RECORD OF PROCEEDINGS
Water Committee Meeting
January 2$,1975
Committee:Chariman Prosser;Trustees Dannels and Sutter
Attending:Chairman Prosser;Trustees Dannels and Sutter
Also Attending:Town Administrator Hill,Mayor Tregent
Absent:None
UPPER THOMPSON SANITATION DISTRICT WATER LINE:
The purpose of this meeting is to make a recommendation to the
Board of Trustees regarding the letter dated January 24,1975 from
the Upper Thompson Sanitation District.This letter is attached
to and made a part of these proceedings.
On January 6,1975,the Water Committee made a recommendation
(approved January 14,1975)to participate with the Upper Thompson
Sanitation District as set fourth in the Town’s water extension
policy.Under the existing water extension policy the Town would
pay for the increased size of the 880 foot water line from a
location in Olympus-Bellview Heights to the Sanitation Plant.
The estimated cost to the Town would be $3,200
The attached letter states the final decision of the Upper Thompson
Sanitation District and that is as follows:The Town would pay
$8,463 and the Upper Thompson Sanitation District would execute a
change order with their contractor for the installation of an
8 inch DIP water line.
The Water Committee makes the following recommendation to the
Board of Trustees:
Since receipt of the Upper Thompson Sanitation District’s latest
request concerning the plant water tap,the Estes Park Water
Committee has carefully examined its 1975 budget.In conjunction with
the budget,the Water Committee is expecting to study a new Priority
Construction Report from its engineers at the regular February meeting.
Since a reply to Upper Thompson Sanitation District’s request cannot
wait for further engineering study,or communication with possible
future customers of an over—sized line,the Committee makes the
following recommendations to the Board of Trustees:
The Water Department still favors an over—sized line under provision
of existing regulations regarding extensions,details of which have
been reported to the Board of Trustees and Directors of Upper Thompson.
If the Upper Thompson Sanitation District finds itself unwillingor
unable to comply with this policy at this time,the Committee recom
mends that the Upper Thompson Sanitation District select the water
tap alternate agreeable to it under Estes Park Water Department
regulations.The Committee does not presume to dictate the alternate,
since the Upper Thompson Sanitation District also has its obligations
and its monetary restrictions.
c Fkflrv’ir’D
S
____________________
375 Dale G Hill,Town Administrator
>,.:..
00
1974 WATER SYSTEM IMPROVEMENTS
Highway 7 -8”Main
Highway Crossing
Highway Crossing
Highway Crossing
“Y”—Junction —6”Main
McGregor Line -4”Main
Stanley Circle to Cummorrah Heights -4”Main
Connecting Birch and High Street -4”Main
High Pines -4”Main
Line at City Dump -4”Main
Majestic Pines
Highway 34,Summit Drive -4”Main
Pipe and Fittings in stock
________
Devon Drive —8”Main
Twin Drive -8”Main
Pine Lane -8”Main
ACTUAL
$69,951
5,740
9,600
2,368
4,134
17,936
2,500
6,268
$118,497TOTAL
co
ESTES PARK WATER DEPARTMENT
1975 MAIN IMPROVEMENT PROGRAM
P.C.R.
Priority Report Work Estimated
No.No.*Description Done By Cost
1 Replacing undersized 2”
and 3”sections of Devil’s
Gulch line across McGregor
Ranch,approx.3,000’(+)Town $32,000
2 20(A)Replace undersized 2”main
in Twin Drive from Highway
7 northwest.400’Town 7,000
3 8(A)Cross connection at Spruce
and Cleave Town 2,000
4 25(A)Lower Broadview -Mary’s
Lake Connection,(alt.
for report item 25)
2,000’Contract 35,000
5 High Street between Aspen
and Birch 200’Town 2,200
6 Virginia Drive -South from
near Wonder View Avenue to
existing dead-end main
1,000’Contract 17,000
7 16(C)Avalon Drive from Country
Club Drive south to Brook
Drive,then east to connect
to existing main in Brook
Drive (alt.route for re
port items 16 and 31)1300’Town 22,300
8 21(C)Along Highway 66 -from
Marys Lake Road,easterly
approx.1800’Town 19,200
TOTAL $137,200
*From PCR 1968 Report,“A Plan for Growth of the Estes Park
Water System”.
NOTE:
Rock at $17.17
Dirt at $10.67
4
flm flfl
UPPER THOMPSON SANITATION DISTRICT
ESTES PARK,COLORADO 80517
DISTRICT
BOARD P.0.Box 568
Giles H.Gere,Chairman
Phone 586-4544E.H.(Andy)Anderson January 21k,1975
John Marks
Louis C.Pettyjohn
Jack Rumley
SECRETARY-
TREASURER
Harper Glezen
—MB.DALE HILL,Town Administrator
MANAGER Town of Estes ParkFredH.Carpenter P.0.Box 1200
Estes Park,Colorado 80517
Dear Dale:Be:UTSD Water Line
Waste Water Treatment Plant
Your letter dated December 13,1971k
We have carefully reviewed the above referenced water line construc
tion situation,and advise that we must act immediately with respect
to authorizing our prime contractor (Schedule ii)Project No.C—080322,
basis one of the three alternatives:
(1)Install the water line per plans and specifications
now under contract.
(2)Change material of pipe as specified from 1”poly—
vynlechioride (PVC)to ductal iron pipe (14”)(DIP).
(3)Cooperate with the Town in the installation,by our
contractor (Western States Construction Company),in
the installation of 8”ductal iron pipe purchased from
you at $6.90 per foot and complying with your recluire—
ments relative details as indicated in your above
referenced letter.
We believe No.3 above represents the best option in supplying this
District’s Waste Water Treatment Plant needs,and would materially
benefit the community as a whole.As discussed many times in the
past,our limits are rigid and dictated by the federally funded
project in which we are now involved.Through consultation with
our engineers,and our contractor,the following appears to be an
objective solution:
f a)Through a Change Order,UTSD will install 14”DIP in lieu
of the 14”PVC as specified in the approved plans.
WORK TO END POLLUHON
‘;00
MR.DALE HILL 2.January 24,1975
Estimated cost to UTSD ——$2,173.00
(b)Western States bid for constructing 8”
DIP water line,with pipe purchased from
Town stock at $6.90 per L.F.,basis
cutting Hwy.34,not boring ——$10,636.00
Essentially,this District would be obligated to pay $2,173.00
over and above the Schedule II contract now held by Western
States Construction Company.The overage of $10,636.00 would
be reduced by that amount,leaving a difference of $8,463.00.
We ask that you pay this difference in order that our combined
efforts will result in future water service to property owners
in the Spruce Knob and Fish Creek sectors.
Your letter of December 13,1974 indicates an amount of $3,136.00
supportable by the current Water Line Extension Policy.During
our recent phone conversation you indicated that you would make
an effort to secure Committee agreement and accord in solving
the problem.
If you can secure approval by the Board of Trustees to spend an
additional $5,327.00 we can proceed.
If you cannot,we have no alternative but to proceed immediately
as we previously planned soley providing water to our Treatment
Plant.
Please give us your reply by February 1,1975.
Yours very truly,
UPPER TH0IWS0N SANITA
R.Carpenter,
FRC:jm