HomeMy WebLinkAboutMINUTES Public Works Committee 1997-08-28BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee
August 28, 1997
Committee:
Attending:
Also Attending:
Absent:
Chairman Doylen, Trustees Barker and Hix
All
Town Administrator Klaphake,' Public Works
Director Linnane, Facilities Manager Sievers,
Deputy Clerk Kuehl
None
Chairman Doylen called the meeting to order at 8:10 a.m.
FALL RIVER LN. ROAD IMPROVEMENT - REQUEST APPROVAL OF REIMBURSEMENT
AGREEMENT IF PROJECT IS APPROVED FOR 1998
Director Linnane explained a 900' section on Fall River Ln. was
never paved but is maintained by the Town. In 1981 the Town and
developer entered into an Improvement Covenant and Hold Harmless
Agreement which states that the owners of lots abutting this area
are responsible to the Town for the cost of paving, prorated on the
basis of street frontage, and that the Town shall be entitled to
recover all costs of enforcing this covenant including attorney and
court fees. Director Stamey noted that this subdivision was
developed prior to improvement guarantees. Director Linnane
requested that this project be budgeted for 1998, that the owners
be required to sign a Reimbursement Agreement upon submittal of a
building permit, and that building permits be held until this
Agreement is finalized. Linnane also requested that the owner of
Lot 1, though it does not abut this area, was not assessed when
other portions of Fall River Ln. were paved and should be included
in this assessment. Administrator Klaphake questioned the legality
of the Improvement Covenant and the inclusion of Lot 1 in this
assessment, and requested a legal opinion from the Town Attorney.
The Committee recommends paving of 900' on Fall River Ln. be
budgeted for 1998, that the Town Attorney provide a legal opinion
on the 1981 Improvement Covenant, and that building permits be held
until the September 9 Town Board meeting when the Agreement and the
legal opinion will be presented to the Town Board.
BLUEBELL WATER MAIN PROJECT - REQUEST CHANGE ORDER APPROVAL
Director Linnane presented the final pay request from Kearney and
Sons for work on the Bluebell 8" water main extension, which
includes $4,500 plus $289 for quantity adjustment, and $350 for a
rockwall addition. The Committee recommends approval of $5,139.00
to Kearney and Sons for the Bluebell Water Main Project.
DONATED BRONZE SCULPTURE - REQUEST TO INSTALL IN TOWN PARK
EPURA Executive Director Anderson explained that the Town has been
offered a 48" tall bronze recirculating fountain sculpture called
"Wishful Thinkin'" by Sonny Lee, Cheyenne, Wyoming, who wants the
sculpture placed in Tregent Park. The Sculpture Committee has
approved this donation. Approximately $5,000 will be needed to
provide water and electricity and a plaque. Senior Planner Joseph
will prepare a site plan, and the sculpture will be placed in 1998.
The Committee recommends approval of this sculpture for placement
in Tregent Park and requests Director Anderson write a thank you
letter to the donor.
WATER DEPARTMENT CARBON FEEDER
- REQUEST
Director Linnane explained that
purchase of a carbon feeder for
TO PURCHASE
the budget includes $11,000 for
the Marys Lake Water Treatment
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee, August 28, 1997 - Page 2
Plant. A bid for $10,100 from Municipal Treatment Equipment in
Lakewood was received. This equipment is needed to eliminate taste
and odor from the water, and will only be used when necessary. The
Committee recommends approval of the carbon feeder purchase in the
amount of $10,100 from Municipal Treatment Equipment.
HWY. 7 WATER LINE & STORM SEWER CHANGE ORDER - REQUEST APPROVAL
Director Linnane explained that CDOT requested the Town relocate a
fire hydrant to facilitate construction of the storm drainage
system. Weinland Construction submitted an invoice in the amount
of $4,400.00 for this work. The Committee recommends approval of
$4,400.00 to Weinland Construction, to be reimbursed by CDOT.
IVY AND ROCKWELL STREET BRIDGE CONSTRUCTION
Manager Sievers explained that the bids received for this
construction are $10,000 higher than the budgeted amount. This is
due to the need for specialized qualifications and equipment to
perform high pressure grouting, of which one in the State is
qualified. Many aspects of construction are lumped into certain
CDOT specification line items, causing those dollar amounts to be
inflated. The three items affected along with the bid amounts are:
rip rap, $1,020 per cubic yard; grouting, $735 per cubic yard; and
bridge rail, $233 per linear foot. Budgeted amount is $166,500.
The low bid is $173,574.02. The engineer estimated high on
quantities, causing a possible $15,000 reduction. Federal funds
will refund 20% to the Town. Other Public Works projects are under
budget and can be transferred if necessary. The Committee
recommends approval of $173,574.02 for completion of the
Ivy/Rockwell St. Bridge rehabilitation. Construction will start
Sept. 15 with completion by October 31.
REPORTS
Highway 7 Project Update: Signal lights will be installed after
October 15, with completion of the project expected by October 31.
Construction of the bike path will continue. Trees at Eagles
Landing need to be removed as they were placed on the right of way
after the condos were built too close to the property line.
Lake Estes Causeway Trail Project, Phase 2: G.L. Hoff will start
construction September 8 with expected completion October 1. EVRPD
will complete the area along the Fire Hall and Bureau, and the Town
will provide a connection to Hwy. 7. Manager Sievers requested a
letter of agreement with the Recreation District regarding plans
for that area. Sievers will determine the length of the complete
path.
Chairman Doylen adjourned the meeting at 9:12 a.m.
Ta.. » K„.Y.X
Tina Kuehl, Deputy Town Clerk
SEP 9 1997
TO a:',`: OF ES S Pc t
WARD D Oz TaSSTEES