Special Water Committee
January 17,1985
Committee:
Attending:
Also Attending:
Chairman Hix,Trustees Aldrich,Wood
Chairman Hix,Trustee Wood
Mayor Dannels,Town Administrator Hill,Water
Superintendent Richards,Public Works Direc
tor Widmer,Finance Officer Vavra,Bob
James/Rocky Mountain Consultants,Bill Van
Horn and Todd Plummer/Van Horn Engineering
Absent:Trustee Aldrich
LAKE MEADOW CONDOMINIUMS -SITE DEVELOPMENT PLAN #13:
As referred by the Board of Trustees at their meeting held
January 8,1985,the Water Committee met with Van Horn Engineer
ing to discuss “fire flows”for Lake Meadow Condominiums.
Discussion followed regarding “Insurance Services Office (ISO)”
standards and existing code requirements.Using the “ISO”
standards,the existing 4”water line serving Grand Estates
Subdivision will not adequately serve Lake Meadow Condominiums.
The Municipal Code states the minimum size water main for a new
extension shall be 6”;the code also states that if the Town
determines that it is in the Town’s best interest to increase the
pipe size on new water main extensions the customer is
installing,the Town shall pay for the cost to increase the pipe
size and related material to by determined by the Town.Water
Superintendent Richards submitted a proposal for the water main
extension for this particular project which would result in the
Town increasing the water main size to 10”and 8”and installing
an additional fire hydrant.The developer would pay 65%or
approximately $10,400 and the Town would pay 35%or approximately
$8,600.The proposed main extension agreement is as follows:
6”Main Extension =790 G.P.M.
20’Highway Cut @ $26.25/ft
520’Grand Estates Drive @ $7.79/ft
6”Tap
Three 6”Valves @ $232.51/each
Three 5¼”Valve Boxes @ $63.00/each
One Fire Hydrant
One 6”Fire Hydrant Tee
6”x600’of Pipe @ $6.97/ft
Asphalt 4’x600’@ $1.26/sq.ft
All-thread,Nuts,Bolts,etc
Compaction
Rounding-off the total =
10”and 8”Main Extension =1,400 G.P.M.
Upgrade/Town oversizing:
One Fire Hydrant $
One Tee
One Valve
Additional 10”Tap
10”Pipe
8”Pipe
One 4”and one 8”Valve
One 8”x8”x4”x4”Cross
6”Main Extension
$2,100.00
4,050.00
1,175.00
697.53
189.00
572.00
111.00
4,182.00
1,900.00
600.00
400.00
$15,976.53
$16,000.00
572.40
111.00
232.00
400.00
225.00
942.00
372.00
220.00
$3,074.40
$16,000.00
8”Main Extension $19,074.40
0 C
BRADFORD PUBLISHING CO.RECORD OF PROCEEDiNGS
Special Water Committee -January 17,1985 -Page two
6”Water Line =790 G.P.N./8”Water Line =1,400 G.P.M.
Average Fire Hydrant Flow/3 Hydrants =350 G.P.M.
Existing 350 G.P.M.=35%
Required =1,000 G.P.M.=65%
Cost of 6”water line $16,000
Town Portion =35%$5,600
Developer’s Portion =65%$10,400
Upgrade to System:
Town —1,400 G.P.M.-350 G.P.M.=1,050 G.P.M.Increase
divided by 1,400 G.P.M.=75%
Developer -790 G.P.M.-350 G.P.M.=440 G.P.M.Increase
divided by 1,400 G.P.M.=55.6%
Following further discussion,the Committee recommends Van Horn
Engineering submit the proposed water main extension agreement to
the developer and advising the Town of the developer’s decision.
There being no further business,the meeting adjourned.