Loading...
HomeMy WebLinkAboutPACKET Public Works, Utilities and Public Safety 2015-09-10 Thursday, September 10, 2015 Public Safety, Utilities 8:00 a.m. & Public Works Committee Town Board Room 1. PUBLIC COMMENT 2. PUBLIC SAFETY a) RECOMMENDATIONS TO THE TOWN BOARD i. None. b) REPORTS i. Verbal Updates and Committee Questions. 3. UTILITIES a) RECOMMENDATIONS TO THE TOWN BOARD i. None. b) REPORTS i. Light & Power Capital Project Change – Glen Haven Delayed Dir. Bergsten & and Allenspark Advanced. Supt. Lockhart ii. Verbal Updates and Committee Questions. 4. PUBLIC WORKS a) RECOMMENDATIONS TO THE TOWN BOARD i. Elm Road Environmental Improvement Plan – Stewart Manager Ash Environmental Consultants Change Order. ii. Dry Gulch Road Improvements – Farnsworth Group Change Manager Ash Order. b) REPORTS i. Verbal Updates and Committee Questions. 5. ADJOURN AGENDA Utilities Department Report To: Public Safety, Utilities & Public Works Committee Town Administrator Lancaster From: Reuben Bergsten, Utilities Director, and Joe Lockhart, Utilities Line Superintendent Date: September 10, 2015 RE: Light & Power Capital Project Change – Glen Haven Delayed and Allenspark Advanced. Objective: To inform the PUP Committee of changes in the start time of capital projects. Present Situation: Power line flood recovery work along County Road 43, which was originally scheduled to be completed this year, has been delayed due to road construction. This capital project, known as Glen Haven Flood Recovery, will be re-scheduled for late 2016. Please see the attached description sheet for this project. The Allenspark 2016 capital construction will be moved to 2015 and completed in 2016 to fill the void left by shifting the power line work on CR43 to late next year. Please see the second description sheet attached for this project. Budget: No action on the 2015 budget is required. The remaining $750,000 funds for Glen Haven will be used for the Allenspark project in 2015. PROJECT INFORMATION Department Utilities AuthorOfApplication J. Lockhart Title_Project Flood Recovery, Glen Haven Location_ofTheProject 7000 block to 10877 of CR43 plus Fox Creek and North Fork roads Justification Flood Recovery Justification_Long Flooding in 2013 obliterated the overhead power along CR 43 just below the switchbacks to 10877 COUNTY ROAD 43 plus the lines along Fox Creek and North Fork roads. We can't reconstruct our line along the road between Dunraven Glade Road and Horseshoe Bend Road. A special use permit from the forest service is required to traverse Triangle Mountain as the alternate route. UsefulLifeYrs 50 PlanningDesignEngineering $75,000 LandPurchase $0 Labor, Materials Equipment $1,500,000 ProjectManagement $0 Legal $0 Contingency (%)10 Other $0 GeneralFund 0 Community Reinvestment 0 OpenSpaceFund 0 Funding_Bonds 0 Federal_GrantOrLoan 0 State_GrantOrLoan 0 Private_GrantOrLoan 0 Other 0 Utilities $0 Maintenance $0 Personnel $0 Equipment $0 ServiceContracts $0 Administrative $0 Other $0 OtherDepartmentsOrEntities: NoneProjectManager:Joe Start 9/23/2013 Estimated Completion 11/15/2016 PROJECT COSTS PROJECT FUNDING (%) Community Participation (yes/No):No Utilities Fund:100 NotesGeneral:As of July 31, 2015 $942,000 has been spent to complete work along North Fork. Work along Fox Creek is 90% complete. A portion of powerline has been rebuilt east of Streamside Dr. Image for Project: FUTURE OPERATIONS & MAINTENANCE COSTS Blank Form to make a New Project Copy this to make a New Project Cat. Of Project:ReplacementCat.OfAsset:Infrastructure Division:Light & Power CostsPrjSubTotal:$1,575,000 TotalCost:$1,732,500 FirstYrCosts:2ndYrCosts:3rdYrCosts:4thYrCosts:5thYrCosts:6thYrCosts:7thYrCosts:8thYrCosts:9thYrCosts:10thYrCosts: This table is for expenditures that will reoccur annually OR multiyear projects. If it will take 7 years, enter estimated annual costs for each of the 7 years. For reoccurring costs enter the total each year. To account for varying cost, funding and/or OM expenes ALSO make an application for each year. Total O&M Costs $0 140 PROJECT INFORMATION Department Utilities AuthorOfApplication J. Lockhart Title_Project Alanspark Circuit (AP2016) Location_ofTheProject Marys Lake substation to Baldpate Justification Underground main line to reduce outages Justification_Long Underground aprox. 20,000 feet of power line close to the substation to address frequent outages due to high winds and trees in difficult terrain. This project includes spare conduit for fiber optics UsefulLifeYrs 60 PlanningDesignEngineering $35,000 LandPurchase $0 Labor, Materials Equipment $1,350,000 ProjectManagement $0 Legal $0 Contingency (%)10 Other $0 GeneralFund 0 Community Reinvestment 0 OpenSpaceFund 0 Funding_Bonds 0 Federal_GrantOrLoan 0 State_GrantOrLoan 0 Private_GrantOrLoan 0 Other 0 Utilities $0 Maintenance $0 Personnel $0 Equipment $0 ServiceContracts $0 Administrative $0 Other $0 OtherDepartmentsOrEntities: CDOT and Larimer CountyProjectManager:J. Lockhart Start 9/14/2015 Estimated Completion 12/12/2016 PROJECT COSTS PROJECT FUNDING (%) Community Participation (yes/No):No Utilities Fund:100 NotesGeneral:Future operations is minimal so the reoccuring cost table is left blank. Image for Project: FUTURE OPERATIONS & MAINTENANCE COSTS Blank Form to make a New Project Copy this to make a New Project Cat. Of Project:ReplacementCat.OfAsset:Infrastructure Division:Light & Power CostsPrjSubTotal:$1,385,000 TotalCost:$1,523,500 FirstYrCosts:2ndYrCosts:3rdYrCosts:4thYrCosts:5thYrCosts:6thYrCosts:7thYrCosts:8thYrCosts:9thYrCosts:10thYrCosts: This table is for expenditures that will reoccur annually OR multiyear projects. If it will take 7 years, enter estimated annual costs for each of the 7 years. For reoccurring costs enter the total each year. To account for varying cost, funding and/or OM expenes ALSO make an application for each year. Total O&M Costs $0 115 ENGINEERING Memo To: Public Safety, Utilities, Public Works Committee (PUP) Town Administrator Lancaster From: Kevin Ash, PE, Public Works Engineering Manager Greg Muhonen, PE, Public Works Director Date: September 10, 2015 RE: Elm Road Environmental Improvement Plan – Stewart Environmental Consultants Change Orders Background: Stewart Environmental Consultants was retained by the Town of Estes Park to provide engineering services related to the Elm Road Landfill as a result of an action letter to the Town issued by the Colorado Department of Public Health and Environment (CDPHE) – October 17, 2011. The Town entered into a contract with Stewart Environmental Consultants on October 22, 2013 to cover services for the engineering of a treatment system that would collect and treat the landfill seepage, explore transfer of the wastewater to the UTSD, and work with CDPHE to correct all issues. After initial meetings with CDPHE, the scope drastically changed and services for survey, drilling and sampling of the subsurface were required. These services were provided under the executed contract (out of scope) and never formalized with a Change Order. The subsurface effort and reporting to the State was performed at a cost of $35,300. Present Situation: Work has progressed under the original contract and subsequent purchase order. The design plans and specifications are now complete. Bidding documents have been provided. Construction is scheduled to begin in October 2015 – with completion in February 2016. To complete these tasks, and meet the requirements delivered by CDPHE, the following Change Orders were needed: 1. Change Order #2 - $22,000. This Change Order accounts for the stormwater design to divert the drainage around the landfill, cross Moraine Avenue, and deliver the runoff to the river. 2. Change Order #3 - $14,500 – Additional plans were requested from the CDPHE that were outside the original scope. These plans included a Materials Management Plan and a Construction Quality Assurance Plan. These plans were requirements for CDPHE to approve the project and give concurrence for the project to go to bid. The original contract had a dollar amount of $134,685.50 and a 10% contingency that brought the project budget total to $148,154. Approval of Change Orders 2 and 3 will add an additional $36,500 to the project budget and a new total of $184,654. Action Recommended by Staff: Public Works has evaluated the scope change and the submitted change orders and determined the services and fees provided were necessary and equitable to the intent of the project with the Town. Staff recommends approval of Change Orders 2 and 3 as presented. Budget: This project will continue to be funded from the Community Reinvestment Fund. The additional $36,500 for design services will come out of the Elm Road Landfill Mitigation line item within that fund. Level of Public Interest Public Interest on this project is expected to be moderate. Sample Committee Recommendation: I recommend the Town Board approve Change Order 2 and Change Order 3 to the professional services contract for design of the Elm Road Environmental Improvement Plan to Stewart Environmental Consultants for an additional project cost not to exceed $36,500. This is to be included as a Consent Item at the September 22, 2015 Town Board Meeting. ENGINEERING Memo To: Public Safety, Utilities, Public Works Committee (PUP) Town Administrator Lancaster From: Kevin Ash, PE, Public Works Engineering Manager Greg Muhonen, PE, Public Works Director Date: September 10, 2015 RE: Dry Gulch Road Improvements – Farnsworth Group Change Order Background: On January 8, 2015, the Town Board approved a design services contract with the Farnsworth Group to provide a design for Dry Gulch Roadway (from Elkhorn Avenue to Stonegate Drive). The original budget for the Dry Gulch project was $1.67 Million. This included $1.37 Million for construction, $200,000 for design and $100,000 for construction management services. The executed contract with Farnsworth for $172,482 included a design for a detached walk in the Sombrero Property to the east. When an easement could not be negotiated, the Town directed the consultant to evaluate options of including a walk along Dry Gulch Road. Several iterations and alternatives were evaluated. On May 12, 2015 at a Town Board Study Session, the most feasible options/costs were presented. The Board authorized staff to proceed with a walk on the west side of Dry Gulch Road at a cost estimated at $2.6 Million. Present Situation: Public Works went out to bid on the Dry Gulch Roadway project in June 2015 and unfortunately received no bids to go to construction. After discussions with contractors on what would create a favorable bidding package, Public Works directed the consultant to make schedule and phasing modifications and re-bid the project. Design efforts to get to this point have resulted in the following change orders from the Farnsworth Group: 1. Change Order #1 - $7946. This Change Order updates the existing bid package. Modifications to the design plans and specs, phasing updates, updates to the bid documents with new completion dates and additional meetings are included. 2. Change Order #2 - $58,434.50. This Change Order accounts for the design of a retaining wall to accommodate a wider roadway section. It includes multiple design iterations to deliver cost effective alternatives to the Dry Gulch Roadway Project. These change orders add $66,380.50 to the design budget. The original design services contract with the Farnsworth Group was $172,482, bringing the total design budget to $238,862.50. This value represents 9.2% of the estimated construction cost and is well within industry standards. The design plans and specifications are complete. Bidding documents have been modified and the project is out to bid for a second time. Action Recommended by Staff: Public Works has evaluated the submitted change order and negotiated a fee for services that is equitable to the Consultant and satisfies the intent of the project scope with the Town. Staff recommends approval of the Change Orders as presented. Budget: This project will be funded from the newly created Street Improvement Fund. The additional $66,380.50 design budget will come out of the Capital line item within that fund. Level of Public Interest Public Interest on this project is expected to be high. This will be the first major project for the voter approved sales tax increase. In addition to the roadway improvements, this project will address trail connections, drainage, wetlands, and utilities. Sample Committee Recommendation: I recommend the Town Board approve Change Order 1 and Change Order 2 to the professional services contract for design of the Dry Gulch Roadway Improvement Project to the Farnsworth Group for a project cost increase not to exceed $66,380.50. This is to be included as a Consent Item at the September 22, 2015 Town Board Meeting.