HomeMy WebLinkAboutPACKET Town Board Study Session 2020-01-14
January 14, 2020
5:45 p.m. – 6:40 p.m.
Rooms 202/203
5:30 p.m. - Dinner
5:45 p.m. Downtown Estes Loop Quarterly Update.
(Director Muhonen)
6:35 p.m. Trustee & Administrator Comments & Questions.
6:40 p.m. Future Study Session Agenda Items.
(Board Discussion)
6:45 p.m. Adjourn for Town Board Meeting.
Informal discussion among Trustees concerning agenda items or other Town matters may occur before this
meeting at approximately 5:15 p.m.
AGENDA
TOWN BOARD
STUDY SESSION
1
2
PUBLIC WORKS Report
To: Honorable Mayor Jirsa
Board of Trustees
Through: Town Administrator Machalek
From: Greg Muhonen, PE, Public Works Director
Project Technical Advisory Committee (TAC)
Date: January 14, 2020
RE: Quarterly Update on Downtown Estes Loop Project (DEL)
Objective:
Update the Town Board on the activities that have taken place on the Downtown Estes
Loop Project (DEL) since the September 2019 Town Board Study Session.
Present Situation:
Right of Way: Purchase of four parcels is complete. Agreements for Possession
& Use are in place for three parcels, and the property owners have been paid the
appraised value for their parcels. The district court will determine if additional
compensation is warranted if ongoing negotiations stall. The owners of the
Donut Haus have posted on social media that they have reopened in a leased
facility on Moraine Avenue.
Budget: Current cost estimates forecast an additional $1.3 million may be
needed to complete the design, right of way acquisitions, easement acquisitions,
and building demolition in 2020.
Hydraulics: Selection of a less-expensive single-span bridge has been confirmed
at the Ivy Street crossing over the Big Thompson River. The Project team will
need to submit a Conditional Letter of Map Revision (CLOMR) to FEMA in order
to incorporate the associated changes into the new floodplain maps.
Scope Revision: As directed by the Town Board at the May 14 meeting, the
Town hired AECOM to prepare and submit an application on July 19 for a federal
BUILD grant that would fund increased project scope to include the Riverside
and Rockwell Bridges and channel widening downstream to US36. The US
Department of Transportation notified us on November 12 that this grant
application was not funded. This Phase 2 work is no longer under consideration
for incorporation into the Phase 1 project.
Schedule: The project schedule anticipates completion of the construction
documents in the fall of 2020. Right of way and easement acquisitions are
expected to extend into 2020 as well. Project construction is expected to begin in
the fall of 2021, while demolition of acquired buildings is expected to occur in the
3
first quarter of 2020. The Town has commenced water system upgrades under
Moraine Ave, Rockwell Street, the post office parking lot, and W Riverside Ave. A
number of interim conditions have been left in place based on reliance that the
DEL project will perform permanent system connections and final surface repairs.
Proposal:
The TAC proposes to continue the design and right-of-way acquisition efforts in 2020
and bid the construction work in early 2021. A future amendment to the Memorandum of
Agreement is requested from Central Federal Lands Highway Division (CFLHD) in order
to complete the preliminary engineering in 2020 instead of delaying the project until
additional FLAP funding or reallocation of construction dollars (through project scope
reductions) could be negotiated in a future funding year.
Advantages:
The project benefits are numerous and include relief to the Town’s downtown traffic
congestion problems, improved downtown mobility for bicyclists, reduction in downtown
flood risk from the Big Thompson River, improved fire protection, and closure to
property owner uncertainty surrounding the DEL.
Disadvantages:
Some community members do not support the partner agencies building the DEL.
Action Recommended:
n/a
Finance/Resource Impact:
The 2014 Memorandum of Agreement between the Town, CDOT, CFLHD, and RMNP
estimated this project would cost $17.2 million with construction occurring in 2016. In
2019 CFLHD dedicated an additional $2 million of Federal Lands Access Program
(FLAP) funds to cover increased right of way acquisition costs. The Town remains
obligated to pay a local match of $4.2 million (CDOT devolution funds) for the $19.2
million Phase 1 project. The Town has spent $3,383,530 to-date. A total of $5.98 million
has been spent on the project through 2019. Conservative cost projections regarding
structure demolition and potential legal costs associated with the remaining parcel and
easement acquisitions imply an additional $1.3 million may be needed to complete the
design and parcel acquisitions in 2020. This not available from the FLAP program in
2020. CDOT has committed to provide an additional $580k to cover the costs of the
ROW consultant effort, contingent upon the Town and CFLHD providing additional
funds as outlined in the budget summary slide. CFL is asking the Town to consider
contributing $560,843 in 2020 to allow this preliminary engineering work to continue in
2020. For reference, this amount is the estimated cost of the W Elkhorn rehabilitation
work proposed by the project. Without the DEL, the Town Water Division will have to
perform additional permanent work estimated to cost several hundred thousand dollars.
Level of Public Interest
The known level of public interest in this item is high.
Attachments:
Preliminary copy of consultant presentation slides for the Phase 1 project
4
Draft Presentation subject to change.
Downtown Estes Loop Project
Estes Park Town Board Study
Session
January 14, 2020
Draft Presentation subject to change.
Today’s Agenda
• Project Schedule
• Progress Update
•Right of Way
•Design
•Budget
• Next Steps
• Q&A on Phase 1
5
Draft Presentation subject to change.
Project Scope – Phase 1
• Phase 1:
– Reconstruction and realignment of
Riverside Drive
– Reconstruction of the Ivy Street Bridge
– New and Coordinated traffic signals with
Riverwalk
– Associated transportation improvements
along Elkhorn and Moraine
– New on street bike lane on Moraine and
Riverside
– Continuous sidewalks along entire Loop
– Channel Improvements between Ivy St
and Rockwell St
– Wayfinding signs, parklands
• Does not include:
– Rockwell and Riverside Bridges
– Relocation of Public Restroom
– Downstream Floodplain Improvements
Draft Presentation subject to change.
Project Schedule
6
Draft Presentation subject to change.
Right-of-Way Acquisitions Process
• CDOT is the lead agency for Right of Way (ROW) Acquisition on
the Project.
• Process follows Uniform Relocation Assistance and Real
Property Acquisition Policies Act of 1970 (Uniform Act).
•CDOT has purchased 4
of 7 properties, and has
possession agreements
with the remaining 3
owners.
• CDOT is assisting property
owners and tenants who require
Relocation. 2 residential owners,
2 tenants and 3 businesses
account for remaining relocations.
X
X
X
XXX
XXX
CDOT owned properties
Draft Presentation subject to change.
Summary of Right-of-Way
Acquisition Process
7
Draft Presentation subject to change.
General Condemnation Process
Draft Presentation subject to change.
Status of Right-of-Way
Acquisitions & Relocations
• CDOT is now in title to 4 of the 7 full property acquisitions.
• Possession and Use Agreements are in place for the remaining 3
properties.
- Negotiations are ongoing for settlement.
- Relocation of owners and tenants is continuing.
• CDOT will proceed with the second portion of the Right-of-Way
acquisitions once plans have been received and authorized.
- Additional 8 fee acquisitions, 1 permanent easement, 20 temporary
easements are estimated in the second portion of acquisition.
- No additional relocations are currently identified.
8
Draft Presentation subject to change.
Update on Properties in
Condemnation
• If settlements cannot be reached with the owners of the 3 properties
on Possession and Use Agreements within the prescribed time,
CDOT will proceed with condemnation for value.
• Each of the 3 properties on Possession and Use Agreements has
been authorized for condemnation.
Draft Presentation subject to change.
Removal of Structures
• Required asbestos and lead-based paint testing
- Has been performed on the 7 advance parcels and the Town of
Estes Park duplex. Five of the eight sites will require removal of
asbestos containing materials. All eight sites will require removal
of hazmat materials including paint containers, solvents, florescent
light bulbs and cleaning supplies.
• Structure removal will occur after mitigation, within the off-season,
between January and March 2020.
9
Draft Presentation subject to change.
Budget Update
Draft Presentation subject to change.
Design Update
CFLHD Lead Agency for Design
Milestone: Refinement of 70% Design Plans
Recent Activities Agencies Consulted
Final ROW Plans for Partial ROW Acquisitions
•Second phase of ROW plans for 8 fee acquisitions, 1 permanent
easement, 20 temporary easements
Town of Estes Park
CDOT
Roundabout Refinements
•Geometric refinements to roundabout to improve efficiency and
traffic flow
Town of Estes Park
CDOT
FHWA Resource Center
Utility Design & Relocation
•Continued coordination with utility companies to find efficiencies
and ensure utilities are installed in advance of project, wherever
possible, to minimize impacts to the public
Town of Estes Park
CDOT
Sanitation District
Century Link and Xcel Energy
12 10
Draft Presentation subject to change.
Next Steps
•Upcoming Milestone: 95% submittal of plans in Spring 2020
– Ongoing Design Refinements
– Continue Right of Way Acquisition (Full and Partial)
• Develop schedule for Building Removals, Winter/Spring 2020
– Finalize Utility Relocation Plans and Schedule
• Initial relocations in 2020
• Monthly Technical Advisory Committee (TAC) Meetings
– Members include representatives from CFLHD, CDOT, Estes Park
• Town Board Quarterly Updates
– next presentation on March 10, 2020
• BUILD Grant Unsuccessful – Evaluate Project Scope and Budget
Draft Presentation subject to change.
Questions and Answers
11
12
January 28, 2020
•Vacation Home Regulations in
PUDs
February 11, 2020
•Facilities Master Plan
•2020 Transit Routes Proposal
February 25, 2020
•Follow Up Discussion of Building
Maintenance Code
Items Approved – Unscheduled:
•Discussion with County Assessor
regarding Assessment of Vacation
Rentals
•Future of Human Resources
Management – HR Strategic Plan
•Distributed Energy Discussion
•ADUs and Sue Ballou, Partnership
for Age Friendly Communities
•Reverse Decriminalization of
Municipal Code
Items for Town Board Consideration:
•Vacation Home Cap and
Transferability of Licenses
•Fish Hatchery Next Steps –
February 11, 2020
Future Town Board Study Session Agenda Items
January 14, 2020
13
14