HomeMy WebLinkAboutMINUTES Public Works Committee 2000-03-16BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Town of Estes Park, Larimer County, Colorado, March 16, 2000
Minutes of a Regular meeting of the PUBLIC WORKS COMMITTEE of the
Town of Estes Park, Larimer County, Colorado. Meeting held in the
Municipal Building in said Town of Estes Park on the 16' day of March,
2000.
Present: Chairman Baudek, Trustees Barker and Jeffrey
Attending:
Absent:
Also Attending:
All
None
Town Administrator Widmer, Public Works Director
Linnane, Construction Manager Sievers, Deputy Town
Clerk van Deutekom
Chairman Baudek called the meeting to order at 3:30 p.m.
MALL ROAD/LAKE ESTES TRAIL PROJECT - APPROVAL
Director Linnane reported that bids for the Mall Road/Lake Estes Trail
construction were received from Kitchen ($383,983.02) and G.L. Hoff
($545,798.04). Larimer County would not allow a trail within the R.O.W. due
to physical limitations and stated the substandard design of the existing
roadway would present a safety issue to trail users. Therefore, the roadway
will be realigned to accommodate the trail and satisfy Larimer County
concerns. Since the area is highly visible and a "Gateway" area to Estes
Park, the Light and Power Department budgeted to underground the power
lines along Mall Road and across Hwy. 36. Construction is scheduled to
begin in April and be completed by Memorial Day. The cost/budget analysis
is as follows:
Kitchen/Cost Budget
Trail (GOCO/EVRPD) $ 144,798.70 $ 173,000.00
Roadway (P.W. Dept.) 174,389.32 266,000.00*
Electrical UG (L&P Dept.) _64.795.00
125, 000.00
$ 383,983.02 $ 564,000.00
*The General Fund budget is $286,000, which includes the $20,000
Design/Construction Management fee payable to Van Horn Engineering.
Trustee Hix, Chairman of the Light & Power Committee recommended
approval of Kitchen's bid for the electrical underground portion of the
project. The Committee recommends accepting the low bid in the
amount of $383,983.02 submitted by Kitchen.
FISH HATCHERY HOUSE ROOF REPAIR — APPROVAL
Director Linnane reported that the roof of house #1 located on the Fish
Hatchery property is very badly blistered and should be replaced. The
BRADFORD PUBLISHING CO.
RECORD OF PROCEEDINGS
Public Works Committee — March 16, 2000 — Page 2
2000 budget includes $5,000 for this roof replacement. Local bids were
received from Apex Roofing ($5,100) and Halls Roofing ($3,435) to include
a full tear off of the old blistered roof. Staff will hold an additional $1,400 as
a contingency, should any unforeseen difficulties arise. Therefore, the total
requested expenditure is $4,835. The Committee recommends
accepting the low bid from Halls Roofing in the amount of $3,435 and
the $1,400 contingency requested by staff.
2000 STREET IMPROVEMENT PROJECT (STIP) - APPROVAL
Construction Manager Sievers reported that the STIP is broken down into
categories of work that take place throughout the year to provide
maintenance and rehabilitation to the asphalt and roadway infrastructure.
The 2000 budget contains $250,000 for the project. Expenditures for the
categories discussed are as follows: Slurry Seal - $50,000, Chip Seal -
$50,000, Patching - $20,000, Overlay - $120,000, and Striping - $10,000
totaling $250,000 for the STIP in 2000. The Committee recommends
proceeding with the STIP expenditures and schedule as presented.
The overlay portion will be brought back to Committee when bids are
received.
REPORTS.
The Customer Service Response Report for February 2000 was
reviewed.
The Highway 36/7 Project is on schedule. Traffic will be rerouted mid -April
to allow work on the existing lanes and the project should be completed the
beginning of June.
There being no further business, Chairman Baudek adjourned the meeting at
4:05 p.m.