Chairman Dickinson called the meeting of the Water Committee to
order at 2:00 P.M.
PROSPECT MOUNTAIN DEVELOPMENT COMPANY -REQUEST REVIEW OF WATER
SERVICE AGREEMENT.
Pursuant to a request submitted by Don Spomer/Prospect Mountain
Development Company,the Committee reviewed the water service
agreement for Prospect Estates Addition.Mr.Spomer particularly
requested review of Paragraph “E”relating to the Town monitoring
the actual cost of the system for a period of five years.The
agreement was signed March 22,1983;however,the water system
was not conveyed to the Town until April,1984.As the five-year
period has not yet elapsed,the Committee recommends Director
Widmer advise Mr.Spomer in writing that the request is prema
ture;the review will,however,be conducted as prescribed in
said agreement.
MDC 1989 PAYMENT -REQUEST TO AMEND PAYMENT SCHEDULE.
Town Administrator Klaphake advised discussion on this item could
take place in open session;however he cautioned the Committee to
safeguard their inquiries.The Committee reviewed a memorandum
dated August 1,1988 submitted by Town Attorney White.In
discussions held with Gary Mandarich/MDC,Mr.Mandarich inquired
as to the possibility of making the 1989 payment over a period of
time for the purchase of the Town’s Windy Gap units.Phasing the
payments could be beneficial to both MDC and the Town due to
consideration of the Town’s needs and those of MDC.With
acceptance of a mutually agreeable arrangement,MDC could fund
certain construction costs in lieu of the lump—sum payment due
March 1,1989.The contract price remains firm and the Town
would not be placed in jeopardy with regard to security.
Following discussion,the Committee recommends Town Attorney
White develop a proposal for review by the Committee.The
Committee stressed that at this time,the recommendation was not
intended to be an endorsement of extending payments.
WATER TREATMENT PLANTS CORROSION CONTROL AND PREDESIGN WORK -
DISCUSSION.
Public Works Director Widmer reported he had received proposals
from the four consultants recommended July 14,1988.Three
proposals were similar in nature;however,one proposal advised
the technology and method to solve corrosivity was readily
available.Fort Collins conducted a similar study in 1981-82 and
they are now in the process of modifying their treatment plants
accordingly.In a meeting with staff from Fort Collins,Town
staff toured a water treatment plant and they have suggested the
approach be revised on this project.Staff is proposing the
pilot plant work be diminished,with the primary focus to be
aimed at design work to ascertain what can be done to cure the
corrosivity in the water.RFPs will be prepared and each firm
0 0
RECORD OF PROCEEDINGS
Water Committee -August 11,1988 -Page two
will be required to list their experience.Staff appreciated the
“open approach”proposal submitted by one firm;however,Director
Widmer confirmed this firm would not receive preferential
treatment.The Committee recommends approval of the approach,
and authorized staff to proceed.The Committee will be advised
of the interview selection status in a work session.
RURAL WATER APPLICATIONS.
Jasim &Linda Al-Rijab.The Committee reviewed a Rural Water
Application submitted by Jasim and Linda Al-Rijab for property
located at 1885 Spur 66.The property is within the Northern
Colorado Water Conservancy District and presents no problem to
the Water Department.The Committee recommends approval of the
application.
Muriel L.MacGregor Charitable Trust.MacGregor Ranch also
submitted an application.The property is within the District
and can he served by the Town.The Committee recommends approval
of the application.
The Committee also recommends staff contact Town Attorney White
with regard to allowing staff to approve Rural Water Applications
in lieu of the Committee;the Committee could review “appeals.”
1988 WATER SYSTEM IMPROVEMENTS -REQUEST AUTHORIZATION TO SOLICIT
BIDS.
Director Widmer reported the drawings have been completed for the
following 1988 Water System Improvements:Pressure Reducing
Station,Stanley Avenue 12”line,Cleave Street 12”line and an
8”line on Lexington Lane.Design has not been completed for the
12”line on Moccasin Saddle.If bids are taken as soon as
possible,the improvements could be completed by late November.
The Committee recommends Director Widmer be authorized to request
bids for the 1988 Water System Improvements.
CRYSTAL WATER COMPANY -REQUEST FOR EMERGENCY WATER CONNECTION.
The Committee reviewed a letter dated August 10,1988 submitted
by N.E.Kitchen/Crystal Water Company.An emergency supply of
treated water for an undetermined period of time is being
requested until the storage tank is supplied with sufficient
water to supply usage.Water Superintendent Goehring has
reviewed this request and reported a temporary 2”meter could be
installed as soon as Friday,August 12th.Installation would
include a back—flow preventer.The Town would charge the bulk
rate of $5.50/1,000 gallons of water.Both the Health Department
and Water Superintendent Goehring would inspect the system.
Staff anticipates the period of time to be approximately 2
months.The Committee recommends approval of the emergency
request,performing the installation as soon as possible.As the
water shortage affects Carriage Hills fire protection,the
Committee also recommends Water Superintendent Goehring advise
Fire Chief Rumley.
FAWN LANE WATER LINE CONSTRUCTION -AUTHORIZATION TO PROCEED.
Director Widmer reported Fawn Lane was included in the 1988
Street Improvement Project for new street paving.Staff has
determined the water line is in need of replacement which should
be completed prior to actual paving of the street.All materials
are on hand,and adequate funds are available in the budget for
this project.The new water line will increase fire protection
for this area.The Committee recommends Director Widmer be
authorized to install a new water line on Fawn Lane.
0 0
BRADFORD PUBLISHING .RECORD OF PROCEEDINGS
Water Committee -August 11,1988 -Page three
Trustee Aldrich complimented the Department in coordinating the
street overlaying project with public entities prior to actual
placement of the asphalt.
REPORTS.
The Committee reviewed the Citizen Service Response,Water
Billed,Water Revenue,and Accountable Water (82%of all treated
water was accounted for)Reports for the month of July.
It is anticipated the Fall River Water Treatment Plant may begin
operation in October.
The Committee also reviewed the “Forecasts compared to Actual”
Report prepared by Finance Officer Vavra.
As the remaining agenda item would contain discussion concerning
negotiations with CRYSTAL WATER COMPANY,consensus of all Trust
ees in attendance was to enter executive session.
Chairman Dickinson adjourned the meeting to executive session at
2:43 P.M.
//
ickie O’Connor,Town Clerk
1’ROVE Di