BUDGET —1975:
Town Administrator Hill submitted the proposed 1975 Public Works Budget to
the Committee for its consideration prior to formal budget hearings.Several
items were discussed in detail:
Public Restrooms:
The Committee discussed the possibilities of refurbishing present
public restroom facilities and also the construction of new restrooms
elsewhere within the Town.The Committee recommends that an additional
$50,000 be budgeted for new restroom construction and $5,000 be budgeted
for remodeling of the present facilities.
Public Works Building:
Director of Public Works Van Horn reported that a new public
Works building of approximately 8,000 square feet would cost $170,000.
The Committee recommends budgeting this amount in 1975 for the building.
Street Equipment:
Dir.of Public Works Van Horn described for the Committee the street
equipment proposed for purchase next year,including a used street sweeper
and a multi—purpose tractor.
Tallant Park Project:
Director of Public Works Van Horn submitted to the Committee a detailed
cost outline for the proposed Tallant Park and Picnic Area.Totaling $120,000,
this project will be funded through matching Bureau of Outdoor Recreation and
Town funds.(Cost estimate attached)
Municipal Building Maintenance:
Town Administrator Hill submitted to the Committee a new contract for
maintenance of the municipal building by Village Maintenance Service.The
proposed contract represents a 2/square foot increase over the present
contract,with a total cost of $11,716.80 per year.The present contract
expires August 31.After discussion and cost comparison with other types
of maintenance plans,the Committee recommends the Town enter into a con
tract with Village Maintenance Service,effective September 1,1974,
through December 31,1975.
RECORD OF PROCEEDINGS
Public Works Committee
August 7,1974
Page Two (2)
Museum Budget Request:
The Museum Board’s 1975 Budget request was considered by the Committee.
The Committee recommends the omission of the Museum’s capital improvement
request of $60,000 for a building addition.An additional request of $3500
for expenses in:the coming year is recommended for approval.(Copy of Request
attached)
Revenue Sharing Funds:
The Committee recommends two expenditures to be allocated from revenue
sharing funds in 1975.These include the extension of walk and bikeways
along highway 7 at a cost of $15,000,and the replacement of the East
Riverside Drive Bridge at a cost of $35,000.
Public Works Department Personnel:
Upon reviewing proposed public Works projects and their manpower
requirements for next year,the Committee recommends the hiring of an
additional full—time,permanent employee to increase total full—time
employees in the department to five.The Committee also recommends the
hiring of another seasonal employee next year to increase total seasonal
employees to four.
MUNICIPAL BUILDING LEASES:
Town Administrator Hill submitted a letter from the School District
requesting a five—year initial lease period and two five—year options for
renewal for the space occupied by the district in the municipal building.
The district also requested that usage of the Town Board Room be included
as part of a new lease.The Committee recommends that the Board Room be
made available for the District’s use,but that the original terms of the
lease remain unchanged.
The lease proposed by the Town to the Upper Thompson Sanitation District
was rejected by the Upper Thompson Sanitation District Board.
GREENBELT:
Town Administrator Hill reported to the Committee that only three
properties for greenbelt acquisition have been offered for sale to the
Town by owners along West Riverside Drive.The Committee felt only two of
these three tracts were desirable for the Town’s purposes and recommends
purchase of tracts B &C for development of a small park,to be planned
in harmony with possible future development of adjacent properties.At
this time,however,no condemnation of adjacent properties is recommended
until further study of the area has been completed.
MCINTYRE ROAD:
A letter from the Town Attorney concerning the status of McIntyre Road was
received by the Committee.It is the Attorney’s opinion that no evidence has
yet been presented that the road has been legally dedicated and accepted as
public.Upon the advice of legal counsel,it is the Committee’s recommendation
that McIntyre Road be considered private property and not a public road under
the jurisdiction of the Town.
00
RECORD OF PROCEEDINGS
Public Works Committee
August 7,1974
Page Three (3)
STREET CLEANING REQUEST:
Director of Public Works Van Horn presented a request which he had received
earlier from Mrs.Hatlestad to wash the street in front of Morehead Shopping
Center.Concern was expressed by the Committee as to the Town’s general
policy of street cleaning.Upon recommendation of the Committee,this
particular request was directed for immediate action by the street department
with an additional request to the staff to develop policy guidelines for
future street cleaning.These guidelines will be presented to the Committee
at a later date.
There being no further business,the meeting adjoured.
Dale G.Hill,Town Administrator
APPflOVE[]
\UG 1%1974
IU1N U EIES PAK
BOARD OF T?USTEES
n
SUMMARY OF ESTIMATED COSTS
TALIANT PARK
Engineering,Site Planning and Supervision:
A.Lump Sum (Substantially In-House)
Contractural Services:
A.Parking —60 spaces @ $600.00
B.Restroom —2 Winterized @ $10,000.00
C.Shelters —3 18’x 36’@ $1,000.00
D.Decorative Fencing -2000’@ $2.00
E.Underground Utilities
(1)Water —500’@ $6.00
(2)Sewer —200’@ $8.00
(3)Power -2000’@ $4.00
(4)Sprinkler System
F.Combination Foot Bridge-Sewer Crossing
C.Stream Bank Stabilization
H.Grass and Plantings
I.Walkways —3500’@ $1.00
Direct Costs:
A.Picnic Tables -20 @ $80.00
B.Litter Barrels —10 @ $20.00
C.Drinking Fountains -4 @ $400.00
D.Lighting —15 @ $500.00
Total Estimated Cost
$4,000.00
36,000 •00
20,000.00
3,000.00
4,000.00
3,000,00
1,600.00
8,000 •00
7,000.00
4,000 •00
7,000,00
8,000.00
3,500.00
1,600.00
200.00
1,600.00
7,500.00
$120,000.00
ESTES PARK AREA HISTORICAL MUSEUM,INC.
Box 1691
Estes Park,Colorado
August 6,1974
TO:MAYOR HARRY TREGENT
BOARD OF TRUSTEES
Town of Estes Park
FROM:Howard I.Stewart and
David Hieb -Committee
SUBJECT:Budget Year -1975
ADMINISTRATION:Cleaning,etc.$50.00
Curator 1,200.00
Heating Gas 200.00
Hostesses 1,210.00
Insurance 125.00
Lights 50.00
Miscellaneous 80.00
Repairs 200.00
Supplies 200.00
Telephone 125.00
Trash Hauling 10.00
Water 50.00
TOTAL:$3,500.00
CAPITAL:$60,000.00
Note:The capital expenditures of $60,000.00 is for the purpose of
completing the museum building as it was originally planned
by adding on the final addition.This addition will be ap
proximately 40’x 40’with a full basement.The basement is
to include a vault and a repair area in addition to other
storage.The upstairs,of course,will be for displays.
The Museum Board feels that the time is now to update our
Museum and bring it into being commensurate with other town
facilities.We have some artifacts that are not displayed
in some cases and not properly displayed in others.It is
the Board’s desire to make the Estes Park Museum an out
standing organization of its kind in the area.The only
way this can be accomplished is to have adequate facilities.
We thank you for your consideration.