600. Staff explained that the
Augmentation Plan is now in the Court system, and deadlines
have been met. There were five oppositions (NCWCD, State &
County Water Courts, NPS, and the Big Thompson Water User
Group), and all were considered standard as they were merely
seeking additional information. The Scope of Services
includes engineering work to satisfy all the objectors and
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 24, 1997 - Page 3
to obtain stipulations from them, prima facie trial in Water
Court should that be recommended by the attorney or water
judge. Staff's goal is to obtain a decree approved by the
Water Court late this year or early next year. If the
estimate is greater than $23,600 it will be returned to
Committee for further consideration. The Committee
recommends approval of the Scope of Services Estimate of
$23,600 submitted by RMC. There is no legal component added
at this time.
6. HWY. 7 WATER MAIN PROJECT - APPROVAL OF FINAL CHANGE ORDER.
Staff summarized the change orders, reporting on the
following costs of $1,110, $8,500, and $1,615.04 for a total
change order cost of $37,629.86. The Town's portion is
$11,633.94 and CDOT's portion is $25,995.92. Staff
anticipates these are the final change orders for this
project. The Committee recommends approval of the Change
Orders.
7. BLUEBELL DRIVE WATER MAIN PROJECT - APPROVAL OF CHANGE
ORDER.
A change order in the amount of $1,729.00 for extra fittings
used on this project was reviewed. This is the first change
order, and staff expects an additional change for repair of
the gravel road ($3,500±). The Committee recommends
approval of the Change Order in the amount of $1,729
submitted by Kearney & Sons Excavating. The total contract
amount is now $81,166.00.
8. STREET IMPROVEMENT PROJECT APPROVAL TO BID OVERLAY
PORTION.
The 1997 Budget contains $200,000 for the rehabilitation of
streets throughout the Town. Expenditures to date are:
Slurry Seal
Chip Seal
Misc. Projects
Castle Mtn. Rd./Hwy. 34 Rock
$40,604
21,549
11,196
42,400
The remaining balance is $84,251, and, providing the
improvements do not exceed this b lance, staff is requesting
authorization to bid the projectSee Consent Items on Page
1 for action.
9. IVY & ROCKWELL STREET BRIDGES/REHABILITATION PROJECTS -
APPROVAL TO SOLICIT BIDS.
The Budget contains $200,000 for the rehab of Ivy and
Rockwell Street Bridges. This is a federal grant project,
administered by CDOT and reimbursed at 80%. To date,
$33,500 has been expended (RMC $28,500 for design &
construction engineering, and $5,000 for CDOT's management).
Following completion of the detailed planning and design
stages set forth by CDOT, staff is requesting to the bid the
project, award the contract, and construct the improvements
if work does not exceed the remaining balance of $166,500.
See Consent Items on Page 1 for action.
�q/q7 - Ate pduAei- '7)Le7' ` /f7' p� n T'.` u c q / �..1 0
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 24, 1997 - Page 4
10. ST. VRAIN AVENUE SIDEWALK PROJECT - RETROACTIVE APPROVAL.
Staff reported that Cornerstone Concrete replaced
approximately 1,000 sq. ft. of sidewalk along Hwy. 36 at a
cost of $15,000 (budget). Administrator Klaphake authorized
this expenditure and also the expenditure of an additional
$7,500 to complete this project up to the Hwy. 36 Bridge.
The Committee approved the original expenditure and the
additional expenditures. See Consent Items on Page 1 for
action.
11. FIFTH STREET "DEAD END" ROAD PROJECT - APPROVAL TO SOLICIT
PRICE & PROCEED.
Fifth Street, at Manford Avenue, will be closed in
conjunction with the signalization of Manford Ave. This
closure was previously discussed and approved at the April
27, 1995 Committee meeting. The Town budgeted $10,000 and
construction will be limited to this amount. See Consent
Items on Page 1 for action.
12. HANFORD AVENUE "NO PARKING" SIGNS ADJACENT TO FAIRGROUNDS -
APPROVAL TO REMOVE.
There are "no parking" signs along the south side of the
fairgrounds on Manford Ave. and staff requested they be
removed as they are not being enforced. See Consent Items
on Page 1 for action.
13. BRODIE AVENUE CONCRETE CURB & GUTTER - RETROACTIVE APPROVAL
OF PRIVATE COST -SHARING PROJECT.
Staff reported that the Elk Ridge Subdivision developer
exceeded Town standards by agreeing to install concrete curb
and gutter and sidewalk in lieu of asphalt within the limits
of the subdivision. The developer agreed to contribute
$5,000 toward concrete curb and gutter along Brodie Ave.,
west to Fish Creek, and the Town would expend $8,200.
Director Linnane explained the benefits of concrete in lieu
of asphalt, adding that in the future, staff will be
recommending concrete for all curb and gutter, and staff
desires to change the Town's standards by requiring concrete
curb and gutter along all public streets. Drainage was
reviewed, and the Committee recommends retroactive approval
of the expenditure of $8,200 to share in the cost of
concrete curb and gutter.
REPORTS.
Hwy. 7 Project Schedule: within 2-3 weeks, concrete curb and
sidewalk should be installed from the Holiday Inn south to Graves
Avenue. Staff anticipates construction will be completed the
first of October.
Construction Manager Sievers reported that he has received
inquiries on several telephone pedestals that appear to be non-
functioning. USWest was contacted and they will begin
identifying problem pedestals and hire a contractor to remove
them - staff anticipates this work will be completed by October.
The Committee commended Manager Sievers in responding to the
public, taking the initiative by contacting USWest, and receiving
a commitment to correct the situation.
Manager Sievers also reported on the Larimer County Task Force on
Street Cut Standards. Criteria has been established and a
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee - July 24, 1997 - Page 5
technical writer has been hired to finalize regulations. The
Task Force includes Ft. Collins, Berthoud, Windsor, Larimer
County, and Estes Park. The end result of the Task Force is the
establishment of uniform standards throughout the County. Larimer
County has taken the lead in establishing a fee structure which
should go into effect October 18t; staff will be requesting
adoption of the new fees and the new standards the first of the
year. Additional information will be presented to the Committee
in October/November. Meetings will be scheduled with private
contractors and utility companies to review criteria and fees.
The Committee complimented Manager Sievers for his work on the
Task Force.
There being no further business, Chairman Doylen adjourned the
meeting at 9:05 a.m.
Vickie O'Connor, CMC/AAE, Town Clerk
052WilrelmOir
APPROVE
AUG 1 2 1997
1 TO' OF EMS
BoAkD OF TRUST.' ES
' ••*o...-o..rz..ect.soo..,Nhr.mt