Loading...
HomeMy WebLinkAboutMINUTES Light and Power Committee 1995-10-19C RECORD OF PROCEEDINGS Light and Power Committee October 19,1995 Committee:Chairman Dekker,Trustees Miller and Pauley Attending:All Also Attending:Town Administrator Klaphake,Light &Power Director Matzke,Assistant Town Administrator Widmer,Deputy Clerk Kuehi Absent:None Chairman Dekker called the meeting to order at 9:00 a.m. LONG RANGE SYSTEM PLAN --AUTHORIZATION TO EXECUTE CONTRACT FOR CONSULTING SERVICES Director Matzke requested proposals from 3 consulting engineering firms for development of a long range system plan for Estes Park’s electric system.The scope of services included an electrical model of the existing system,evaluation of age of major facilities and need for replacement,a five-year capital improvement plan, funding requirements,and a system design for the year 2005.The names of the firms and the estimate to complete the scope of services is as follows: Consultant Cost Estimate Additional Mapping P..W.Beck $25,000 to $30,000 Miner &Miner $19,500 $4,100 Electrical Systems $14,000 -$4,500 Two consultants submitted estimates to develop digital system maps. Electrical Systems Consultants also submitted an estimate of $6,000 to perform a coordination study in conjunction with the long-range system plan.A rate analysis and revenue impact assessment may be required in addition to this study.Light &Power Department Staff have reviewed the proposal with each consultant and are comfortable with their capabilities to perform the study.All three firms have offices in the state.Director Matzke noted that the Department has had previous experience with both R.W.Beck and Miner &Miner. Electrical System Consultants has performed work for PRPA and all four member cities,and sample reports from these other municipalities were available for review.The 1995 Light &Power Budget has $25,000 available for this study.Administrator Klaphake noted that low bid should not be the dominant consideration for this type of study.The Committee recommends that Electrical Systems Consultants from Fort Collins be engaged to perform the Long-Range System Plan for an estimated cost of $24,500,including the proposed additional mapping work and a coordination study,subject to reference analysis.Director Matzke noted the Planning Engineer who will perform the work is also the Vice President of Electrical System Consultants.When all materials are supplied to Electrical Systems Consultants,the project is expected to take 120 days to complete.Chairman Dekker questioned whether this study will complement the Comprehensive Plan.Director Matzke will verify the compatibility of this study with the GIS system. 0 0 RECORD OF PROCEEDINGS Light &Power Committee,October 19,1995 -Page 2 PLATTE RIVER POWER AUTHORITY Proposed Wholesale Rate Change:Director Matzke has been attending meetings with PRPA directed at studying a proposed rate schedule that will include time-of-day charge to consist of a base load, intermediate load,and peak load with transmission cost separate from generation cost.Recommendations are expected by April 1996. Report:Assistant Administrator Widmer reviewed Platte River’s budget,along with activities during recent board meetings and a board retreat. REPORTS Director Matzke presented various graphs and the Financial Reports for September. Project Updates:The Fish Creek Street Lights should be installed within the month.The Park Service Rate Study is proceeding.The new bucket truck is in service and will be modified as a result of a lineman accident. There being no further business,Chairman Dekker adjourned the meeting at 10:15 a.m. Tina Kuehl,Deputy Town Clerk F 0C1241995 I -,5ihz.. ? TC....c_.-J..