HomeMy WebLinkAboutMINUTES Light and Power Committee 1987-08-060 0
RECORD OF PROCEEDINGS
/Light and Power Committee
August 6,1987
Committee:Chairman Hix,Trustees Brown and Habecker
Attending:All
Also Attending:Mayor Dannels,Town Administrator Hill,Light
and Power Dekker,Finance Officer Vavra,
Clerk O’Connor
Absent:None
MANDATORY DEMAND CONTROLLER INSTALLATION -DISCUSSION:
Pursuant to the Committee’s recommendation of June 4,1987,Town Attorney
White submitted a legal opinion concerning mandatory installation of demand
controllers.In summary,the opinion stated the Town could require such an
installation;however,the Town would become involved in controlling
equipment beyond the electric meter.Following discussion,the Committee
recommends (1)the Town continue existing policy of not requiring a demand
controller to be installed beyond residential demand meters and (2)a
paragraph be incorporated into the Application for Service alerting all
potential electric—heat customers to consider installing a demand control
ler.
CUSTOMER REQUEST FOR RELIEF IN REALIGNMENT OF ELECTRIC LINE:
Trustee Habecker,informally representing Rob Erwin,1213 Chasm Road,
stated Mr.Erwin has constructed an addition to his house.The addition
has created a clearation violation for telephone cable and power lines.
Director Dekker presented three (3)alternatives that could correct the
situation:(1)innerset a pole and raise the electric wires and cable at a
cost of $552.00;(2)install a new pole and raise the electric wires and
cable —$797.75;or (3)install a new pole and realign the entire line —
$1,500.00.This particular line loops to Glen Haven;adequate clearance
(10’)existed prior to the addition.Following existing policy,if a
customer causes the Town to remove and/or revise existing facilities,the
customer is responsible for all costs incurred.Regardless of what alter
nate,if any,the customer requests,the telephone company will relocate
their cable and invoice Mr.Erwin.Following discussion,the Committee
recommends adhering to existing policy whereby the customer will pay for
any change in electric facilities.
PUBLIC POWER WEEK -DISCUSSION:
The Committee reviewed a letter dated July 28,1987 submitted by Joe Exum,
President/American Public Power Association.Public Power Week has been
scheduled for October 4 -10;all community-owned electric systems through
out the country have been urged to participate.Several materials have
been offered which include signs and decals,t—shirts,balloons,etc.
Director Dekker advised the Department will prepare a program and advise.
The Committee recommends (1)approval of Public Power Week for Estes Park
October 4 -10;(2)adoption of a Public Power Week Resolution;and (3)an
expenditure not—to—exceed $1,000.
CITIZEN REQUEST FOR RELIEF IN TRAFFIC ACCIDENT INVOLVING STREET LIGHT -
DISCUSSION:
Director Dekker advised an accident,involving Watson Freight Line,oc
curred May 18,1987 when Watson’s trailer struck a street light located at
the intersection of Elkhorn Avenue and Wiest Drive.The Town’s cost to
repair and reset the light is $125.00;Mr.Watson is appealing the charge
because,in his opinion,several lights have been placed too close to the
street making it difficult to avoid damaging them.In reviewing the
“traffic accident report”,the Committee observed if vehicles remain on the
roadway damage to street lights should not occur.Discussion followed with
0 0
RECORD OF PROCEEDINGS
Light and Power Committee -August 6,1987 -Page two
the Committee recommending Mr.Watson be advised the invoice in the amount
of $125.00 is due and payable.
EPURA REQUEST TO RELOCATE STREET LIGHTS -DISCUSSION:
Pursuant to EPURA’s request to relocate four (4)street lights,Director
Dekker submitted a cost estimate of $250.00/each for the following lo
cations:
1.Southeast corner of Wiest Drive and Elkhorn Avenue (move back
18”)
2.Southwest corner of Wiest Drive and Elkhorn Avenue (move one light
back 12”).
3.Southeast corner intersection of Moraine and Elkhorn Avenues (move
two lights).
Stating the lights were placed as designed,the Committee recommends the
Light and Power Department perform the work at EPURA’s expense of approxi
mately $1,000.00.
POWER LINE FROM CHELEY CAMP TO BALDPATE -DISCUSSION:
Director Dekker submitted four (4)alternative routes to rebuild the power
line from Cheley Camp to Baldpate.The line was constructed by Public
Service Company approximately 50 years ago and it is the main line serving
Allenspark.The line must be replaced as soon as possible.Director
Dekker advised discussion has taken place with the developers of the
Baldpate property.A mutually-beneficial arrangement could take place if
the line were relocated to pass through the proposed development.If the
developers wish a portion of the line be placed underground,the Committee
feels the developers should pay the difference in costs.Should nego
tiation be successful,the Town could relocate the line which would allow
access by vehicle.The range of cost estimates is between $60,000 and
$96,000.FEMA funds will pay for a portion of the project.Discussion
followed,with the Committee recommending Director Dekker be authorized to
negotiate construction options and fees with the developers,returning to
the Committee with additional information.
HAZARDOUS WASTE DUMPING SITE -DISCUSSION:
Director Dekker advised a claim has been filed by EPA against Rose Chemi
cal.In 1982,the Town shipped certain capacitors to the Rose Chemical
site for disposal.The Town has been identified as a producer of toxic
waste and is,therefore,one of several entities responsible for clean—up
of the site.The Department shipped a very small amount of products and
waste to Rose Chemical and the responsibility for polluting the site will
be dispersed among all contributing entities.In a letter dated July 30,
1987,Town Attorney White stated that due to the involvement of numerous
insurance carriers for the Town,legal costs are being incurred concerning
inquiries for information.Following discussion,the Committee recommends
Town Attorney White continue to monitor this issue on behalf of the Town,
answering any direct inquiries for information that may arise.
PCB TESTING AND CONTROL PROCEDURES -REVIEW:
The Committee reviewed PCB testing and control procedures currently being
followed by the Light and Power Department.Oil samples from various units
are being submitted to National Electric Company for analysis.Following
testing,National Electric provides a PCB analysis to the Town.50 samples
were submitted in July;2 samples were found to be contaminated.Contam
inated units are then identified as such with a “yellow”label and properly
disposed.A “blue”label is attached to all units found to be free of PCB
agents.All testing records are being maintained by the Department.
0 0
RECORD OF PROCEEDINGS
Light and Power Committee -August 6,1987 -Page three
SAFETY AND HEALTH PERFORMANCE AWARD -DISCUSSION:
In a letter dated July 28,1987,the National Safety Council commended the
Light and Power Department in preventing accidents and occupational ill
nesses during 1986.Consideration is being given to the possibility of
awarding an informal “incentive award”to Department employees.
“CPR”INSTRUCTION -DISCUSSION:
Director Dekker advised a “CPR”course is available to all Town employees
and officials at a cost of approximately $5.00/person.All fees would be
paid by the Town;course instructors are Jo Hutter and Steve Smee.The
8—hour course will be offered on two separate days.Anyone desiring to
participate in the course is asked to advise Bob Dekker,Light and Power
Department,586—5331,extension 202.
RMEL CONFERENCE -SEPTEMBER 13 -15,1987:
The annual Rocky Mountain Electrical League (RMEL)Conference will be held
September 13 -15,1987 in Durango.Those Trustees planning on attending
the Conference are asked to advise Clerk O’Connor as soon as possible.
TRAPPER MINE AND CRAIG POWER PLANT TOUR:
Platte River Power Authority has invited all member officials to attend an
all day tour of the Trapper Mine and Craig Power Plant either September 2
or 10,1987.
REPORTS:
Finance Officer Vavra reported one check in the amount of $46,000 has been
received from FEMA for flood-related projects.Officer Vavra will obtain
information from FEMA regarding possible stipulations regulating work to be
performed by Town crews vs.private contractors.
An agreement has been reached with the National Park Service concerning the
Cascade Dam Project.The Town has requested proposals for construction of
the diversion structure and penstock contingent upon the Town receiving a
“404 Permit.”North American Hydro is still interesting in leasing the
Town’s property for a generating plant.
No further action has taken place on the Olympus Dam Project.
Thaine J.Michie has been selected as the General Manager of Platte River
Power Authority.Mr.Michie was promoted from within the organization.
Year-to-Date kilowatt hour sales are up 7.4%;revenue is up 6.8%.
The Delinquent Account Report for July indicated 63 telephone calls were
made,16 notes placed at the customer’s residence and 6 accounts were
disconnected.Discussion followed concerning alternative methods that
could be implemented to advise customers of their delinquent status.
Finance Officer Vavra will research information regarding the habitual
delinquent customer for presentation at the next Committee meeting.
Lineman Joe Beaman has submitted his resignation and will be relocating to
Indiana.
There being no further business,the meeting adjourned.
Vickie O’Connor,Town Clerk
1\UG 11198?