HomeMy WebLinkAboutORDINANCE 27-790
ORDINANCE NO.
AN ORDINANCE AMENDING SECTIONS 13.08.050 B,
13.12.020 C,13.12.030 C,13.12.040 C,
13.12.050 C and D,13.12.060 C and ID,
13.12.070 B and ID,13.12.080 C and ID,
AND 13.12.090 C OF THE MUNICIPAL CODE OF
THE TOtTN OF ESTES PARK,COLORADO,RELATING
TO INTEREST PAID ON DEPOSITS FOR ELECTRIC
SERVICE AND TO LIGHT AND POWER RATE SCHEDULES
CONTAINING CHARGES FOR THE SERVICE OF ELECTRIC
POWER AND ENERGY BY THE LIGHT AND POWER DEPART
MENT OF THE TOWN OF ESTES PARK,COLORADO.
BE IT ORDAINED BY THE BOARD OF TRUSTEES OF THE TOWN
OF ESTES PARK,COLORADO:
Section 1.Section 13.08.050 B of the Municipal
Code of the Town of Estes Park,Colorado is amended to read
as follows:
13.08.050 B.Service Deposits:The department may,
at any time,require that the user maintain a deposit
with the department of a sum not exceeding an estimated
ninety days’bill or a satisfactory guarantee of the
payment be made for service for a like period.Such
deposits will not be considered as advance payment for
service bills and will be applied as credits to users’
accounts only after service has been discontinued.The
deposit may be in addition to any advance,contribution,
or guarantee in connection with construction of any
lines or facilities as provided for in the department’s
line extension policies.In the event any person is in
arrears to the department for electric service,satisfactory
arrangements must be made for paying for the old accounts
in full before any application for new service will be
approved.
The department may return deposits at any time and
will return such deposits upon discontinuance of the
service after withholding therefrom payment for unpaid
charges or bills for service.Deposits will be returned
only after the department has determined that sufficient
evidence exists that the user is entitled to the return
of the deposit.
The interest rate applied to deposits,the calcula
tion of interest and the distribution of interest on
deposits shall be made in accordance with the applicable
rule governing customer deposits as promulgated by the
Public Utilities Commission of the State of Colorado,
as may be amendedor modified from time to time.The
superintendent of the department is hereby authorized
to file the required tariffs with the Public Utilities
Commission,as required under the applicable Commission
rules and regulations,setting forth the interest rate
to be applied to deposits,the calculation of interest
and the distribution of interest earned on customer
deposits.
0 0
Section 2.Sections 13.12.020 C,13.12.030 C,
13.12.040 C,13.12.050 C and D,13.12.060 C and D,13.12.070
B and ID,13.12.080 C and ID,and 13.12.090 C of the Municipal
Code of the Town of Estes Park,Colorado are amended to read
as follows:
13.12.020 C.Rate:
The first 30 KWH per month $2.76
The next 20 KWH per month,
per KWH at .09147
The next 50 KWH per month,
per KWH at .06447
The next 200 KWH per month,
per KWH at .03947
All additional KWH used
per month,per KWH at .03367
Minimum -Net minimum charge
per meter per month $2.76
13.12.030 C.Rate:
The first 30 KWH per month $2.76
The next 20 KWH per month,
per KWH at .09147
The next 50 KWH per month,
per KWH at .06547
The next 150 KWH per month,
per KWH at .03947
The next 250 KWH per month,
per KWH at .03047
All additional KWH used per
month,per KWH at .03367
Minimum -Net minimum charge
per meter per month $2.76
13.12.040 C.Rate:
The first 100 KWH per month $7.96
The next 150 KWH per month,
per KWH at .04047
The excess KWH per month,
per KWH at .03047
Minimum per month $7.96
—2—
0
13.12.050 C.Rate:For all energy used between meter
readings taken approximately between 1ay 20th and September 20th,
the rate shall be:
First 22 KWH used per month $2.86
The next 78 KWH used per
month,per KWH at .10747
The next 100 KWH used per
month,per KWH at .08247
The next 800 KWH used per
month,per KWH at .07347
The next 1500 KWH used per
month,per KWH at .05747
The next 2500 KWH used per
month,per KWH at .04547
All additional KWH used per
month,per KWH at .03577
For all energy used between meter readings taken approximately
between September 20th and May 20th,the rate shall be:
First 23 KWH used per month $2.86
The next 77 KWH used per
month,per KWH at .09647
The next 100 KWH used per
month,per KWH at .05547
The next 800 KWH used per
month,per KWH at .05047
The next 2000 KWH used per
month,per KWH at .04247
All additional KWH used per
month,per KWH at .03577
D.Minimum:
Net minimum charge per meter,
per month $2.86
13.12.060 C.Rate:
All KWH used per month,
per KWH at .03397
D.Minimum:
Net minimum charge
per month $2.88
—3—
0 0
Section 3.Except as herein specifically amended,
Title 13 and all ordinances or parts of ordinances of the Muni
cipal Code of the Town of Estes Park relative to the Light and
Power Department shall be and hereby are designated to
remain in full force and effect and are hereby ratified,
confirmed and approved.
Section 4.The Board of Trustees hereby authorizes
the Town Clerk and other officials of the Town to file with the
Public Utilities Commission of the State of Colorado such docu
ments and to take such action,including the employment of per
sonnel and the payment therefor,as maybe necessary to obtain
the approval of said Public Utilities Commission as may be re
quired under applicable law for changes in rates for electric
service,but subject only to such jurisdiction as may
exist in the Public Utilities Commission relative to electric
service provided outside the municipal boundaries of the
Town.
Section 5.The Board of Trustees of the Town of
Estes Park,Colorado,herewith finds,determines and desig
nates that this Ordinance is necessar for the immediate
preservation of the public peace,health and safety,for
reliable electric service affects the public peace,health and
safety;and the changes in electric rates authorized herein
are necessary to maintain reliable electric service and preserve
the financial and operating integrity of the municipal
electric system;and whereas,in the opinion of the Board
of Trustees,an emergency exists,this Ordinance shall take
effect and be in force as of the first electric billing
period commencing after January 7,1980,or as of
the first billing period commencing after the final approval
of the rates set forth in this Ordinance relative to the
service provided outside the municipal boundaries of the
—5—
C
Town is obtained from the Public Utilities Commission of the
State of Colorado,whichever date is the later to occur,and
after its final passage,adoption and the signature of the
Mayor.
PASSED BY THE BOARD OF TRUSTEES THIS 3rd DAY OF
DECEMBER,1979,AND SIGNED THIS 3rdDAY OF DECEMBER,1979.
-/MAYOR
TOWN OF ESTES PARK,COLORADO
I HEREBY CERTIFY AND ATTEST THAT THE ABOVE ORDINANCE
WAS INTRODUCED AND READ AT A RECONVENED REGULAR MEETING OF
THE BOARD OF TRUSTEES ON THE 3rd DAY OF DECEMBER,1979,AND
PUBLISHED IN A NEWSPAPER OF GENERAL CIRCULATION IN THE TOWN
OF ESTES PARK,COLORADO,ON THE 5th DAY OF DECEMBER,1979,
ALL AS REQUIRED BY THE STATUTES OF THE STATE OF COLORADO.
TOWN CLERK
—6—