HomeMy WebLinkAboutORDINANCE 30-78ORDINANCE NO.30 -78
AN ORDINANCE AMENDING SECTIONS 13.12.020 C,
13.12.030 C,13.12.040 C,13.12.050 C and D,
13.12.060 C and D,13.12.070 B and D,
13.12.080 C and D,AND 13.12.090 C OF THE
MUNICIPAL CODE OF THE TOWN OF ESTES PARK,
COLORADO,RELATING TO LIGHT AND POWER RATE
SCHEDULES CONTAINING CHARGES FOR THE SERVICE
OF ELECTRIC POWER AND ENERGY BY THE LIGHT
AND POWER DEPARTMENT OF THE TOWN OF ESTES
PARK,COLORADO.
BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE TOWN
OF ESTES PARK,COLORADO:
Section 1.Sections 13.12.020 C,13.12.030 C,
13.12.040 C,13.12.050 C and D,13.12.060 C and D,13.12.070
B and D,13.12.080 C and D,and 13.12.090 C of the Municipal
Code of the Town of Estes Park,Colorado are amended to read
as follows:
13.12.020 C.Rate:
The first 30 KWH per month $2.74
The next 20 KWH per month,
per KWH at .09096
The next 50 KWH per month,
per KWH at .06396
The next 200 KWH per month,
per KWH at .03896
All additional KWH used per
month,per KWH at .03316
Minimum —Net minimum charge
per meter per month $2.74
13.12.030 C.Rate:
The first 30 KWH per month $2.74
The next 20 KWH per month,
per KWH at .09096
The next 50 KWH per month,
per KWH at .06496
The next 150 KWH per month,
per KWH at .03896
The next 250 KWH per month,
per KWH at .02996
.0 0
All additional KWH used per
month,per KWH at .03316
Minimum —Net minimum charge
per meter per month $2.74
13.12.040 C.Rate:
The first 100 KWH per month $7.91
The next 150 KWH per month,
per KWH at .03996
The excess KWH per month,
per KWH at .02996
Minimum per month $7.91
13.12.050 C.Rate:For all energy used between meter
readings taken approximately between May 20th and September 20th,
the rate shall be:
First 22 KWH used per month $2.85
The next 78 KWH used per
month,per KWH at .10696
The next 100 KWH used per
month,per KWH at .08196
The next 800 KWH used per
month,per KWH at .07296
The next 1500 KWH used per
month,per KWH at .05696
The next 2500 KWH used per
month,per KWH at .04496
All additional KWH used per
month,per KWH at .03526
For all energy used between meter readings taken approximately
between September 20th and May 20th,the rate shall be:
First 23 KWH used per month $2.85
The next 77 KWH used per
month,per KWH at .09596
The next 100 KWH used per
month,per KWH at .05496
The next 800 KWH used per
month,per KWH at .04996
The next 2000 KWH used per
month,per KWH at .04196
—2—
0
All additional KWH used per
month,per KWH at .03526
D.Minimum:
Net minimum charge per meter,
per month $2.85
13.12.060 C.Rate:
All KWH used per month,
per KWH at $.03346
D.Minimum:
Net minimum charge
per month $2.84
13.12.070 B Rate per month:
First 20 KWH per KW of billing
demand,but not less than 200
KWH,per KWH $.07696
Next 40 KWH per KW of billing
demand,but not less than
400 KWH,per KWH .06396
Next 100 KWH per KW of billing
demand,but not less than
100 KWH,per KWH .05196
All additional KWH,per KWH .04536
D.Minimum:
The following minimum rates are subject to the special
provisions of the extention policy:
The monthly minimum per KW
of billing demand $1.27
But not less than $12.70
All rates and contracts shall be subject to all special
provisions of the extension policy.
All contracts under this schedule shall be for a mini
mum period of three months and thereafter shall be terminated,
where service is no longer required,on thirty (30)days notice.
13.12.080 C.Rate:
The first 100 KWH per month
per KW of demand,but not
less than 10,000 KWH per
month,per KWH at $.05096
The next 100 KWH per month
per KW of demand,but not
less than 10,000 KWH per
month,per KWH at .03896
—3—
0
The excess KWH per month,
per KWH at .02352
B.Minimum:The minimum charge per meter per
month shall not be less than $296.00 per month nor less than
$1.27 per KW of billing demand,whichever shall be the
greater.
13.12.090 C Rate:(net)
Metered Service
All KWH used per month,per KWH $.03496
Section 2.Except as herein specifically amended,
Title 13 and all ordinances or parts of ordinances of the Muni
cipal Code of the Town of Estes Park relative to the Light and
Power Department shall be and hereby are designated to
remain in full force and effect and are hereby ratified,
confirmed and approved.
Section 3.The Board of Trustees hereby authorizes
the Town Clerk and other officials of the Town to file with the
Public Utilities Commission of the State of Colorado such docu
ments and to take such action,including the employment of per
sonnel and the payment therefor,as may be necessary to obtain
the approval of said Public Utilities Commission as may be re
quired under applicable law for changes in rates for electric
service,but subject only to such jurisdiction as may
exist in the Public Utilities Commission relative to electric
service provided outside the municipal boundaries of the
Town.
Section 4.The Board of Trustees of the Town of
Estes Park,Colorado,herewith finds,determines and desig
nates that this Ordinance is necessary for the immediate
preservation of the public peace,health and safety,for
reliable electric service affects the public peace,health and
safety;and the changes in electric rates authorized herein
are necessary to maintain reliable electric service and preserve
—4—
0
the financial and operating integrity of the municipal
electric system;and whereas,in the opinion of the Board
of Trustees,an emergency exists,this Ordinance shall take
effect and be in force as of the first electric billing
period commencing after January 9,1979,or as of
the first billing period commencing after the final approval
of the rates set forth in this Ordinance relative to the
service provided outside the municipal boundaries of the
Town is obtained from the Public Utilities Commission of the
State of Colorado,whichever date is the later to occur,and
after its final passage,adoption and the signature of the
Mayor.
PASSED BY THE BOARD OF TRUSTEES THIS 12TH DAY OF
DECEMBER,1978,AND SIGNED THIS 12TH DAY OF DECEMBER,1978.
TOWN OF E’ES PARK,COLORADO
I HEREBY CERTIFY AND ATTEST THAT THE ABOVE ORDINANCE
WAS INTRODUCED AND READ AT A REGULAR MEETING OF THE BOARD OF
TRUSTEES ON THE /Z DAY OF DECEMBER,1978,AND PUBLISHED
IN A NEWSPAPER OF GENERAL CIRCULATION IN THE TOWN OF ESTES
PARK,COLORADO,ON THE DAY OF DECEMBER,1978,ALL AS
REQUIRED BY THE STATUTES OF THE STATE OF COLORADO.
:
1(LU //tLA_1
TOWN CLERK
—5—