RECORD OF PROCEEDINGS
Public Works Committee
March 8,1973
Committee:Chairman Dannels;Trustees Petrocine and Prosser
Attending:Chairman Dannels;Trustee Prosser
Also Attending:Town Administrator Hill,Street Superintendent McCracken,
Town Engineer Van Horn
Absent:Trustee Petrocine
NEW MUNICIPAL BUILDING:
Mr.Bill Simons,architect for DMJM-PhillipsReister,Inc.,presented
and reviewed the working drawings for the construction and remodeling
of the new Municipal Building.
Cost estimates were presented as follows:
Construction cost $622,960
A/E 49,000
$671,960
Paid in 1972 -14,388
1973 Cost $657,572
The Committee recommends to the Board of Trustees that the architect
be instructed to proceed with bids on the new Municipal Building.The
bids will be received at a Public Works Committee meeting on April 16,
1973,and bid award will be made on April 23,1973 by the Board of
Trustees.
There being no further business,the meeting adjourned.